1#標(biāo)段房建項目
基坑二次開挖
基坑工程專項施工方案
(格式最終版)
編制人:
審核人:
審批人:
建設(shè)單位:
監(jiān)理單位:
施工單位:
編制日期:2023年7月4日
目錄
第1章工程概況.......................................................................................................................1
1.1工程位置及周邊環(huán)境................................................................................................1
1.1.1工程規(guī)模...........................................................................................................2
1.1.2周邊建筑物及地下管線情況...........................................................................2
1.2基坑支護情況概況....................................................................................................2
1.2.1基坑區(qū)域劃分、開挖深度...............................................................................2
1.2.2基坑支護剖面形式...........................................................................................2
1.3工程地質(zhì)情況............................................................................................................5
1.3.107塊塊工程地質(zhì)情況.......................................................................................5
1.3.209塊塊工程地質(zhì)情況.......................................................................................6
1.4水文地質(zhì)概況............................................................................................................7
1.4.107塊塊水文地質(zhì)概況.......................................................................................7
1.4.209塊塊水文地質(zhì)概況.......................................................................................8
1.5工程地質(zhì)、水文地質(zhì)剖面圖....................................................................................9
1.6周邊使用條件概況..................................................................................................11
1.6.1工程周邊使用情況.........................................................................................11
1.6.2施工場地硬化.................................................................................................11
1.6.3地面排水設(shè)施.................................................................................................12
1.7場地布置原則及劃分..............................................................................................12
1.7.1布置原則及依據(jù).............................................................................................12
1.7.2施工場地布置劃分.........................................................................................12
第2章編制依據(jù).....................................................................................................................14
2.1設(shè)計、勘察文件......................................................................................................14
2.2相關(guān)法律、條例、規(guī)定..........................................................................................14
2.3現(xiàn)行相關(guān)規(guī)范、規(guī)程、標(biāo)準(zhǔn)..................................................................................15
第3章施工計劃.....................................................................................................................16
3.1總體施工部署..........................................................................................................16
3.1.1施工總體目標(biāo).................................................................................................16
3.1.2場地布置原則及劃分.....................................................................................16
3.2總體施工流程..........................................................................................................18
3.3施工資源配置..........................................................................................................19
3.3.1勞動力配置計劃.............................................................................................19
3.3.2主要施工機械配置計劃.................................................................................20
3.3.3材料進場計劃.................................................................................................21
第4章施工工藝技術(shù).............................................................................................................22
4.1土釘墻施工工藝......................................................................................................22
4.1.1材料準(zhǔn)備.........................................................................................................22
4.1.2機具準(zhǔn)備.........................................................................................................22
4.1.3其他準(zhǔn)備.........................................................................................................22
4.1.4施工工藝流程.................................................................................................22
4.1.5施工方法及操作要點.....................................................................................22
4.1.6施工檢測.........................................................................................................26
4.1.7質(zhì)量要求.........................................................................................................27
4.2預(yù)應(yīng)力錨索施工工藝..............................................................................................27
4.2.1材料準(zhǔn)備.........................................................................................................27
4.2.2機具準(zhǔn)備.........................................................................................................28
4.2.3其他準(zhǔn)備.........................................................................................................28
4.2.4工藝流程.........................................................................................................28
4.2.5施工方法及操作要點.....................................................................................28
4.2.6施工檢測.........................................................................................................31
4.3鋼管樁施工工藝......................................................................................................31
4.3.1工藝流程.........................................................................................................31
4.3.2技術(shù)要求.........................................................................................................31
4.4冠梁施工工藝..........................................................................................................32
4.4.1冠梁施工流程.................................................................................................33
4.4.2鋼筋加工及安裝.............................................................................................33
4.4.3模板安裝.........................................................................................................34
4.4.4澆注砼.............................................................................................................34
4.4.5拆模及養(yǎng)護.....................................................................................................34
4.5止水帷幕施工工藝..................................................................................................34
4.5.1材料準(zhǔn)備.........................................................................................................34
4.5.2機具準(zhǔn)備.........................................................................................................34
4.5.3其他準(zhǔn)備.........................................................................................................34
4.5.4施工工藝流程.................................................................................................35
4.5.5高壓旋噴樁施工方法及操作要點.................................................................35
4.5.6特殊情況處理措施.........................................................................................36
4.6疏干井施工工藝......................................................................................................37
4.6.1施工流程.........................................................................................................37
4.6.2施工要點.........................................................................................................37
4.7深基坑土方開挖方案..............................................................................................38
4.7.1土方施工前期準(zhǔn)備.........................................................................................38
4.7.2土方施工總體思路.........................................................................................39
4.7.3土方挖運設(shè)計.................................................................................................39
4.7.4土方施工技術(shù)措施..........................................................................................40
4.7.5土方施工的質(zhì)量要求.....................................................................................41
第5章施工安全保證措施.....................................................................................................42
5.1安全管理目標(biāo)..........................................................................................................42
5.2安全管理方針..........................................................................................................42
5.2.1安全施工重點分析.........................................................................................42
5.2.2安全組織保證體系.........................................................................................44
5.2.3安全管理制度.................................................................................................44
5.2.4技術(shù)保障措施.................................................................................................53
5.2.5消防安全措施.................................................................................................54
5.3監(jiān)測監(jiān)控措施..........................................................................................................55
5.3.1監(jiān)測目的.........................................................................................................55
5.3.2監(jiān)測原則.........................................................................................................55
5.3.3監(jiān)測項目及頻率.............................................................................................56
5.3.4實施方法.........................................................................................................58
5.3.5測點布置.........................................................................................................59
5.3.6監(jiān)測管理體系.................................................................................................63
5.3.7施工監(jiān)測反饋程序.........................................................................................63
5.3.8監(jiān)測過程要求.................................................................................................64
5.3.9應(yīng)急方案.........................................................................................................64
第6章施工管理及作業(yè)人員配備和分工.............................................................................65
6.1主要管理人員配置..................................................................................................65
6.2項目組織機構(gòu)..........................................................................................................65
6.3項目主要管理人員一覽表......................................................................................65
6.4崗位職責(zé)劃分..........................................................................................................66
6.5勞動力配置計劃......................................................................................................67
6.5.1勞動力組織方案.............................................................................................67
6.5.2勞動力投入計劃.............................................................................................68
第7章驗收要求.....................................................................................................................70
7.1驗收程序..................................................................................................................70
7.2驗收相關(guān)標(biāo)準(zhǔn)..........................................................................................................70
7.3驗收時應(yīng)具備的文件..............................................................................................71
第8章應(yīng)急處置措施.............................................................................................................72
8.1應(yīng)急策劃..................................................................................................................72
8.1.1應(yīng)急預(yù)案工作流程.........................................................................................72
8.1.2突發(fā)事件風(fēng)險分析和預(yù)防.............................................................................72
8.1.3應(yīng)急資源分析.................................................................................................72
8.1.4法律法規(guī)要求.................................................................................................73
8.2應(yīng)急準(zhǔn)備..................................................................................................................73
8.2.1機構(gòu)與職責(zé).....................................................................................................73
8.2.2應(yīng)急資源.........................................................................................................76
8.2.3教育、訓(xùn)練.....................................................................................................76
8.2.4互相協(xié)議.........................................................................................................76
8.3預(yù)案啟動前提..........................................................................................................76
8.4基坑變形應(yīng)急預(yù)案..................................................................................................76
8.4.1二級應(yīng)急措施.................................................................................................76
8.4.2一級應(yīng)急措施.................................................................................................77
8.5應(yīng)急響應(yīng)..................................................................................................................77
8.6基坑突發(fā)事故應(yīng)急救援預(yù)案..................................................................................78
8.7機械事故應(yīng)急救援預(yù)案..........................................................................................79
8.8電擊傷害應(yīng)急救援預(yù)案..........................................................................................80
8.9高空墜落應(yīng)急救援預(yù)案..........................................................................................81
8.10急救路線................................................................................................................81
第九章計算書及相關(guān)施工圖紙...............................................................................................83
第1章工程概況
1.1工程位置及周邊環(huán)境
擬建延慶區(qū)南辛堡村、民主村、百眼泉村棚戶區(qū)改造項目YQ00-0007-0018地塊項
目,位于北京市延慶區(qū)媯水河南,07街區(qū)地塊邊界:東至匯川街,西至07街區(qū)規(guī)劃邊
界,北至南辛堡街,南至知榮街,本工程主要包含YQ00-0007-0018地塊獨立承臺基坑
及0021地塊東側(cè)商業(yè)住宅樓基坑,09地塊開閉站基坑位于0038地塊基坑西南角30米
左右,基坑開挖最大深度為9.0m;
本工程位置如下:
1
1.1.1工程規(guī)模
本工程建設(shè)用地面積145967平方米(07地塊92474.74m2,09地塊53492m2),總
建筑面積452440平方米(07地塊278623m2,09地塊173816.21m2),其中地上建筑面
積275193平方米(07地塊168209m2,09地塊106984m2),地下建筑面積177247平方
米(07地塊110414.07m2,09地塊66832.21m2)。
1.1.2周邊建筑物及地下管線情況
本項目各地塊主樓施工已基本完成等,現(xiàn)開挖基坑位于0018地塊7-28#樓南側(cè)、7-
22#樓北側(cè)及0021地塊東側(cè)商業(yè)樓,09地塊開閉站基坑位于0038地塊西南角,距0038
地塊原基坑30米左右,基坑內(nèi)原預(yù)留管線均已移除,開挖作業(yè)面內(nèi)無管線。
1.2基坑支護情況概況
基坑支護采用預(yù)應(yīng)力錨索復(fù)合土釘墻支護、預(yù)應(yīng)力錨索、微型樁復(fù)合土釘墻支護、
土釘墻支護等多種支護形式,安全等級為二級,基坑使用年限為1年。
1.2.1基坑區(qū)域劃分、開挖深度
7-28#樓南側(cè)獨立承臺基坑開挖深度為8.3m(3-3剖面),7-22#樓北側(cè)獨立承臺基
坑開挖深度為5.5~8.3m(1-1、2-2、3-3剖面),0021地塊東側(cè)商業(yè)樓基坑開挖深度約
3.05m(5-5剖面),09地塊開閉站開挖深度9.0m(4-4剖面)。
1.2.2基坑支護剖面形式
本工程采用預(yù)應(yīng)力錨索復(fù)合土釘墻支護、微型樁復(fù)合土釘墻支護、土釘墻支護等
多種支護形式,根據(jù)基坑深度不同,分為5個剖面。
1-1剖面:基坑深度5.5m,復(fù)合土釘墻面板厚100,1:0.4放坡,兩道注漿土釘
(第一、二道主筋?22;L=9000m;φ150@1200),一道預(yù)應(yīng)力錨索(主筋2sφ15.2低
松弛鋼絞線;L=16500,其中自由段長5500,錨固段長11000;φ150@1500),鋼腰梁
(雙20a槽鋼)。
2
2-2剖面:基坑深度7.2m,復(fù)合土釘墻面板厚100,1:0.4放坡,三道注漿土釘
(主筋?22;L=9000m;φ150@1200),一道預(yù)應(yīng)力錨索(主筋2sφ15.2低松弛鋼絞
線;L=16500,其中自由段長5500,錨固段長11000;φ150@1500),鋼腰梁(雙20a
槽鋼),微型樁φ150@500注漿鋼管樁,長度L=9000。
3
3-3剖面:基坑深度8.3m,復(fù)合土釘墻面板厚100,1:0.4放坡,三道注漿土釘
(第一、二、三道主筋?22;L=12000;φ150@1200),兩道預(yù)應(yīng)力錨索(第一道主筋2s
φ15.2低松弛鋼絞線;L=16500,其中自由段長5500,錨固段長11000;φ150@1500,
第二道主筋2sφ15.2低松弛鋼絞線;L=18000,其中自由段長6500,錨固段長12000;
φ150@1500),兩道鋼腰梁(雙20a槽鋼),微型樁φ150@500注漿鋼管樁,長度
L=12000。
4-4剖面:基坑深度9.0m,復(fù)合土釘墻面板厚100,1:0.4放坡,三道注漿土釘
(第一、二、三道主筋?22;L=12000;φ150@1200),兩道預(yù)應(yīng)力錨索(第一道主筋2s
φ15.2低松弛鋼絞線;L=16500,其中自由段長5500,錨固段長11000;φ150@1500,
第二道主筋2sφ15.2低松弛鋼絞線;L=18000,其中自由段長6500,錨固段長12000;
φ150@1500),兩道鋼腰梁(雙20a槽鋼),微型樁φ150@500注漿鋼管樁,長度
L=12000。
4
5-5剖面:基坑深度3.05m,采用1:0.6簡易支護形式,面板厚50mm,內(nèi)襯
30*50*2mm鋼板網(wǎng)。
1.3工程地質(zhì)情況
1.3.107塊塊工程地質(zhì)情況
根據(jù)中材地質(zhì)工程勘查研究院有限公司提供的07地塊巖土工程勘察資料,07塊塊
擬建場區(qū)40.0米勘察深度范圍內(nèi)的土層劃分為人工堆積層和一般第四紀(jì)沉積層,并按地
層巖性和物理力學(xué)性質(zhì)指標(biāo),進一步劃分為8層,現(xiàn)按照自上而下的順序?qū)Ω魍翆拥幕?/p>
本特征綜述如下:
人工堆積層
①填土層:以雜填土和粉質(zhì)黏土素填土為主,雜色、黃褐色,稍濕,松散,強度極
5
不均勻,含磚塊、碎石、灰渣、建筑垃圾和生活垃圾等;厚度一般為0.6~3.6米,平均
厚度1.65米;局部(79#、82#、84#附近)較厚,厚約5.0米。
一般第四紀(jì)沉積層
②粉質(zhì)黏土、重粉質(zhì)黏土層:褐黃色,很濕,可塑~軟塑;含少量云母、氧化鐵;
局部夾②1層黏質(zhì)粉土、砂質(zhì)粉土和②2層黏土;厚度一般為1.5~7.9米,平均厚度4.95
米。
③粉質(zhì)黏土、重粉質(zhì)黏土層:灰色,很濕,硬塑~可塑;含云母、有機質(zhì);局部夾
③1層黏質(zhì)粉土、砂質(zhì)粉土和③2層黏土;厚度一般為2.2~9.3米,平均厚度5.85米。
④黏質(zhì)粉土、砂質(zhì)粉土層:黃褐色、灰褐色,密實,稍濕~濕;含云母、氧化鐵、
有機質(zhì);局部夾④1層粉質(zhì)黏土、重粉質(zhì)黏土和④2層粉砂;厚度一般為1.2~8.8米,平
均厚度3.73米。
⑤黏土層:灰色、青灰色,很濕,可塑;含云母、有機質(zhì);局部夾⑤1層重粉質(zhì)黏
土、粉質(zhì)黏土和⑤2層黏質(zhì)粉土、砂質(zhì)粉土;厚度一般為1.2~6.6米,平均厚度3.98米。
⑥粉質(zhì)黏土、重粉質(zhì)黏土層:褐黃色,很濕,可塑;含云母、氧化鐵;局部夾⑥1
黏質(zhì)粉土、砂質(zhì)粉土和⑥2黏土;厚度一般為0.8~6.0米,平均厚度3.12米。
⑦卵礫石層:以卵石、圓礫為主,雜色,密實,濕,骨架顆粒粒徑一般為
10~30mm,最大粒徑80mm左右,亞圓形,磨圓度中等,含量60%~70%左右;骨架孔
隙全部被充填,充填物主要為中粗砂、礫砂,含量30%~40%左右,級配較好;局部夾
薄層⑦1層粉細砂、⑦2層粉質(zhì)黏土、重粉質(zhì)黏土和⑦3層黏土。厚度一般為0.3~6.4米,
平均厚度3.25米。
⑧黏土、重粉質(zhì)黏土層:灰色、青灰色、黑灰色,很濕,硬塑~可塑;含云母、有
機質(zhì);局部夾⑧1層粉質(zhì)黏土和⑧2層黏質(zhì)粉土、砂質(zhì)粉土;本次詳細勘察40.0米深度范
圍內(nèi)未鉆穿該層,最大揭露厚度為14.3米。
1.3.209塊塊工程地質(zhì)情況
根據(jù)中國兵器工業(yè)北方勘察設(shè)計研究院有限公司提供的09地塊巖土工程勘察資料,
勘察地面以下41.00m范圍內(nèi)揭露的地層可劃分為人工填土層和第四紀(jì)沉積層兩大類。
根據(jù)地層巖性和工程性質(zhì)指標(biāo)各土層根據(jù)其性質(zhì)不同,又可進一步劃分下表所述地層:
地基土工程性質(zhì)分析如下:
(1)人工填土層:
雜填土①層:雜色,稍濕,稍密,以建筑垃圾、磚渣等為主,含少許粘性土、粉
土。厚度0.8~2.6m只在部分鉆孔揭露。
素填土①1層:黃褐色,稍濕,稍密,以砂質(zhì)粉土主。厚度0.50~3.00m。
(2)第四系沉積層:
6
砂質(zhì)粉土-粘質(zhì)粉土②層:褐黃-黃褐,濕-飽和,稍密-中實,含云母、氧化鐵、有
機質(zhì)等,局部為有機質(zhì)土,局部夾粉質(zhì)粘土薄層,層厚2.60~3.50m。
粉質(zhì)粘土②1層:褐黃-黃褐,軟塑-可塑,土質(zhì)不均,含云母有機質(zhì),局部夾粉土薄
層,層厚0.80~4.40m。
細砂②2層:褐黃-黃褐,飽和,中密,砂質(zhì)不純,分選性一般,主要礦物成份為石
英、長石,含圓礫,局部夾粉土薄層。層厚0.80~1.30m,只有部分鉆孔揭露。
粉質(zhì)粘土③層:褐黃-黃褐,軟塑-可塑,含云母、氧化鐵、有機質(zhì),局部為有機
質(zhì)土,局部夾粘質(zhì)粉土、粉砂薄層。厚度0.30-4.60m。
砂質(zhì)粉土-粘質(zhì)粉土③1層:褐黃-黃褐,濕-飽和,稍密-中實,含云母、氧化鐵、
有機質(zhì)等,局部夾粉質(zhì)粘土薄層,層厚0.80~4.70m。
細砂③2層:褐黃-黃褐,飽和,中密,砂質(zhì)不純,分選性一般,主要礦物成份為石
英、長石,含圓礫,局部夾粉土薄層。層厚0.70~3.00m,只有部分鉆孔揭露。
卵石④層:雜色,飽和,密實,最大粒徑100mm,一般粒徑30-50mm,呈亞圓形,
約占總量的35%,級配較好,中砂充填,厚度2.30-8.10m。
中砂④1層:褐黃,飽和,中密-密實,砂質(zhì)不純,分選性一般,主要礦物成份為
石英、長石,局部夾粉土薄層。只有部分鉆孔揭露,層厚0.10~2.80m。
粉質(zhì)粘土④2層:褐黃-黃褐,軟塑-可塑,含云母、氧化鐵、有機質(zhì),只有121#鉆
孔揭露。厚度0.50m。
重粉質(zhì)粘土-粘土⑤層:黃灰-灰色,可塑-硬塑,含少量姜石、氧化鐵、有機質(zhì)
等。厚度3.00-6.00m。
重粉質(zhì)粘土-粘土⑥層:灰-灰綠色,可塑-硬塑,含云母、氧化鐵、有機質(zhì),局部
夾粘質(zhì)粉土、粉砂薄層。厚度3.30-7.60m。
粘土⑦層:靑灰-灰色,可塑-硬塑,含云母、氧化鐵、有機質(zhì),局部夾粘質(zhì)粉
土、粉砂薄層。厚度0.90-12.50m。
細砂⑧層:灰-灰白色,飽和,中密-密室,砂質(zhì)不純,分選性一般,主要礦物成份
為石英、長石,局部夾粉土薄層。層厚0.50~4.00m,未鉆穿。
1.4水文地質(zhì)概況
1.4.107塊塊水文地質(zhì)概況
(1)場區(qū)地下水埋藏條件及變化規(guī)律
擬建場地40米勘察深度范圍內(nèi)共發(fā)現(xiàn)4層地下水:
第一層地下水類型為上層滯水,勘察期間穩(wěn)定水位埋深在自然地面下3.3~4.0m,
勘察時僅在個別鉆孔中觀測到該層地下水,主要為大氣降水、場區(qū)內(nèi)及周邊管道滲漏垂
向補給,以蒸發(fā)方式排泄;該層地下水分布不連續(xù),水位年變化幅度較大。
7
第二層地下水類型為潛水,勘察期間穩(wěn)定水位埋深在自然地面下6.0~7.7米;含水
層為③層及其夾層,主要為大氣降水補給,以蒸發(fā)方式排泄;該層地下水水位年變化幅
度為1~2米左右。
第三層地下水類型為潛水,勘察期間穩(wěn)定水位埋深在自然地面下8.0~12.5米,具
微承壓性;含水層為④層及其夾層,主要為地下側(cè)向徑流補給,以側(cè)向徑流方式排泄;
該層地下水水位年變化幅度不大。
第四層地下水類型為潛水,勘察期間穩(wěn)定水位埋深在自然地面下19.2~22.2米;含
水層為⑦層及其夾層,主要為地下側(cè)向徑流補給,以側(cè)向徑流方式排泄;該層地下水水
位年變化幅度不大。
現(xiàn)場實測各層地下水水位情況及類型參見表1。
表1地下水穩(wěn)定水位量測情況一覽表
層號類型埋深(m)標(biāo)高(m)
一上層滯水3.3~4.0484.48~483.18
二潛水6.0~7.7481.87~479.45
三潛水8.0~12.5479.18~474.94
四潛水19.2~22.2468.23~464.98
(2)場區(qū)歷年最高地下水位和近3~5年最高地下水位
本場區(qū)歷年(1955年以來)最高地下水位為接近自然地面;近3~5年最高地下水位
埋深為自然地面下5.0米左右。
(3)地下水及淺層土的腐蝕性評價
初、詳勘分別于C4#、C12#、C13#、18#、126#、218#和223#鉆孔共采取地下水試
樣16件,進行了水的腐蝕性分析試驗,根據(jù)試驗分析結(jié)果,按照《巖土工程勘察規(guī)范》
GB50021-2001(2009年版)的相關(guān)標(biāo)準(zhǔn)綜合判定:
按Ⅱ類環(huán)境類型考慮,第二層地下水對混凝土結(jié)構(gòu)具中腐蝕性,腐蝕介質(zhì)為侵蝕性
CO2;第一層、第三層和第四層地下水對混凝土結(jié)構(gòu)具微腐蝕性。在長期浸水條件下,
四層地下水對鋼筋混凝土結(jié)構(gòu)中的鋼筋均具微腐蝕性;在干濕交替條件下,第一層和第
四層地下水對鋼筋混凝土結(jié)構(gòu)中的鋼筋具弱腐蝕性,腐蝕介質(zhì)為Cl-,第二層和第三層
地下水對鋼筋混凝土結(jié)構(gòu)中的鋼筋具微腐蝕性。
對混凝土結(jié)構(gòu)中的鋼筋具微腐蝕性。
1.4.209塊塊水文地質(zhì)概況
(1)地下水揭露情況
本次勘察施工期間,41米深度范圍內(nèi)共揭露2層地下水,第一層為潛水,穩(wěn)定水位
8
埋深6.500-7.40米m,高程484.49-485.39m。第二層為承壓水,穩(wěn)定水位埋深13.00-
15.7米m,高程477.490-479.48m。
(2)地下水補給排條件
場區(qū)上層滯水和臺地潛水主要受管線和大氣降水以及上部地層結(jié)構(gòu)影響,變化規(guī)律
較差。
場區(qū)臺地潛水天然動態(tài)類型屬滲入-蒸發(fā)、逕流型,主要接受大氣降水入滲、地下
水側(cè)向逕流及管道滲漏等方式補給,以蒸發(fā)及地下水側(cè)向逕流為主要排泄方式;其水位
年動態(tài)變化規(guī)律一般為:6月份~9月份水位較高,其他月份水位相對較低,水位年變
幅一般為2~3m。
場區(qū)地下潛水天然動態(tài)類型為滲入-蒸發(fā)、逕流型,主要接受大氣降水入滲、側(cè)向
徑流等方式補給,并以蒸發(fā)及徑流方式排泄。該潛水在場區(qū)內(nèi)普遍分布,水位年動態(tài)為
7-10月份水位較高,其它月份相對較低,周年變化幅度一般為2m左右。
(3)工程場區(qū)地下水歷年最高水位
鑒于本工程場區(qū)的水文地質(zhì)條件、地質(zhì)環(huán)境及“北京市區(qū)地下水長期觀測網(wǎng)”等資
料綜合分析,近3~5年最高水位埋深約為2.00m,近3~5年最高水位標(biāo)高約為490.00m
左右,場地歷年最高地下水位標(biāo)高接近自然地面。
(4)地下水、土的腐蝕性
本區(qū)屬暖溫帶半濕潤季風(fēng)氣候,根據(jù)區(qū)域水文地質(zhì)資料,場地環(huán)境類型為Ⅱ類。本
次勘察期間共取得6組地下水(15#鉆孔、19#鉆孔兩組、34#鉆孔、54#鉆孔兩組、106#
鉆孔)進行水質(zhì)簡分析,取土樣兩組(1#鉆孔、135#鉆孔)進行易溶鹽實驗分析。根據(jù)
水質(zhì)簡試驗及易溶鹽試驗報告分析:地下水以上土對混凝土結(jié)構(gòu)具弱腐蝕性,地下水對
混凝土具有微腐蝕性,腐蝕介質(zhì)為Cl-。在長期浸水條件下,地下水對鋼筋混凝土結(jié)構(gòu)
中的鋼筋具微腐蝕性;在干濕交替條件下,地下水對鋼筋混凝土結(jié)構(gòu)中的鋼筋具弱腐蝕,
腐蝕介質(zhì)為Cl-,對混凝土結(jié)構(gòu)中的鋼筋具微腐蝕性。在長期浸水及干濕交替作用下,
對混凝土結(jié)構(gòu)中的鋼筋具微腐蝕性。
1.5工程地質(zhì)、水文地質(zhì)剖面圖
根據(jù)勘察報告,選取07地塊典型的地質(zhì)縱斷面圖,如圖1-3所示;
9
圖1-307地塊典型的地質(zhì)縱斷面圖
10
圖1-409地塊典型的地質(zhì)縱斷面圖
1.6周邊使用條件概況
1.6.1工程周邊使用情況
(1)施工道路
各地塊基坑周邊2m外設(shè)置消防通道。
(2)加工料場
07地塊主體施工已進入收尾階段,基坑支護鋼筋加工場地與主體鋼筋加工棚共用,
噴錨后臺位于18地塊西南角空地,距離開挖基坑20m。
(3)地面超載取值
基坑開挖面2m范圍外附加荷載取值30KPa,使用時,嚴(yán)禁超出設(shè)計取值荷載。
1.6.2施工場地硬化
施工場地全部硬化,并注意開挖上口線向外1m范圍內(nèi)的找坡。
11
1.6.3地面排水設(shè)施
施工場地的排水設(shè)施在施工道路外側(cè),排水盡量遠離基坑。
1.7場地布置原則及劃分
1.7.1布置原則及依據(jù)
施工總平面設(shè)計、布置遵循了如下原則:現(xiàn)場設(shè)施必須滿足政府部門及授權(quán)的相關(guān)
管理部門有關(guān)要求和規(guī)定,同時滿足行業(yè)管理的相關(guān)要求和規(guī)定的原則;有利于施工現(xiàn)
場道路暢通、便于總體施工的原則;便于總體規(guī)劃統(tǒng)一管理的原則;施工聲源、光源、
震源遠離居民區(qū)的原則;同時兼顧了盡可能減少大宗施工材料的二次倒運,材料堆放相
對集中;現(xiàn)場辦公區(qū)與業(yè)主、監(jiān)理、總包單位溝通方便,又相互獨立的原則。
1.7.2施工場地布置劃分
(1)施工總平面具體布置
工地大門口設(shè)置門衛(wèi)室?,F(xiàn)場臨時用電由現(xiàn)場配電柜接出,臨時用水由總接水管接
出,并沿各基坑邊沿埋設(shè),通往各施工作業(yè)面。
在場地大門內(nèi)側(cè)設(shè)洗車池,配備專業(yè)車輪清洗設(shè)備對進出車輛車輪進行清洗,保證
進出車輪不夾泥土。
現(xiàn)場設(shè)置采用集裝箱設(shè)置臨時辦公用房,墻板為巖棉阻燃材質(zhì);臨時用房內(nèi)嚴(yán)禁做
飯,嚴(yán)禁搭設(shè)帳篷;在現(xiàn)場設(shè)置移動廁所,廁所為阻燃型廁所。定期抽排,保持廁所干
凈。
(2)施工用水
本工程施工用水使用由甲方提供的供水管作施工用水,最終位置以供水部門指定位
置為準(zhǔn)。
(3)施工排水
布設(shè)好場地內(nèi)的地表排水擋水系統(tǒng),沿基坑邊臨時圍擋根部設(shè)置300mm×240mm擋
水臺,防止雨水倒灌;頂部適當(dāng)找坡,向遠離基坑的一側(cè)排水。在場地四周基坑上口線
2m范圍外設(shè)環(huán)形截水溝,保證場區(qū)內(nèi)的施工廢水、雨水等順利疏排,排水溝設(shè)置攔污
網(wǎng),并定期進行清理。排水溝的水流入沉淀池,經(jīng)沉淀后,再用水泵抽排入市政下水道。
施工泥漿、渣土等采用專用泥漿運輸車與渣土運輸車運輸外卸至規(guī)定地點排放。
(4)施工用電
根據(jù)業(yè)主提供用電接駁點,設(shè)總動力箱進入配電房,采用三相五線制供電系統(tǒng),施
工點設(shè)分動力箱,各個電箱為全新電箱,并在各個電閘箱處標(biāo)明用途標(biāo)識;分動力箱用
電纜為各負荷供電,坑外各線路盡量靠近圍墻,避免干擾,坑內(nèi)電纜電線采用支架架空
敷設(shè)?,F(xiàn)場采用LED節(jié)能燈作為工地照明,供夜間施工人員上下班行走照明。用電設(shè)
12
備采用專用電箱,各電箱一機一閘。
(5)施工交通運輸
1)場外運輸:利用現(xiàn)狀道路進行施工運輸,進料盡量安排在晚上,以免影響市內(nèi)
交通。土方運輸車輛均采用政府規(guī)定的綠色車輛。
2)場內(nèi)運輸:考慮鋼筋及商業(yè)混凝土罐車的運輸,運輸通道必須有足夠的剛度,
必要時鋪設(shè)渣土碎石或鋼板墊道。
3)行人馬道:臨時馬道采用鋼管刷漆掛密目網(wǎng)鋪設(shè)腳手板搭設(shè)。禁止與土方車共
用一條坡道。
4)土方馬道:土方車下基坑馬道要求做好臨邊防護,并做太陽能障礙燈、掛反光
條,做夜間警示。
13
第2章編制依據(jù)
2.1設(shè)計、勘察文件
本工程依據(jù)的設(shè)計與勘察文件見表2-1:
表2-1設(shè)計與勘察文件
序
名稱提供單位日期
號
延慶區(qū)南辛堡村、民主村、百眼泉村棚戶
中材地質(zhì)工程勘查研究院有限
1區(qū)改造項目YQ00-0007-0021、0018、00212018年4月
公司
地塊安置房建設(shè)項目巖土工程勘察報告
延慶區(qū)南辛堡村、民主村、百眼泉村棚戶
中國兵器工業(yè)北方勘察設(shè)計研
2區(qū)改造項目YQ00-0009-0038、0040地塊安2018年4月
究院有限公司
置房建設(shè)項目巖土工程勘察報告
延慶區(qū)南辛堡村、民主村、百眼泉村棚戶中土大地國際建筑設(shè)計有限公
32020年9月
區(qū)改造項目二次開挖基坑支護工程設(shè)計圖司
2.2相關(guān)法律、條例、規(guī)定
本工程依據(jù)的相關(guān)法律、條例和規(guī)定見表2-2;
表2-2相關(guān)法律、條例和規(guī)定
類別名稱編號
中華人民共和國建筑法中華人民共和國主席令(第91號)
中華人民共和國安全生產(chǎn)法中華人民共和國主席令(第70號)
中華人民共和國環(huán)境保護法中華人民共和國主席令(第9號)
國家中華人民共和國環(huán)境噪聲污染防治法中華人民共和國主席令(第77號)
2007年6月29日第十屆全國人民代表
中華人民共和國勞動法
大會常務(wù)委員會第二十八次會議通過
建設(shè)工程質(zhì)量管理條例中華人民共和國國務(wù)院令第279號
建設(shè)工程安全生產(chǎn)管理條例中華人民共和國國務(wù)院令第393號
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實施《危險性較
大的分部分項工程安全管理規(guī)定》有關(guān)問題建辦質(zhì)〔2018〕31號
部委的通知
危險性較大的分部分項工程安全管理規(guī)定住建部37號令
地方北京市建設(shè)工程施工現(xiàn)場管理辦法政府令第72號
14
北京市危險性較大的分部分項工程安全專
項施工方案專家論證細則(2015版)
北京市人民政府關(guān)于修改《北京市人民政府
北京市人民政府令第115號
關(guān)于加強垃圾渣土管理的規(guī)定》的決定
關(guān)于頒發(fā)《北京市建設(shè)工程施工現(xiàn)場環(huán)境保
京建施[2003]3號
護標(biāo)準(zhǔn)》的通知
關(guān)于在全市建設(shè)工程推行綠色施工的通知京建施[2008]651號
2.3現(xiàn)行相關(guān)規(guī)范、規(guī)程、標(biāo)準(zhǔn)
本工程依據(jù)的現(xiàn)行規(guī)范、規(guī)程和標(biāo)準(zhǔn)如表2-3;
表2-3現(xiàn)行相關(guān)規(guī)范、規(guī)程和標(biāo)準(zhǔn)
類別名稱編號
建筑地基與基礎(chǔ)工程施工質(zhì)量驗收標(biāo)準(zhǔn)GB50202-2018
混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范GB50204-2015
錨桿噴射混凝土支護技術(shù)規(guī)范GB50086-2015
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024政工程合同協(xié)議書:新能源項目合作協(xié)議3篇
- 2024建筑水電安裝系統(tǒng)檢測與維護合同
- 2024消防工程維保與消防系統(tǒng)智能化改造服務(wù)協(xié)議3篇
- 專業(yè)消防站施工建設(shè)協(xié)議樣本版A版
- 2024版專業(yè)土方外運工程承包合同范本版B版
- 2024氣象站氣象儀器設(shè)備采購與維護服務(wù)協(xié)議3篇
- 2024靈活就業(yè)人員的勞動合同
- 專業(yè)液體化工品運輸協(xié)議2024定制版版B版
- 個人房產(chǎn)轉(zhuǎn)讓協(xié)議范本2024版版B版
- 企業(yè)員工培訓(xùn)之喚醒正能量培訓(xùn)
- 2024年天津市中考歷史試卷真題(含答案逐題解析)
- DL∕T 681.1-2019 燃煤電廠磨煤機耐磨件技術(shù)條件 第1部分:球磨機磨球和襯板(代替DLT 681-2012)
- AQ/T 1121-2023 煤礦安全現(xiàn)狀評價實施細則(正式版)
- 四川省成都市青白江區(qū)2023-2024學(xué)年八年級下學(xué)期期末數(shù)學(xué)試題(含答案詳解)
- 骨科中醫(yī)護理方案培訓(xùn)計劃(2篇)
- 2024年美國X射線熒光光譜儀(XRF)市場現(xiàn)狀及上下游分析報告
- Other-the-other-others-another等習(xí)題辨析(附答案+解析)
- DZ∕T 0289-2015 區(qū)域生態(tài)地球化學(xué)評價規(guī)范(正式版)
- 2024年江蘇農(nóng)牧科技職業(yè)學(xué)院單招職業(yè)適應(yīng)性測試題庫必考題
- 食品機械與設(shè)備智慧樹知到期末考試答案章節(jié)答案2024年西北農(nóng)林科技大學(xué)
- DB32T 4400-2022《飲用水次氯酸鈉消毒技術(shù)規(guī)程》
評論
0/150
提交評論