版權(quán)說(shuō)明:本文檔由用戶(hù)提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請(qǐng)進(jìn)行舉報(bào)或認(rèn)領(lǐng)
文檔簡(jiǎn)介
1、7-1source: pmbok guide 1996 1999 robbins-gioia, inc. pmp preparation training cost management chapter7 7-2source: pmbok guide 1996 1999 robbins-gioia, inc. project cost management resource planning cost estimating cost budgeting cost control processes required to ensure the project is completed with
2、in the approved budget 7-3source: pmbok guide 1996 1999 robbins-gioia, inc. cost management 7.1 resource planning planning 7.3 cost budgeting 7.4 cost control controlling 7.2 cost estimating 7-4source: pmbok guide 1996 1999 robbins-gioia, inc. resource planning determining physical resources needed
3、(i.e., material, equipment, and people) and number of resources required to perform the project activities 7-5source: pmbok guide 1996 1999 robbins-gioia, inc. resource planning inputs scope statement wbs resource pool description organizational policies historical information tools always scheduled
4、 to occur in the future task 1 task 2 task 4 task 5 task 3 work packages planning packages work packages detailed, short-span tasks or material items; required to accomplish the ca objectives; typically for the near term control account elements cost control 7-34source: pmbok guide 1996 1999 robbins
5、-gioia, inc. performance measurement baseline (pmb) the plan against which actual performance can be compared based on budgets assigned to scheduled segments of work build pmb by summing the bcws for all control accounts, by reporting period budget at completion (bac) equal to the cumulative bcws fo
6、r the total project cost control 7-35source: pmbok guide 1996 1999 robbins-gioia, inc. time-phased budget performance measurement baseline (pmb) 0 500 1000 1500 2000 2500 3000 3500 4000 4500 janfebmaraprmayjun reporting period bcws $k bac cost control 7-36source: pmbok guide 1996 1999 robbins-gioia,
7、 inc. work schedule to be accomplished budgeted cost of work scheduled (bcws) performance measurement baseline 0 10000 20000 30000 40000 50000 6000 0 70000 80000 januaryfebruarymarchaprilmayjunejuly current bcws bac cost control bcws january0 february2500 march8000 april13000 may42000 june62000 july
8、70700 7-37source: pmbok guide 1996 1999 robbins-gioia, inc. budgeted value of completed or in-process work performance measurement baseline 0 10000 20000 30000 40000 50000 60000 70000 80000 januaryfebruarymarchaprilmayjunejuly current bcwp bcws bcwsbcwp january00 february25003600 march80008000 april
9、1300010000 may4200038000 june62000 july70700 budgeted cost of work performed (bcwp) cost control 7-38source: pmbok guide 1996 1999 robbins-gioia, inc. actual cost of work performed (acwp) actual value of completed or in-process work performance measurement baseline 0 10000 20000 30000 40000 50000 60
10、000 70000 80000 januaryfebruarymarchaprilmayjunejuly current bcwp bcws acwp cost control bcwsbcwpacwp january000 february250036006000 march800080008000 april13000100008000 may420003800048000 june62000 july70700 7-39source: pmbok guide 1996 1999 robbins-gioia, inc. schedule variance comparing the bcw
11、p, the amount originally budgeted for the work that has been completed or is in-process, to the bcws, the amount budgeted for the work that was planned to have been accomplished sv = bcwp bcws a negative result means less work has been performed than was planned cost control 7-40source: pmbok guide
12、1996 1999 robbins-gioia, inc. sv example bcws = $42,000 bcwp = $38,000 acwp = $48,000 sv = bcwp bcws = $38,000 $42,000 = - $4,000 sv% = sv / bcws =- $4000 / $42,000 = - 0.095 = - 9.5% cost control 7-41source: pmbok guide 1996 1999 robbins-gioia, inc. cost variance comparing the amount originally bud
13、geted for the work completed or in-process, the bcwp, to the actual costs of that work, the acwp cv = bcwp acwp a negative cv means more dollars were spent to accomplish the work than was planned cost control 7-42source: pmbok guide 1996 1999 robbins-gioia, inc. cost variance example bcws = $42,000
14、bcwp = $38,000 acwp = $48,000 cv = bcwp - acwp = $38,000 $48,000 = - $10,000 cv% = cv / bcwp = - $10,000 / $38,000 = - 26% cost control 7-43source: pmbok guide 1996 1999 robbins-gioia, inc. performance indices dfn: cost- and schedule-performance efficiency calculations; expressed in $ cost performan
15、ce index (cpi) cpi = bcwp/acwp schedule performance index (spi) spi = bcwp/bcws cost control 7-44source: pmbok guide 1996 1999 robbins-gioia, inc. cpi example bcws = $42,000 bcwp = $38,000 acwp = $48,000 cpi = bcwp / acwp = $38,000 / $48,000 = 0.79 $0.79 worth of work was actually done for each $1.0
16、0 spent cost control 7-45source: pmbok guide 1996 1999 robbins-gioia, inc. spi example bcws = $42,000 bcwp = $38,000 acwp = $48,000 spi = bcwp / bcws = $38,000 / $42,000 = 0.90 $0.90 worth of work has been done for each $1.00 worth of work that was planned to be done cost control 7-46source: pmbok g
17、uide 1996 1999 robbins-gioia, inc. estimate at completion (eac) dfn: the managements assessment of the cost of the project at completion after variance analysis, the estimated cost at completion is determined cost control 7-47source: pmbok guide 1996 1999 robbins-gioia, inc. eac example one methodol
18、ogy: eac = bac / cpi bac = $80,000 cpi = 0.79 eac = $80,000 / 0.79 = $101,265 cost control 7-48source: pmbok guide 1996 1999 robbins-gioia, inc. variance at completion bac = $80,000 eac = $101,265 vac = bac eac = $80,000 $101,265 = $21,265 based on past performance, project will exceed planned budge
19、t by $21,265 cost control 7-49source: pmbok guide 1996 1999 robbins-gioia, inc. to complete performance index (tcpi) work remaining / cost remaining tcpi = (bac bcwp) / (eac acwp) = ($ 80,000 $ 38,000) / ($ 101,265 $ 48,000) = $ 42,000 / $ 53,265 = 1.4 cost control 7-50source: pmbok guide 1996 1999
20、robbins-gioia, inc. earned value examples bcwsbcwpacwp $1$1$1on scheduleon cost $2$2$1on scheduleunder cost $1$1$2on scheduleover cost $1$2$2ahead of scheduleon cost $1$2$3ahead of scheduleover cost $1$2$1ahead of scheduleunder cost $3$2$1behind scheduleunder cost $2$1$3behind scheduleover cost $2$1
21、$1behind scheduleon cost cost control 7-51source: pmbok guide 1996 1999 robbins-gioia, inc. example bcwsbcwp acwpeac bac 100125 75600 560 125100 100850 800 75 75 75700560 100 75 100570 600 cost control 7-52source: pmbok guide 1996 1999 robbins-gioia, inc. sample cost problem bac = $ 40k bcwp = $ 20k
22、 bcws = $ 28k acwp = $ 26k calculate % of work scheduled % of budget spent % of work accomplished cost variance schedule variance cost control 7-53source: pmbok guide 1996 1999 robbins-gioia, inc. sample solution calculate % of work scheduledbcws / bac = $ 28k / $ 40k = 70 % % of budget spentacwp /
23、bac = $ 26k / $ 40k = 65 % % of work accomplished bcwp / bac = $ 20k / $ 40k = 50 % cost variancebcwp acwp = $ 20k $ 26k = - $ 6k schedule variance bcwp bcws = $ 20k $ 28k = - $ 8k cost control 7-54source: pmbok guide 1996 1999 robbins-gioia, inc. summary review questions 7-55source: pmbok guide 199
24、6 1999 robbins-gioia, inc. case 1 bcws = $ 1,860 bcwp = $ 1,860 acwp = $ 1,860 this is the ideal situation, where everything goes according to plan. 7-56source: pmbok guide 1996 1999 robbins-gioia, inc. case 2 bcws = $ 1,900 acwp = $ 1,700 in this case, without earned value measurements, it appears
25、were in good shape. expenditures are less than planned. spending variance = - $ 200 7-57source: pmbok guide 1996 1999 robbins-gioia, inc. case 2 bcws = $ 1,900 bcwp = $ 1,500 acwp = $ 1,700 but with ev measurements, we see.$400 worth of work is behind schedule in being completed; i.e., we are 21 per
26、cent behind where we planned to be. sv = bcwp bcws = - $ 400 sv % = sv / bcws x 100 = - 21 % 7-58source: pmbok guide 1996 1999 robbins-gioia, inc. case 2 bcws = $ 1,900 bcwp = $ 1,500 acwp = $ 1,700 in addition, we can see. “actuals” exceed “value earned” (bcwp), i.e., $1,500 worth of work was accom
27、plished but it cost $1,700 to do so. we have a $200 cost overrun (i.e., 13% over budget) . cv = bcwp acwp = - $ 200 cv % = cv / bcwp x 100 = - 13 % 7-59source: pmbok guide 1996 1999 robbins-gioia, inc. case 2 bcws = $ 1,900 bcwp = $ 1,500 acwp = $ 1,700 this means only 79 cents worth of work was don
28、e for each $1.00 worth of work planned to be done. and, only 88 cents worth of work was actually done for each $1.00 spent spi = bcwp / bcws = $ 0.79 cpi = bcwp / acwp = $ 0.88 7-60source: pmbok guide 1996 1999 robbins-gioia, inc. case 2 bcws = $ 1,900 bcwp = $ 1,500 acwp = $ 1,700 this is the worst
29、 kind of scenario, where all performance indicators are negative. sv = - $ 400; spi = 0.79 cv = - $ 200; cpi = 0.88 7-61source: pmbok guide 1996 1999 robbins-gioia, inc. bcws = $ 2,600 bcwp = $ 2,400 acwp = $ 2,200 in this case there is bad news and good news. case 3 7-62source: pmbok guide 1996 199
30、9 robbins-gioia, inc. bcws = $ 2,600 bcwp = $ 2,400 acwp = $ 2,200 the bad news is that our work efficiency is a bit low; were getting only 92 cents of work done on the dollar. as a result, we are behind schedule. spi = 0.92 sv = - $ 200; sv % = - 8 % case 3 7-63source: pmbok guide 1996 1999 robbins
31、-gioia, inc. bcws = $ 2,600 bcwp = $ 2,400 acwp = $ 2,200 the good news is that were under-running our budget. were getting $1.09 worth of work done for each $1.00 were spending. cv = + $ 200; cv % = + 8 % cpi = 1.09 case 3 7-64source: pmbok guide 1996 1999 robbins-gioia, inc. case 4 bcws = $ 1,700
32、bcwp = $ 1,500 acwp = $ 1,500 in this case, the work is not being accomplished on schedule. sv = - $ 200; sv % = - 12 % spi = 0.88 7-65source: pmbok guide 1996 1999 robbins-gioia, inc. case 4 bcws = $ 1,700 bcwp = $ 1,500 acwp = $ 1,500 .but the cost of the work accomplished is just as we budgeted.
33、cv = $ 0.00 cpi = 1.00 7-66source: pmbok guide 1996 1999 robbins-gioia, inc. case 5 bcws = $ 1,400 bcwp = $ 1,600 acwp = $ 1,400 a positive scenario; right? but is it because we are out-performing our learning-curve standards or because we planned too pessimistically? 7-67source: pmbok guide 1996 19
34、99 robbins-gioia, inc. case 5 bcws = $ 1,400 bcwp = $ 1,600 acwp = $ 1,400 here in this case, we are getting work done at 114 percent efficiency. spi = 1.14 cpi = 1.14 7-68source: pmbok guide 1996 1999 robbins-gioia, inc. case 5 bcws = $ 1,400 bcwp = $ 1,600 acwp = $ 1,400 .work is ahead of schedule
35、 by 14 percent and under-running cost by 12.5%. sv = + $ 200; sv % = + 14 % cv = + $ 200; cv % = + 12.5 % 7-69source: pmbok guide 1996 1999 robbins-gioia, inc. case 6 bcws = $ 2,000 bcwp = $ 2,200 acwp = $ 2,400 in case 6, work is being done efficiently, but a cost overrun is occurring. spi = 1.10 c
36、v = - $ 200; cv % = - 9 % 7-70source: pmbok guide 1996 1999 robbins-gioia, inc. case 7 bcws = $ 2,200 bcwp = $ 2,400 acwp = $ 2,400 in case 7, work is being done efficiently, and costs are right on target. spi = 1.09 cv = $ 0.00 7-71source: pmbok guide 1996 1999 robbins-gioia, inc. case 8 bcws = $ 2
37、,000 bcwp = $ 2,000 acwp = $ 2,200 see if you can analyze this one! sv = bcwp bcws sv % = sv / bcws cv = bcwp acwp cv % = cv / bcwp spi = bcwp / bcws cpi = bcwp / acwp 7-72source: pmbok guide 1996 1999 robbins-gioia, inc. case 8 bcws = $ 2,000 bcwp = $ 2,000 acwp = $ 2,200 were on schedule. but in o
38、rder to be on schedule, its costing us $1.00 to do each 91-cents worth of work. theres a $200 overrun as a result. sv = $ 0.00 cv = - $ 200; cpi = 0.91 7-73source: pmbok guide 1996 1999 robbins-gioia, inc. case 9 bcws = $ 1,700 bcwp = $ 1,500 acwp = $ 1,900 ok, see how you do with this one! sv = bcwp bcws sv % = sv / bcws cv = bcwp acwp cv % = cv / bcwp spi = bcwp / bcws cpi = bcwp / acwp 7-74source: pmbok guide 1
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 福建省南平市武夷山第三中學(xué)高三化學(xué)下學(xué)期期末試卷含解析
- 福建省南平市吳屯中學(xué)2021-2022學(xué)年高三化學(xué)聯(lián)考試卷含解析
- 5 周?chē)娜斯な澜?說(shuō)課稿-2024-2025學(xué)年科學(xué)二年級(jí)上冊(cè)冀人版
- 2024深圳對(duì)外貿(mào)易貨物進(jìn)口貨物保險(xiǎn)合同3篇
- 2024汽車(chē)停車(chē)場(chǎng)管理三方租賃合同樣本
- 2024張家港新材料研發(fā)基地共建合同
- 暫估價(jià)設(shè)置及財(cái)政評(píng)審的要求和注意事項(xiàng)
- 外賣(mài)員合同范本(2篇)
- 大學(xué)生三方協(xié)議書(shū)(2篇)
- 2024年銷(xiāo)售折扣與信用政策3篇
- 浙江省溫州市溫州中學(xué)2025屆數(shù)學(xué)高二上期末綜合測(cè)試試題含解析
- 2024河南鄭州市金水區(qū)事業(yè)單位招聘45人歷年高頻難、易錯(cuò)點(diǎn)500題模擬試題附帶答案詳解
- GB/T 15843.2-2024網(wǎng)絡(luò)安全技術(shù)實(shí)體鑒別第2部分:采用鑒別式加密的機(jī)制
- 食物損失和浪費(fèi)控制程序
- 完整版:美制螺紋尺寸對(duì)照表(牙數(shù)、牙高、螺距、小徑、中徑外徑、鉆孔)
- 2024年黑龍江齊齊哈爾中考英語(yǔ)試題及答案1
- TCI 373-2024 中老年人免散瞳眼底疾病篩查規(guī)范
- 2024四川太陽(yáng)能輻射量數(shù)據(jù)
- 西南師大版五年級(jí)上冊(cè)小數(shù)乘除法豎式計(jì)算題200道及答案
- 石油鉆采專(zhuān)用設(shè)備制造考核試卷
- 法人變更股權(quán)轉(zhuǎn)讓協(xié)議書(shū)(2024版)
評(píng)論
0/150
提交評(píng)論