新世界增城綜合發(fā)展項(xiàng)目B標(biāo)段總承包工程
施工電梯安拆方案
(B類(lèi)方案)
編制單位:中國(guó)建筑第八工程局有限公司
日期:2023年11月
目錄
第一章編制依據(jù)..............................................................................................................................................4
第二章工程概況..............................................................................................................................................5
2.1工程建設(shè)概況.......................................................................................................................................5
2.2設(shè)計(jì)概況................................................................................................................................................5
2.3施工條件.............................................................................................................................................7
第三章施工安排..............................................................................................................................................7
3.1項(xiàng)目人員配置及職責(zé).........................................................................................................................7
3.2項(xiàng)目管理目標(biāo).....................................................................................................................................7
3.3各項(xiàng)資源供應(yīng)方式.............................................................................................................................8
3.3.1勞務(wù)資源安排一覽表..............................................................................................................8
3.3.2工程用大宗物資供應(yīng)安排一覽表..........................................................................................8
3.3.3大型機(jī)械設(shè)備采購(gòu)供應(yīng)安排一覽表......................................................................................8
3.4施工流水段的劃分及施工工藝流程.................................................................................................8
3.4.1施工流水段劃分........................................................................................................................8
3.4.2施工工藝流程............................................................................................................................8
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施.............................................................................................8
第四章施工進(jìn)度計(jì)劃........................................................................................................................................9
第五章施工準(zhǔn)備與資源配置計(jì)劃..................................................................................................................9
5.1施工準(zhǔn)備計(jì)劃.....................................................................................................................................9
5.1.1技術(shù)準(zhǔn)備....................................................................................................................................9
5.1.2現(xiàn)場(chǎng)準(zhǔn)備..................................................................................................................................10
5.2資源配置計(jì)劃...................................................................................................................................10
5.2.1勞動(dòng)力配置計(jì)劃......................................................................................................................10
5.2.2工程機(jī)具配置計(jì)劃................................................................................................................10
5.2.3測(cè)量計(jì)量?jī)x器配置計(jì)劃........................................................................................................11
第六章施工方法............................................................................................................................................11
6.1方案及技術(shù)參數(shù)...............................................................................................................................11
6.1.1施工電梯方案及技術(shù)參數(shù)......................................................................................................11
6.1.2施工電梯基礎(chǔ)施工方案及技術(shù)參數(shù)....................................................................................13
6.1.3電梯附墻方案及技術(shù)參數(shù)....................................................................................................14
6.2施工工藝流程...................................................................................................................................17
6.3施工電梯安裝控制要點(diǎn)...................................................................................................................17
6.3.1施工電梯基礎(chǔ)施工................................................................................................................17
6.3.2底盤(pán)、外籠、導(dǎo)軌架安裝....................................................................................................19
6.3.3附著架的安裝........................................................................................................................21
6.3.4電纜滑輪及導(dǎo)電裝置的安裝................................................................................................23
6.3.5電纜保護(hù)架的安裝................................................................................................................24
6.3.6防風(fēng)圈的安裝........................................................................................................................25
6.3.7限位碰鐵的安裝....................................................................................................................25
6.3.8防護(hù)門(mén)的安裝........................................................................................................................25
6.3.9電梯使用之前的驗(yàn)收............................................................................................................26
6.3.9.1驗(yàn)收標(biāo)準(zhǔn).............................................................................................................................26
6.3.9.2驗(yàn)收內(nèi)容.............................................................................................................................26
1
6.3.9.3驗(yàn)收程序、驗(yàn)收人員.........................................................................................................31
6.3.10電梯使用前的檢查..............................................................................................................32
6.3.11電梯的拆卸..........................................................................................................................33
第七章進(jìn)度管理計(jì)劃....................................................................................................................................34
7.1確定施工進(jìn)度控制點(diǎn).......................................................................................................................34
7.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工...............................................................................................35
7.3進(jìn)度管理措施...................................................................................................................................35
第八章質(zhì)量管理計(jì)劃....................................................................................................................................35
8.1質(zhì)量控制目標(biāo)分解...........................................................................................................................35
8.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工...................................................................................................36
8.3確定質(zhì)量控制點(diǎn)...............................................................................................................................36
8.4質(zhì)量保證措施...................................................................................................................................37
第九章安全管理計(jì)劃....................................................................................................................................37
9.1職業(yè)健康安全管理分解目標(biāo)...........................................................................................................37
9.2安全管理組織機(jī)構(gòu)和職責(zé)分工.......................................................................................................37
9.3職業(yè)健康安全重大危險(xiǎn)源...............................................................................................................38
9.4職業(yè)健康安全資源配置計(jì)劃...........................................................................................................38
9.5安全生產(chǎn)管理制度...........................................................................................................................39
9.6安全生產(chǎn)保證措施...........................................................................................................................40
第十章環(huán)境管理計(jì)劃....................................................................................................................................41
10.1環(huán)境管理目標(biāo).................................................................................................................................42
10.2環(huán)境管理組織機(jī)構(gòu)和職責(zé)分工.....................................................................................................42
10.3重大環(huán)境因素清單.........................................................................................................................42
10.4環(huán)境保護(hù)資源配置計(jì)劃.................................................................................................................42
10.5環(huán)境保護(hù)措施.................................................................................................................................42
第十一章綠色施工管理計(jì)劃........................................................................................................................43
11.1綠色施工組織機(jī)構(gòu)和職責(zé)分工.....................................................................................................43
11.2綠色施工實(shí)施措施.........................................................................................................................44
11.3綠色施工評(píng)價(jià).................................................................................................................................44
第十二章成品保護(hù)管理計(jì)劃........................................................................................................................44
12.1成品保護(hù)管理組織和職責(zé)分工.....................................................................................................44
12.2成品保護(hù)計(jì)劃及保證措施.............................................................................................................45
第十三章應(yīng)急預(yù)案........................................................................................................................................45
13.1事故類(lèi)型和危害程度分析.............................................................................................................45
13.2組織機(jī)構(gòu)及職責(zé)分工.....................................................................................................................45
13.2.1應(yīng)急組織機(jī)構(gòu)......................................................................................................................45
13.2.2應(yīng)急小組職責(zé)分工..............................................................................................................46
13.3預(yù)防與預(yù)警.....................................................................................................................................46
13.3.1危險(xiǎn)源監(jiān)控..........................................................................................................................46
13.3.2預(yù)警行動(dòng)..............................................................................................................................47
13.4信息報(bào)告程序.................................................................................................................................47
13.5應(yīng)急處置.........................................................................................................................................48
13.5.1相應(yīng)分級(jí)..............................................................................................................................48
13.5.2響應(yīng)程序..............................................................................................................................48
13.5.3處置措施..............................................................................................................................48
2
第十四章計(jì)算書(shū)..............................................................................................................................................54
14.1施工電梯基礎(chǔ)計(jì)算...........................................................................................................................54
3
第一章編制依據(jù)
序
類(lèi)別編制依據(jù)文號(hào)
號(hào)
1《中華人民共和國(guó)建筑法》國(guó)家主席令第91號(hào)
《中華人民共和國(guó)特種設(shè)備安全法》國(guó)家主席令第號(hào)
2國(guó)家行4
政法規(guī)
3《中華人民共和國(guó)安全生產(chǎn)法》國(guó)家主席令第13號(hào)
4《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》國(guó)務(wù)令第393號(hào)
5《吊籠有垂直導(dǎo)向的人貨兩用施工升降機(jī)》GB26557-2011
6《施工升降機(jī)安全使用規(guī)程》GB/T34023-2017
7《建筑施工升降機(jī)安裝、使用、拆卸安全技術(shù)規(guī)程》JGJ215-2010
8《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
9《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》(2015版)GB50010-2010
技術(shù)規(guī)
10《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59—2011
范
11《施工現(xiàn)場(chǎng)機(jī)械設(shè)備檢查技術(shù)規(guī)范》JGJ160-2016
12《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
13《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》JGJ46-2005
14《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
15《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》JGJ130-2011
16《施工升降機(jī)使用說(shuō)明書(shū)》/
17新世界增城綜合發(fā)展項(xiàng)目施工組織設(shè)計(jì)/
18新世界增城綜合發(fā)展項(xiàng)目施工圖紙/
其他
19《安全施工管理手冊(cè)》CSCEC81-AS-2023
20《技術(shù)質(zhì)量管理手冊(cè)》CSCEC81-JS-2023
4
第二章工程概況
2.1工程建設(shè)概況
新世界增城綜合發(fā)展項(xiàng)目B標(biāo)段
工程名稱(chēng)工程性質(zhì)II類(lèi)民用建筑工程
總承包工程
建設(shè)規(guī)模9.89億工程地址
總占地面積1.86萬(wàn)平方米總建筑面積22.98萬(wàn)平方米
樁基、基礎(chǔ)、主體、部分裝修、人防、
建設(shè)單位項(xiàng)目承包范圍
周邊道路及設(shè)施工程等
基坑及土石方開(kāi)挖工程、幕墻工程、
設(shè)計(jì)單位主要分包工程
電氣、空調(diào)機(jī)消防工程
勘察單位質(zhì)量合格
計(jì)劃開(kāi)工日期:2018年12月01日;
監(jiān)理單位合同要求工期計(jì)劃竣工日期:2023年10月31日;
總工期1066日歷天,以開(kāi)工令為準(zhǔn)。
總承包單位中國(guó)建筑第八工程局有限公司安全
工程主要功能
辦公及酒店配套;地下室為車(chē)庫(kù)及設(shè)備用房
或用途
2.2設(shè)計(jì)概況
根據(jù)本工程結(jié)構(gòu)圖紙、結(jié)構(gòu)高度、現(xiàn)場(chǎng)總平面管理情況,為滿足主體結(jié)構(gòu)、二次結(jié)構(gòu)、
裝飾階段施工人員和材料的垂直運(yùn)輸要求,計(jì)劃2#塔樓、4#塔樓每棟安裝2臺(tái)施工電梯,
共計(jì)安裝4臺(tái),施工電梯生產(chǎn)廠家為廣州京龍和廣州逸安。施工電梯安裝的基本概況見(jiàn)表
2.2-1、圖2.2-1。
表2.2-1施工電梯安裝基本概況表
結(jié)構(gòu)
序號(hào)建筑單體建筑層數(shù)建筑高度型號(hào)
形式
地上46層地下5
12#塔樓剪力墻214.65SC200/200
層
地上46層地下5
22#塔樓剪力墻214.65SC200/200
層
地上45層地下5
34#塔樓剪力墻198.95SC200/200
層
地上45層地下5
44#塔樓剪力墻198.95SC200/200
層
5
施工電梯平面布置圖
2#塔樓1#、2#施工電梯平面定位圖
6
4#塔樓3#、4#施工電梯平面定位圖
圖2.2-1施工電梯安裝位置示意圖
2.3施工條件
施工電梯安裝施工時(shí),主體結(jié)構(gòu)施工至5層,現(xiàn)場(chǎng)設(shè)置2臺(tái)塔吊配合施工電梯安拆施
工材料加工、轉(zhuǎn)運(yùn)等,施工電梯基礎(chǔ)混凝土試驗(yàn)報(bào)告已出具,施工電梯安裝告知已報(bào)備完
畢。
第三章施工安排
3.1項(xiàng)目人員配置及職責(zé)
序號(hào)姓名崗位名稱(chēng)職責(zé)
1項(xiàng)目經(jīng)理曲守豐工程全方面管理、首次技術(shù)復(fù)核
2項(xiàng)目總工李明輝工程技術(shù)質(zhì)量、進(jìn)度及安全生產(chǎn)管理
3商務(wù)經(jīng)理鄭燕確定施工電梯工程合同、工程量
4生產(chǎn)經(jīng)理候健彤施工現(xiàn)場(chǎng)生產(chǎn)及安全管理工作
5專(zhuān)業(yè)工程師胡永,寸興龍落實(shí)施工電梯施工進(jìn)度、安全文明施工措施
6安全工程師李梁杰,蔣健康考核安全生產(chǎn)保證措施及文明施工措施
7技術(shù)工程師張帆,鄧兆杰施工電梯安裝過(guò)程中技術(shù)復(fù)核,旁站監(jiān)督
3.2項(xiàng)目管理目標(biāo)
項(xiàng)目管理目標(biāo)名稱(chēng)目標(biāo)值
工期按計(jì)劃工期完成施工任務(wù),確保施工總進(jìn)度計(jì)劃的常實(shí)施。
質(zhì)量目標(biāo)必須符合現(xiàn)行建設(shè)工程相關(guān)規(guī)范規(guī)定及國(guó)家、項(xiàng)目所在地的質(zhì)量
7
項(xiàng)目管理目標(biāo)名稱(chēng)目標(biāo)值
檢驗(yàn)驗(yàn)收標(biāo)準(zhǔn),并全部達(dá)到一次性驗(yàn)收“合格”標(biāo)準(zhǔn)。
安全目標(biāo)確保“廣東省建筑施工安全文明標(biāo)準(zhǔn)示范工地”
節(jié)能目標(biāo)達(dá)到《建筑節(jié)能工程施工質(zhì)量驗(yàn)收規(guī)范》要求
符合環(huán)境管理標(biāo)準(zhǔn)GB/T24000的要求,創(chuàng)造良好的施工環(huán)境,
環(huán)保目標(biāo)
營(yíng)造綠色建筑,做好工程周?chē)妗h(huán)保事業(yè)。
3.3各項(xiàng)資源供應(yīng)方式
3.3.1勞務(wù)資源安排一覽表
施工項(xiàng)目專(zhuān)業(yè)施工隊(duì)資質(zhì)開(kāi)始施工時(shí)分包分包商
建設(shè)工期責(zé)任人
名稱(chēng)名稱(chēng)要求間方式選擇方式
廣州龍升建
施工電梯
筑機(jī)械租賃貳級(jí)2023.12.30468天專(zhuān)業(yè)分包公司選定鄭燕
安拆
有限公司
3.3.2工程用大宗物資供應(yīng)安排一覽表
物資名稱(chēng)租賃單位擬選供應(yīng)商租賃地點(diǎn)要求進(jìn)場(chǎng)時(shí)間責(zé)任人
廣州龍升建
施工電梯筑機(jī)械租賃/廣州2023.12李梁杰
有限公司
3.3.3大型機(jī)械設(shè)備采購(gòu)供應(yīng)安排一覽表
機(jī)械設(shè)備名稱(chēng)擬選供應(yīng)商提供方式要求進(jìn)場(chǎng)時(shí)間計(jì)劃出場(chǎng)時(shí)間責(zé)任人
塔吊山東中誠(chéng)租賃2023年3月2023年5月李梁杰
3.4施工流水段的劃分及施工工藝流程
施工流水段劃分
根據(jù)本工程總體施工部署,施工電梯在每棟塔樓結(jié)構(gòu)施工至3層時(shí)開(kāi)始電梯基礎(chǔ)施工,
結(jié)構(gòu)施工完成5層時(shí)開(kāi)始安裝施工電梯。一臺(tái)施工電梯安拆為一個(gè)流水段。
施工工藝流程
底座、外籠、導(dǎo)軌架
施工電梯基礎(chǔ)施工附著架安裝電纜滑輪及導(dǎo)電安裝
安裝
室外電梯架及防護(hù)門(mén)
限位碰鐵安裝防風(fēng)圈安裝電纜保護(hù)架安裝
安裝
施工電梯使用前檢查
施工電梯使用施工電梯拆卸
驗(yàn)收
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施
序號(hào)重點(diǎn)和難點(diǎn)具體分析應(yīng)對(duì)措施責(zé)任人
8
提前準(zhǔn)備墊片,每道附墻
導(dǎo)軌架垂直度及底座的水平度前后必須測(cè)量垂直度,預(yù)
底座及導(dǎo)軌架
1不易控制,電梯廂與外立面間距埋件安裝前進(jìn)行多方復(fù)李明輝
的安裝
不易控制核,確保電梯廂與外立面
間距符合設(shè)計(jì)要求
編制與實(shí)際工程密切相符
的施工技術(shù)方案,施工電
施工電梯安拆屬于危險(xiǎn)性較大梯安拆前對(duì)作業(yè)人員進(jìn)行
危險(xiǎn)性較大,
2分項(xiàng)工程,在安拆過(guò)程中存在傾詳細(xì)的安全技術(shù)交底。施李梁杰
安全管理較難
覆、沖頂、高處墜落等危險(xiǎn)源工過(guò)程中進(jìn)行旁站監(jiān)督,
使用過(guò)程中日、周、月巡
檢全覆蓋。
電梯使用過(guò)程施工電梯司機(jī)必須經(jīng)專(zhuān)門(mén)
施工電梯司機(jī)責(zé)任心不強(qiáng),操作
5過(guò)程控制難度安全技術(shù)培訓(xùn),考試合格,李梁杰
不當(dāng)
大持證上崗。嚴(yán)格酒后作業(yè)。
第四章施工進(jìn)度計(jì)劃
表4.1施工電梯安裝進(jìn)度計(jì)劃統(tǒng)計(jì)表
單位工程施工部位計(jì)劃安裝時(shí)間計(jì)劃拆除時(shí)間責(zé)任人負(fù)責(zé)人
3號(hào)施工電梯安
2#塔樓2023.12.302023.4.10寸興龍李梁杰
裝
4號(hào)施工電梯安
2#塔樓2023.3.102023.4.10寸興龍李梁杰
裝
2號(hào)施工電梯安
4#塔樓2023.1.5胡永李梁杰
裝
1號(hào)施工電梯安
4#塔樓2023.2.202023.3.20胡永李梁杰
裝
第五章施工準(zhǔn)備與資源配置計(jì)劃
5.1施工準(zhǔn)備計(jì)劃
技術(shù)準(zhǔn)備
表5.1.1-1技術(shù)文件準(zhǔn)備計(jì)劃一覽表
序號(hào)文件名稱(chēng)文件編號(hào)配備數(shù)量持有人
1《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-20121鄧兆杰
《建筑施工電梯安裝、使用、拆卸安全
2JGJ215-20101鄧兆杰
技術(shù)規(guī)程》
3《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-20111鄧兆杰
4《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》(2015年版)GB50010-20101鄧兆杰
9
5《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》GB50007-20111鄧兆杰
6《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-20151鄧兆杰
7《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-20161鄧兆杰
8《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》JGJ46-20051鄧兆杰
9施工電梯廠家使用說(shuō)明書(shū)及相關(guān)設(shè)備參數(shù)/1鄧兆杰
2施工方案編制計(jì)劃表
序號(hào)施工方案名稱(chēng)編制單位負(fù)責(zé)人完成時(shí)間
1施工電梯安拆方案新世界增城項(xiàng)目部張帆
3技術(shù)復(fù)核和隱蔽驗(yàn)收計(jì)劃表
序號(hào)技術(shù)復(fù)核、隱蔽驗(yàn)收部位復(fù)核和隱蔽內(nèi)容責(zé)任人
1施工電梯定位各單體施工電梯位置胡永,寸興龍
施工電梯基礎(chǔ)是否按照方
案施工,鋼筋、砼強(qiáng)度、地
2施工電梯基礎(chǔ)張帆,胡永,寸興龍
腳螺栓是否正確,基礎(chǔ)澆筑
完成及時(shí)養(yǎng)護(hù)
施工電梯安裝是否按照審
3施工電梯安裝李明輝,李梁杰,張帆
批方案執(zhí)行
地下室鋼管支撐是否按照
4地下室鋼管支撐回頂方案搭設(shè),立桿間距、步距、張帆,李梁杰
扣件連接是否牢靠。
施工電梯防墜器、附著拉
5施工電梯安裝李梁杰
結(jié)、標(biāo)準(zhǔn)節(jié)連接等限位檢查
現(xiàn)場(chǎng)準(zhǔn)備
序號(hào)設(shè)施名稱(chēng)種類(lèi)數(shù)量規(guī)模(或可存儲(chǔ)量)設(shè)施構(gòu)造完成時(shí)間責(zé)任人
施工電梯配
1/2100㎡標(biāo)準(zhǔn)化2023.11.30候健彤
件材料堆場(chǎng)
5.2資源配置計(jì)劃
5.2.1勞動(dòng)力配置計(jì)劃
202320232023
序號(hào)專(zhuān)業(yè)工種121234567891011121234責(zé)任人
月月月月月月月月月月月月月月月月月
1安拆工66662222222222226候健彤
2塔吊司機(jī)22222222222222222候健彤
3塔吊指揮22222222222222222候健彤
5.2.2工程機(jī)具配置計(jì)劃
10
序號(hào)名稱(chēng)型號(hào)單位數(shù)量責(zé)任人
1塔吊TC7530臺(tái)2李梁杰
5.2.3測(cè)量計(jì)量?jī)x器配置計(jì)劃
數(shù)
序號(hào)儀器名稱(chēng)分類(lèi)使用特征檢定周期保管人
量
1全站儀B1定位、垂直度測(cè)量12個(gè)月姜武
2水準(zhǔn)儀B1標(biāo)高測(cè)量12個(gè)月姜武
3力矩扳手C1螺栓力矩檢測(cè)12個(gè)月姜武
材料厚度、直徑、設(shè)備
4游標(biāo)卡尺C212個(gè)月姜武
間隙等測(cè)量
5鋼卷尺C20測(cè)量12個(gè)月姜武
第六章施工方法
6.1方案及技術(shù)參數(shù)
施工電梯方案及技術(shù)參數(shù)
本工程選用2臺(tái)廣州逸安、2臺(tái)廣州京龍生產(chǎn)的SC200/200型施工電梯,額定載重量
為2000kg,額定提升速度:63m/min,吊籠內(nèi)空尺寸:3.2×1.5×2.5m。施工升降機(jī)均為
雙籠,傳動(dòng)機(jī)構(gòu)在吊籠上方,每個(gè)吊籠最大載重量為2000㎏。具體性能參數(shù)見(jiàn)表
6.1.1-1,升降機(jī)外形總體平面尺寸見(jiàn)圖6.1.1-1。
表6.1.1-1施工電梯性能參數(shù)表
序號(hào)項(xiàng)目單位參數(shù)備注
1額定載重量kg2000
每人攜帶工具不超過(guò)
2限定乘員人9
20kg
3額定提升速度m/min63
4最大提升高達(dá)m550
5吊籠內(nèi)空m×m3.2×1.5×2.5
6標(biāo)準(zhǔn)節(jié)規(guī)格mm650×650×1508
7吊籠內(nèi)部?jī)舾叨萴2.5
8電能耗量KVA小于12×2
11
序號(hào)項(xiàng)目單位參數(shù)備注
9電機(jī)功率KW2×3×11
10標(biāo)準(zhǔn)節(jié)質(zhì)量kg170
11吊籠質(zhì)量kg2200
12安全器型號(hào)/SAJ50-1.4
13自由端高度m3~7.5
12
圖6.1.1-1升降機(jī)外形總體平面尺寸圖
6.1.2施工電梯基礎(chǔ)施工方案及技術(shù)參數(shù)
1#施工電梯將采用SC200/200中速施工電梯,安裝高度為190.5m(45F)。1#施工電梯
基礎(chǔ)在地下室頂板面上,施工電梯基礎(chǔ)的尺寸為長(zhǎng)6000mm、寬4000mm、高300mm,基礎(chǔ)底
標(biāo)高為+0.050m。
2#施工電梯將采用SC200/200中速施工電梯,安裝高度為190.5m(45F)。2#施工電梯
基礎(chǔ)在地下室頂板面上,施工電梯基礎(chǔ)的尺寸為長(zhǎng)6000mm、寬4000mm、高300mm,基礎(chǔ)底
標(biāo)高為+0.050m。
3#施工電梯將采用SC200/200中速施工電梯,安裝高度為222m(46F)。3#施工電梯基
礎(chǔ)在地下室頂板面上,施工電梯基礎(chǔ)的尺寸為長(zhǎng)6000mm、寬4000mm、高300mm,基礎(chǔ)底標(biāo)
高為-2.100m。
4#施工電梯將采用SC200/200中速施工電梯,安裝高度為222m(46F)。4#施工電梯基
礎(chǔ)在地下室頂板面上,施工電梯基礎(chǔ)的尺寸為長(zhǎng)6000mm、寬4000mm、高300mm,基礎(chǔ)底標(biāo)
13
高為-2.100m。
編基礎(chǔ)尺寸基礎(chǔ)中心離混凝
軸線電梯選型地基情況
號(hào)(長(zhǎng)
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 《倉(cāng)庫(kù)現(xiàn)場(chǎng)管理》課件
- 《倉(cāng)庫(kù)庫(kù)存管理系統(tǒng)》課件
- 《小學(xué)細(xì)節(jié)描寫(xiě)》課件
- 單位管理制度集粹選集員工管理篇
- 單位管理制度合并匯編【職員管理】
- 四川省南充市重點(diǎn)高中2024-2025學(xué)年高三上學(xué)期12月月考地理試卷含答案
- 單位管理制度分享合集職員管理篇十篇
- 單位管理制度范文大合集【人事管理】十篇
- 單位管理制度呈現(xiàn)大全職工管理篇十篇
- 《運(yùn)算律》教案(20篇)
- 2024年時(shí)事政治試題【有答案】
- 2024年認(rèn)證行業(yè)法律法規(guī)及認(rèn)證基礎(chǔ)知識(shí)
- MT 285-1992縫管錨桿
- 【高中化學(xué)校本課程】《生活中的化學(xué)》校本教材
- 水資源管理培訓(xùn)材料課件
- SCA自動(dòng)涂膠系統(tǒng)培訓(xùn)講義
- 促銷(xiāo)活動(dòng)方案(共29頁(yè)).ppt
- 農(nóng)民專(zhuān)業(yè)合作社財(cái)務(wù)報(bào)表(三張表)
- 培訓(xùn)準(zhǔn)備工作清單
- 沉井工程檢驗(yàn)批全套【精選文檔】
- 貝類(lèi)增養(yǎng)殖考試資料
評(píng)論
0/150
提交評(píng)論