版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請(qǐng)進(jìn)行舉報(bào)或認(rèn)領(lǐng)
文檔簡(jiǎn)介
1、 engineering standard for start-up sequence and general commissioning procedures 試車程序this standard specification is reviewed and updated by the relevant technical committee on may 2004. the approved modifications are included in the present issue of ips. contents : page no. 0. introduction.2 1. scop
2、e.3 2. references.3 3. definitions and terminology.3 4. symbols and abbreviations.4 5. units.4 6. general requirements.4 7. preparation prior to initial start-up.5 7.1 operational check-out.5 7.2 hydrostatic testing.6 7.3 final inspection of vessels.9 7.4 flushing of lines.9 7.5 instruments.11 7.6 a
3、cid cleaning of compressor lines.12 7.7 breaking-in pumps.12 7.8 breaking-in compressors.13 7.9 dry-out and boil-out.14 7.10 catalyst loading.16 7.11 tightness test.16 8. normal start-up procedures.17 8.1 general.17 8.2 prestart-up check list.18 8.3 make area safe.18 8.4 utilities commissioning.18 8
4、.5 air purging and gas blanketing of non-catalytic sections.18 8.6 catalytic units reactor section air purging and gas blanketing.19 8.7 heat exchanger activation.20 8.8 vacuum test.20 8.9 establish flow in the unit.20 8.10 inhibitor/chemical injections.20 8.11 adjust operation to obtain quality.20
5、appendices :appendix a typical acid cleaning procedure for compressor lines.21appendix b typical heater dry-out procedure.23appendix c typical chemical boil-out sequence.25 0. introduction the standard practice manuals titled as fundamental requirements for the project design and engineering is inte
6、nded for convenience of use and pattern of follow-up and also a guidance. these standard engineering practice manuals also indicate the check points to be considered by the process engineers for assurance of fulfillment of prerequisitions at any stage in the implementation of process plant projects.
7、 it should be noted that these iranian petroleum standards (ips), as practice manuals do not profess to cover all stages involved in every process project, but they reflect the stages that exist in general in process projects of oil, gas and petrochemical industries of iran. these preparation stages
8、 describe the following three main phases which can be distinguished in every project and include, but not be limited to: phase i): basic design stages (containing seven standards). phase ii): detailed design, engineering and procurement stages (containing two standards). phase iii): start-up sequen
9、ce and general commissioning procedures (containing two standards). the process engineering standards of this group include the following 11 standards: standard code standard title i) manuals of phase i (numbers 1-7) ips-e-pr-150 basic design package and recommended practice for feasibility studies
10、ips-e-pr-170 process flow diagram ips-e-pr-190 layout and spacing ips-e-pr-200 basic engineering design data ips-e-pr-230 piping & instrumentation diagrams (p & ids) ips-e-pr-250 performance guarantee ii) manuals of phase ii (numbers 8&9) ips-e-pr-260 detailed design, engineering and procurement ips
11、-e-pr-300 plant technical and equipment manuals (engineering dossiers) ips-e-pr-308 numbering system iii) manuals of phase iii (numbers 10-11) ips-e-pr-280 start-up sequence and general commissioning procedures ips-e-pr-290 plant operating manuals this engineering standard specification covers: 1. s
12、cope this engineering standard specification covers minimum process requirements for plant start-up sequences and general commissioning procedures for non-licensed units or facilities. for licensed units, instructions given by the licenser shall be followed. although, the start-up sequences and comm
13、issioning procedures differ to some extent from process to process, the basic philosophy and general aspects shall conform to the concepts of this standard. however, considering the general commissioning and all activities to be performed prior to initial start-up as outlined in this standard, feed
14、introduction to the unit shall be according to the stepwise start-up procedure provided by the contractor in the unit operating manual. note: this standard specification is reviewed and updated by the relevant technical committee on may 2004. the approved modifications by t.c. were sent to ips users
15、 as amendment no. 1 by circular no. 231 on may 2004. these modifications are included in the present issue of ips. 2. references throughout this standard the following dated and undated standards/codes are referred to. these referenced documents shall, to the extent specified herein, form a part of
16、this standard. for dated references, the edition cited applies. the applicability of changes in dated references that occur after the cited date shall be mutually agreed upon by the company and the vendor. for undated references, the latest edition of the referenced documents (including any suppleme
17、nts and amendments) applies. api (american petroleum institute) api std. 650, welded steel tanks for oil storage, english edition latest edition, asme (american society of mechanical engineers) asme code, section viii ips (iranian petroleum standards) ips-e-gn-100 “engineering standard for units” ip
18、s-c-pi-350 plant piping system pressure testing ips-e-pr-308 numbering system 3. definitions and terminology company or employer/owner refers to one of the related affiliated companies of the petroleum industries of iran such as national iranian oil company (nioc), national iranian gas company (nigc
19、), national petrochemical company (npc), etc., as parts of the ministry of petroleum. contractor refers to the persons, firm or company whose tender has been accepted by the employer, and includes the contractors personnel representative, successors and permitted assignees. licenser or licensor refe
20、rs to a company duly organized and existing under the laws of the said companys country and as referred to in the preamble to the contract. project refers to the equipment, machinery and materials to be procured by the contractor and/or “company” and the works and/or all activities to be performed a
21、nd rendered by the contractor in accordance with the terms and conditions of the contract documents. unit or units refer to one or all process, offsite and/or utility units and facilities as applicable to form a complete operable refinery/ and or plant. 4. symbols and abbreviations symbol/abbreviati
22、on description dn diameter nominal, in (mm). lpg liquefied petroleum gas. nigc national iranian gas company. nioc national iranian oil company. npc national petrochemical company. ogp oil, gas and petrochemical. ppm (by mass) parts per million, in (mg/kg). psv pressure safety/relief valves. ssu sayb
23、olt universal seconds. 5. units this standard is based on international system of units (si) as per ips-e-gn-100, except where otherwise specified. 6. general requirements 6.1 commissioning shall start from the point at which steps are taken to bring the unit/facility up to operating pressure and te
24、mperature and to cut in the feed. it shall be complete when the unit/facility is operating at design capacity and producing products to specification. 6.2 for a project involving a number of process units and offsite facilities, it shall be agreed between the contractor and company in the earliest s
25、tages of a project the sequence of the commissioning of the units. it shall be necessary to commission utilities and some of the units in advance of others, because of their interdependence from a process point of view. 6.3 the responsibilities of the contractor and company during commissioning stag
26、e should be clarified for the provision of labor, operators, specialists and service engineers, and also for the correction of faulty equipment, etc. 6.4 the general requirements outlined in this standard for testing of equipment/lines shall be followed. the detail procedures for testing of equipmen
27、t and lines and other precommissioning steps are not included in this standard and shall be prepared in accordance with the companys engineering standards by the contractor and submitted to the company for approval. however, on completion of testing, vessels, equipment and piping should be vented an
28、d drained, and where necessary cleaned and dried to the satisfaction of the company. spades, blanks and other equipment installed for testing shall be removed on completion of testing. wherever a flange joint is broken after testing, e.g.,on heat exchangers, pipework, fired heaters and at machinery,
29、 then the joint rings or gaskets must be renewed. particular attention must be given to heat exchangers employing solid metal or filled gaskets, and great care should be taken to ensure that all gaskets renewed after testing of heat exchangers and are correctly fitted before tightening flanges. wher
30、e required, valves are to be repacked with the appropriate grade of material. any temporary bolting which has been used shall be replaced and any temporary fittings which may have been installed to limit travel, e.g., in expansion joints and pipe hangers, shall be removed. 6.5 prior to commissioning
31、, each item of equipment should have its name, flowsheet number and identification number painted and/or stamped on it according to the companys specifications. for numbering system reference is made to ips-e-pr-308, numbering system. 7. preparation prior to initial start-up the procedures described
32、 in this section shall be carried out at the completion of construction and before initial operation of the unit. appropriate phases should be repeated after any major repair, alteration, or replacement during subsequent shutdowns. the phases of preparation for initial start-up shall be according to
33、 the following steps: - operational checkout list. - hydrostatic testing. - final inspection of vessels. - flushing of lines. - instruments. - acid cleaning of compressor lines. - breaking in pumps. - breaking in compressors. - dry-out and boil-out. - catalyst loading. - tightness test. 7.1 operatio
34、nal check-out a) check line by line against flowsheet and locate all items. b) identify the location of instruments. c) indicate the location of all critical valves including valves at critical vent and drain locations. d) check control valves, valves, and globe valves to see that they are installed
35、 properly with respect to flow through their respective lines. special attention must be given to check valves regarding their direction of flow. e) review all piping and instrument connections for steam tracing. f) check that the following facilities have been installed so that the plant can be com
36、missioned and put on stream: - start-up bypass lines. - purge connections. - steam-out connections. - drains. - temporary jumpovers. - blinds. - check valves. - filters and strainers. - bleeders. - etc. g) check pumps and compressors for start-up. h) check sewer system for operability. i) check blow
37、down systems. j) check heater for burner installation, refractories, stack damper controls, burner refractories, etc. 7.2 hydrostatic testing 7.2.1 hydrostatic pressure testing of the unit shall be performed to prove strength of the materials and weld integrity after completion of the construction.
38、the tests shall be made on new or repaired equipment and pipings. the initial testing is ordinarily done by the contractor in the course of erection. 7.2.2 detail procedure for testing the equipment and lines shall be prepared by the contractor and submitted to the company for approval. in addition
39、to the specifications outlined herein, the requirements specified in ips-c-pi-350, plant piping system pressure testing shall be strictly followed unless otherwise specified in this standard. 7.2.3 fresh water containing a corrosion inhibitor which meets the companys approval shall be used for hydro
40、static test purpose unless otherwise specified in this standard. in systems where residual moisture can not be tolerated, e.g., in so2, acid, ammonia and lpg service, and where certain catalysts are used, oil is the preferred test medium. if the water has to be used, the system should afterwards be
41、dried out with hot air. special attention should be given to the points where water may be trapped, such as in valve bodies or low points. 7.2.4 if for any reason it is not practical to carry out a hydraulic test, a pneumatic or partially pneumatic test may be substituted subject to prior agreement
42、with the company. full details, including proposed safety precautions, will be required. the following are usually excluded from hydrostatic testing, and are usually tested with compressed air and soap suds: a) instrument air lines (test with dry air only, if possible). b) air lines to air-operated
43、valves (test with dry air only). c) very large (usually over dn 600 or 24 inches) gas or steam overhead lines. d) pressure parts of instruments in gas or vapor service. 7.2.5 when austenitic or austenitic acid clad or lined equipment and piping are tested, the test fluid chloride ion content shall m
44、eet the following conditions: a) if the piping and equipment metal temperature never exceeds 50c during commissioning, operation or nonoperation, water containing up to 30 ppm (by mass) chlorides ion shall be used. the chlorides ion content might be increased up to 150 ppm (by mass) if the equipment
45、 or piping can be thoroughly washed out using water containing less than 30 ppm (by mass) chlorides ion as soon as testing is complete if allowed by the company. in any case, the water must be drained and the equipment thoroughly dried immediately thereafter. b) if the piping and equipment metal tem
46、perature exceeds 50c during commissioning, operation or nonoperation, the piping shall be tested using condensate water, demineralized water or oil with minimum flash point of 50c. 7.2.6 the testing medium should not adversely affect the material of the equipment or any process fluid for which the s
47、ystem has been designed. reference should be made to the applicable codes in the case of pressure vessels to determine the minimum ambient and fluid temperatures at which testing may be carried out. if it is desired to test vessels, tanks or piping at temperatures below 16c, attention shall be made
48、to the danger of brittle fracture occurring in carbon steels and ferritic alloy steels unless the materials have adequate notch ductility properties. for any equipment or piping, water should not be used for testing, when either the water temperature or the ambient temperature is below 5c. hydrostatic testing at temperatures below this value may be carried out usi
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024年定制化客戶合作協(xié)議
- 廠區(qū)園林景觀養(yǎng)護(hù)服務(wù)協(xié)議模板2024
- 2024年度高品質(zhì)鋁單板購(gòu)銷協(xié)議
- 2023-2024學(xué)年浙江省紹興市重點(diǎn)中學(xué)第二學(xué)期高三數(shù)學(xué)試題統(tǒng)練(一)
- 2024年專業(yè)吊車租賃服務(wù)協(xié)議范本
- 2024跨境航空貨物運(yùn)輸協(xié)議范本
- 2024年度高級(jí)店長(zhǎng)任職協(xié)議
- 2024種苗行業(yè)購(gòu)銷協(xié)議樣本
- 城市水溝2024年清理維護(hù)協(xié)議樣式
- 2024年個(gè)人經(jīng)營(yíng)店鋪?zhàn)赓U協(xié)議
- 高考地理復(fù)習(xí):過程類推理綜合題解析-以地貌景觀題為例
- 1+X智能財(cái)稅考證理論考核試題及答案
- 施工圖交接表
- 盤扣支模架工程監(jiān)理細(xì)則
- 教育科研征文
- CT增強(qiáng)檢查及風(fēng)險(xiǎn)知情同意書
- 本科生畢業(yè)論文寫作指導(dǎo)課件
- 第三方支付賬戶管理辦法
- smt首件檢驗(yàn)記錄表
- 旅行社間航班切位協(xié)議書(無補(bǔ)貼)
- GB∕T 22165-2022 堅(jiān)果與籽類食品質(zhì)量通則
評(píng)論
0/150
提交評(píng)論