1、隧道淺埋巖堆體ø108大管棚超前支護(hù)施工工藝編制: 審核: 目 錄1. 前言·····································22. 工程概況····
2、83;····························22.1概述····················
3、83;·············22.2大管棚變更情況························32.3大管棚超前支護(hù)方法········
4、83;···········43. 施工工藝·································73.1測量放樣···
5、;···························73.2鉆孔······················
6、;············93.3配管·································113.4送管··
7、3;······························123.5下鋼筋籠··················&
8、#183;··········133.6管口封閉·····························133.7注漿·······
9、83;·························133.8沉降觀測·······················
10、······183.9事故預(yù)防和處理·······················183.10機(jī)具設(shè)備和勞力·················
11、;·····194.安全措施································205.結(jié)論··········
12、83;·························216.相關(guān)知識點(diǎn)·······················
13、·······217.主要參考書目····························241.前言xx市xx二級公路A 標(biāo)段下南城隧道全長772m(K2+423K3+195),但其進(jìn)口處于破碎土巖堆地段長達(dá)182m(K2+423K2+605),且
14、最淺埋深僅2m,同時圍巖含水量大,工程力學(xué)性質(zhì)差,開挖后易坍塌,成洞困難。為確保開挖穩(wěn)定,進(jìn)口K2+433K2+488段55 m,隧道拱部120°范圍采用ø108×8mm超前大管棚注漿支護(hù)輔助施工,共設(shè)兩環(huán),每環(huán)鋼管總長度30m。我公司施工類似大直徑的長大管棚,并且達(dá)到兩環(huán)以上(包括兩環(huán)),這是第一次。其施工工藝和方法尚無成熟的經(jīng)驗(yàn)可以借鑒,需要進(jìn)行摸索和研究。因此有必要對ø108大管棚超前支護(hù)的施工方法、適用機(jī)械、勞動組織等進(jìn)行研究和總結(jié),以便更好地加以推廣和應(yīng)用。將ø108大管棚超前支護(hù)的施工工藝,形成一整套操作性強(qiáng)、系統(tǒng)完整、詳實(shí)準(zhǔn)確、技
15、術(shù)含量高、有推廣價值的成果。對于提高工程的科技含量,增強(qiáng)技術(shù)創(chuàng)新能力,全面貫徹“科技是第一生產(chǎn)力”,推動公司的科技進(jìn)步和“科技興企”戰(zhàn)略的實(shí)施,都具有重大的意義。2.工程概況2.1概述xx二級公路A 標(biāo)段下南城隧道位于xx市彭水縣城南郊下南城,隧道穿越下南城山,進(jìn)口里程K2+423,出口里程K3+195,全長772m,路線設(shè)計(jì)縱坡-3%、-0.094%。進(jìn)口30.632m及出口段192.75m分別位于半徑為120m及200m的曲線上,其余地段位于直線上。進(jìn)口K2+433+488段55m,為類圍巖,隧道位于坡積碎石土層上,含水量大,埋深淺,工程力學(xué)性質(zhì)差,圍巖開挖后易坍塌,成洞困難。于隧道拱部1
16、20°范圍采用超前大管棚注漿支護(hù)輔助施工(大管棚共布置兩環(huán)),邊墻及仰拱采用超前小導(dǎo)管注漿支護(hù)輔助施工。且設(shè)2榀/m拱、墻、仰拱格柵鋼架加強(qiáng)支護(hù)。隧道開挖最大尺寸為寬×高=13.24m×9.86m。隧道襯砌內(nèi)凈空寬度為9+2×1.0米。限界凈寬:10.5m,限界凈高: 5.0m。2.2大管棚變更情況原設(shè)計(jì)管棚里程段為K2+438K2+488(50m),管棚長度60m,分兩環(huán)布置。變更一:管棚里程段由K2+438K2+488(50m)變更為K2+433K2+488(55m),形成兩個方案:按兩環(huán)布置,管棚長度為65m(里程段+一個接頭+超前量=55+5+5
17、=65m);按三環(huán)布置,管棚長度為70m(里程段+二個接頭+超前量=55+5×2+5=70m)。考慮到按施工,每環(huán)管棚長度都超過了30m,很難達(dá)到規(guī)范和質(zhì)量要求。故采用,每環(huán)長度分別定為24m、24m、22m。實(shí)際施工時,鉆孔記錄顯示,第二環(huán)管棚已有2m伸入巖層,這樣,第三環(huán)管棚已無必要,將其取消。變更二:鋼管接頭原設(shè)計(jì)為管子兩頭車公螺紋,對接后,外套厚壁管箍,將絲扣上緊??紤]到加工螺紋,費(fèi)用很高,故變更為兩種接頭方法:外套管和絲扣法。其中,外套管法用于第一環(huán)大管棚,絲扣法用于第二環(huán)大管棚。2.3大管棚超前支護(hù)方法2.3.1管棚構(gòu)造管棚由鋼管和鋼格柵拱架組成。管棚是利用鋼格柵拱架,沿
18、著開挖輪廓線,以較小的外插角,向開挖面前方打入鋼管,形成對開挖面前方圍巖的預(yù)支護(hù)。見下圖2.3.2管棚的性能特點(diǎn)及適用條件管棚是利用鋼管作為縱向支撐、鋼格柵拱架作為橫向環(huán)形支撐,構(gòu)成縱、橫向整體剛度較大,能阻止和限制圍巖變形,并能提前承受早期圍巖壓力的一種超前支護(hù)形式。管棚適用于特殊困難地段(如極破碎巖體、塌方體、巖堆地段、砂土質(zhì)地層、強(qiáng)膨脹性地層、斷層破碎帶、淺埋大偏壓等圍巖)的隧道施工中采用。長管棚與短管棚相比,其一次超前量較大,可減少安裝鋼管次數(shù),并減少與開挖作業(yè)之間的干擾,適用于大中型機(jī)械進(jìn)行大斷面開挖。2.3.3管棚支護(hù)結(jié)構(gòu)要點(diǎn)大管棚鉆孔孔口位置沿隧道拱部開挖輪廓線外10cm布置,環(huán)
19、向中心間距40cm,外插角約 ,每環(huán)35根。鋼管采用外徑ø108、壁厚8mm的無縫鋼管,每環(huán)鋼管總長度為30m。鋼管分段安裝。第一段按奇、偶數(shù)分別編號,奇、偶數(shù)不同的管長相差2m(若奇數(shù)管長為4m,則偶數(shù)管長為6m),其后各分段管長可取相等長度(6m)。兩段之間用絲扣連接,絲扣螺紋段長度不小于15cm。鋼管上鉆注漿孔,孔徑為ø10mm,孔間距50cm,呈梅花型布置。鋼管尾部2m不鉆孔作為止?jié){段。為提高鋼管的剛度和強(qiáng)度,鋼管內(nèi)增設(shè)由4根20mm螺紋鋼筋和固定短環(huán)組成的鋼筋籠,固定環(huán)采用外徑ø42mm、壁厚8mm,長4cm的短管環(huán),環(huán)向間距1m。市政施工視頻 備考13
20、年一二級建造師 市政 必備參考資料十一月主講首先講一下我的整個講解過程方式:總體而言從現(xiàn)在開始復(fù)習(xí)就算是從零開始,時間上面來說還是夠的,市政一門課應(yīng)該保證100小時以上的學(xué)習(xí),如果現(xiàn)場經(jīng)驗(yàn)不足,可能要需要200小時甚至更多的時間。之前說的三部曲呢,主要是入門把書讀厚階段:理解全書,各類施工方式80分詳細(xì)分析:理解考點(diǎn)、用真題捕捉考點(diǎn)。記憶。背誦。讀薄階段。90分全書融會貫通,就是閉上眼睛。整書有個概念。最后就是針對太極拳的題目,我們盡量去用無賴的技巧去多拿分.十一月 收集整理 2013年5月 5日 更多資料請聯(lián)系QQ813517521縱向兩組管棚間,應(yīng)有不小
21、于3.0m的水平搭接長度。鋼拱架采用鋼格柵鋼架。(4)在鋼管內(nèi)放置鋼筋籠并灌注水泥漿單液漿或水泥-水玻璃雙液漿,可增加鋼管剛度。(5)注漿漿夜采用水泥漿,水灰比為:W:C=0.5:1。當(dāng)?shù)叵滤^發(fā)肓或漿液擴(kuò)散范圍較大時,注漿漿液改為水泥-水玻璃雙液漿。注漿壓力采用0.51Mpa。2.3.4大管棚施工工藝流程圖備 料施工準(zhǔn)備機(jī)具設(shè)備檢修鋼管原材檢驗(yàn)加工鋼管鉆機(jī)就位鋼管與鉆桿連接地質(zhì)鉆機(jī)鉆 孔鉆機(jī)移位至設(shè)計(jì)深度管棚施鉆完畢安設(shè)注漿管路配 漿管路壓水試驗(yàn)注 漿結(jié) 束3.施工工藝3.1測量放樣 第一環(huán)大管棚(K2+432K2+456)a.根據(jù)隧道進(jìn)口布設(shè)的三角導(dǎo)線網(wǎng),用坐標(biāo)法測設(shè)管棚的起始中心里程(K
22、2+433),落點(diǎn)。然后置鏡中心點(diǎn),測設(shè)中心線的垂線方向, 在該方向上測設(shè)控制樁,每邊各2個,以便隨時恢復(fù)并檢查方向的正確性。b.然后,在該方向上安設(shè)一鋼格柵(其半徑與大管棚半徑相對應(yīng)),以作定位用。測設(shè)每根導(dǎo)管的中心線方向,并測設(shè)控制樁2個,同時在鋼格柵上落點(diǎn),于點(diǎn)位兩端焊接20的的短鋼筋頭(長20cm),以作導(dǎo)向用。同時在鋼格柵下邊用18工字鋼布設(shè)五道支撐加固,確保鋼格柵穩(wěn)固。c鉆孔的方向和傾斜度控制方向控制:在每個導(dǎo)管中心線方向上,均釘設(shè)兩個方向樁,以控制鉆孔的方向。傾斜度控制:孔外,通過測設(shè)大導(dǎo)管孔口及鉆機(jī)中心的高程進(jìn)行控制??變?nèi),用精密水平陀螺儀控制傾斜度,分別在距孔口2m處、1/2
23、孔深處、終孔處三處進(jìn)行測量,不符合鉆孔精度和要求的鉆孔,必須封孔重鉆。第二環(huán)大管棚(K2+452K2+476)一般測設(shè)同第一環(huán)大管棚。不同之處如下:a第二環(huán)大管棚增設(shè)工作室(K2+445K2+453),長為8m(每節(jié)ø108×8mm大導(dǎo)管長6.0m,加鉆機(jī)機(jī)身及主動鉆桿必需的2.0m)。圍巖開挖后,立即初噴混凝土,架設(shè)鋼格柵支撐和打設(shè)錨桿,掛網(wǎng)并噴混凝土覆蓋。該工作室尺寸比設(shè)計(jì)輪廓線相應(yīng)的增大,工作室縱斷面示意圖如下: b.由于第二環(huán)大管棚在洞內(nèi)施做,工作空間狹小,且不能影響后續(xù)工序,所以不能象第一環(huán)管棚那樣,將控制方向護(hù)樁釘設(shè)在地面上,而是在鉆機(jī)機(jī)身中心上面的初期支護(hù)拱部
24、設(shè)點(diǎn),并用紅油漆標(biāo)記。同時,通過這些拱部點(diǎn)位的標(biāo)高來反算鉆機(jī)中心的高度,通過孔口及鉆機(jī)中心兩點(diǎn)的高程便于控制鉆孔時的傾斜度(孔外)。3.2鉆孔檢查開挖的斷面中線及高程,確保開挖輪廓線符合設(shè)計(jì)要求。在開挖工作面處安設(shè)受力拱架,并在其上正確標(biāo)明管棚位置;鋼架安裝垂直度允許誤差為±20,中線及高程允許誤差為±5cm。在鋼架上沿隧道開挖輪廓線縱向鉆設(shè)管棚孔,其外插角以不侵入隧道開挖輪廓線越小越好。鉆孔順序見下圖:兩臺鉆機(jī)鉆孔順序示意圖說明:部和部同時開孔,同時結(jié)束;部和部同時開孔,同時結(jié)束。方向前進(jìn)如上圖所示。原則為:任何時候都必須保證有兩臺鉆機(jī)同時工作。因?yàn)樯蠈?dǎo)坑需人工開挖掘進(jìn),
25、工效很低,是控制整個隧道工期的關(guān)鍵因素,所以必須千方百計(jì)地加快管棚施工進(jìn)度,為人工開挖掘進(jìn),贏得一定的時間。按照布好的孔位及鉆孔的方向和傾斜度開始鉆孔??卓谖恢门c設(shè)計(jì)位置的允許偏差為±5cm;孔底位置偏差小于孔深的10。剛開孔時,要低壓、慢轉(zhuǎn),以便于控制方向,然后逐漸地提高鉆速,保持正常壓力。如遇到大孤石時,則需高壓、低速進(jìn)行。總之,要隨著地質(zhì)的不斷變化,相應(yīng)地調(diào)整鉆進(jìn)參數(shù)。鉆進(jìn)時,用清水護(hù)壁,中間定期將取芯管取出,取出巖芯。當(dāng)快成孔時,用水將孔內(nèi)的懸浮物或泥漿、石碴等清洗出來,做到孔壁圓、角度準(zhǔn)、孔身直、深度夠、巖粉清洗干凈。當(dāng)出現(xiàn)嚴(yán)重卡鉆、孔口不出水時停止鉆孔,立即注漿。鉆孔結(jié)束
26、后,掏孔檢查,在確認(rèn)無塌孔和探頭石時,才可安設(shè)鋼管。鉆頭采用130的合金鉆頭,遇孤石時,則采用金剛石鉆頭。大管棚施工完成后,成傘形輻射狀。詳見下圖:3.3配管為了使大管棚的整體受力效果更好,在接長管棚鋼管時,鋼管接頭在隧道縱斷面上錯開2m。下管時,由于108×8mm的大導(dǎo)管從46m不等,故必須將管子相互連接起來,才能達(dá)到設(shè)計(jì)長度。管子連接采用兩種方法:第一環(huán)管棚使用外套管法;第二環(huán)管棚使用絲扣法。絲扣法:即在一根管子的兩端,分別車出一個公螺紋,一個母螺紋,螺紋長度不小于15cm,螺紋深度不大于1/2壁厚(4mm)。連接時,前一根管的母螺紋與后一根管的公螺紋套在一起,用力擰緊,以防止松
27、動,引起質(zhì)量事故。外套管法:即管子兩端不車螺紋,只在兩根管子的接頭外邊套一127×4mm的外套管,長40 cm,然后用電弧焊將縫隙焊滿、焊牢。優(yōu)缺點(diǎn):法,省時、省力、方便,但加工費(fèi)用較高。 法,費(fèi)時、費(fèi)力、不方便,但加工費(fèi)用較低。3.4送管:只要具備足夠的場地或空間,就可充分利用大型機(jī)械送管,以提高效率,并減少工人的勞動強(qiáng)度。第一環(huán)大管棚,利用CAT320挖掘機(jī)挖斗向前送管。但第二環(huán)大管棚由于在洞內(nèi),場地狹窄,大型機(jī)械無法操作,只能用鉆機(jī)送管。成孔后,通過異型接頭,用主動鉆桿帶動108×8mm的大導(dǎo)管,邊旋轉(zhuǎn)(克服磨擦阻力)邊向前推進(jìn),直至將全部管子送到位。兩環(huán)大管棚縱斷面
28、布置如下圖: 這樣,每一環(huán)大管棚都正好搭在兩環(huán)襯砌頭上,相當(dāng)于過梁。可以更好地起到預(yù)支護(hù)的作用。3.5下鋼筋籠鋼筋籠由4根20的螺紋鋼筋組成,中間內(nèi)襯一42×8的導(dǎo)管環(huán),間距1m。鋼筋籠主要是為了增強(qiáng)大導(dǎo)管的整體剛度和強(qiáng)度。36管口封閉36.1在管子端部焊一帶眼的鋼板,然后將32×4mm(長50cm)的注漿管與該鋼板相焊,就可以了。36.2注漿管構(gòu)造 注漿管須是三通構(gòu)造:一通接108×8的大導(dǎo)管。一通接塑膠管,一通為沖洗用(沖洗口主要是為防止水泥漿或水玻璃凝固,造成堵管,可以及時地將管道用水沖洗干凈)。37注漿37.1大導(dǎo)管注漿施工參數(shù)先在ø108
29、15;8mm鋼管上鉆ø10mm的出漿孔,孔距50cm,呈梅花型布置。鋼管尾部2m不鉆花孔作為止?jié){段。鋼管沿隧道開挖輪廓線布置,外傾角1 0,間距0.4m,縱向前后兩排鋼管水平搭接長度不小于3m。單液注漿:水泥漿水灰比(W:C)為0.5:1。雙液注漿(當(dāng)?shù)叵滤^發(fā)育或漿液擴(kuò)散范圍大時,注漿漿液改為水泥-水玻璃雙液漿。):水泥漿水灰比(W:C)為0.5:1;水玻璃模數(shù) 2.6-2.9,濃度35波美度;水泥漿、水玻璃體積比1:0.3。注漿壓力采用0.5-1.0Mpa。試配水泥漿如下:水泥漿配合比水灰比材料名稱水泥水0.5:11m3用量(Kg)1123562采用雙液漿時,商品水玻璃玻美度為4
30、5°be,實(shí)際要求為35°be。這樣,需要將水玻璃加水稀釋,采用公式如下:水玻璃稀釋計(jì)算公式V11+VWW= V22V1+ VW= V2V1 、V2稀釋前后水玻璃體積;1、2稀釋前后水玻璃密度;=145/(145-Be)W 、VW水的密度和體積;37.2大導(dǎo)管注漿量計(jì)算:按下式計(jì)算Q=r2H其中: r漿液擴(kuò)散半徑;H大導(dǎo)管長度,取24m;巖體孔隙率,取0.6。充填率系數(shù),取0.3。大管棚注漿量計(jì)算表rQH010.20.30.40.524543122121713393鋼管凈空容量160說明:1.r、H單位以米計(jì);Q單位以升計(jì)。2注漿量必須大于鋼管的凈空容量。 注漿時,每根鋼管
31、的注漿量一般達(dá)到300升左右,估計(jì)擴(kuò)散半徑小于0.2m。開挖以后,發(fā)現(xiàn)一般在0.1m左右。37.3漿液的調(diào)制步驟:水泥漿液攪拌在拌合機(jī)內(nèi)進(jìn)行,根據(jù)拌合機(jī)容量大小,嚴(yán)格按要求投料;攪拌投料的順序?yàn)椋涸诜潘耐瑫r,將外加劑(如有)一并加入攪拌,待水量加足后,繼續(xù)攪拌1min,并將水泥投入,攪拌時間不小于3min,并在注漿過程中不停攪拌漿液;采用水玻璃漿液時,其濃度宜為25400Be(取350Be)。為稀釋水玻璃,采取邊加水,邊攪拌,邊用波美計(jì)量測的辦法進(jìn)行;配制水泥漿或稀釋水玻璃漿液時,嚴(yán)防水泥包裝紙及其他雜物混入。拌好的漿液在進(jìn)入貯漿槽及注漿泵之前均應(yīng)對漿液進(jìn)行過濾,未經(jīng)過濾網(wǎng)過濾的漿液不允許進(jìn)
32、入泵內(nèi)。 配制的漿液在規(guī)定時間內(nèi)注完。37.4注漿方式及順序 37.4.1注漿方式 根據(jù)圍巖類別、地質(zhì)條件、機(jī)械設(shè)備及注漿孔的深度選用全孔式。即鉆孔直至孔底,然后一次注漿完畢。37.4.2注漿順序先注無水孔,后注有水孔;從拱頂順序?qū)ΨQ向下進(jìn)行。如遇竄漿或跑漿,則間隔一孔或數(shù)孔灌注。注漿結(jié)束后,利用止?jié){閥保持孔內(nèi)壓力,直至漿液完全凝固。注漿壓力與地層條件及注漿范圍要求有關(guān),一般要求能擴(kuò)散到管周0.51.0m的半徑范圍內(nèi)。但應(yīng)控制注漿量,每根大導(dǎo)管內(nèi)已達(dá)到規(guī)定注入量時就可結(jié)束,若孔口壓力已達(dá)到規(guī)定壓力值而注入量仍不足時,亦應(yīng)停止注漿,以防壓裂開挖面。3.7.5注漿作業(yè)要求 漿液的濃度、膠凝時間符合
33、設(shè)計(jì)要求,不得任意變更;經(jīng)常檢查泵口及孔口注漿壓力的變化,發(fā)現(xiàn)問題及時處理;采用雙液注漿時,經(jīng)常測試混合漿液的膠凝時間,發(fā)現(xiàn)不符,立即調(diào)整。3.7.6注漿結(jié)束條件單孔結(jié)束條件:注漿壓力達(dá)到設(shè)計(jì)終壓,漿液注入量已達(dá)到計(jì)算值80%以上。全地段結(jié)束條件:所有注漿孔均已符合單孔結(jié)束條件,無漏注漿情況。3.7.7注漿效果檢查采用以下兩法進(jìn)行檢查分析法:即分析注漿記錄,看每個孔的注漿壓力、注漿量是否達(dá)到設(shè)計(jì)要求;在注漿過程中,漏漿、跑漿是否嚴(yán)重;以漿液注入量估算漿液擴(kuò)散半徑,分析是否與設(shè)計(jì)相符。檢查孔法:用地質(zhì)鉆機(jī)按設(shè)計(jì)孔位和角度鉆檢查孔,取巖芯進(jìn)行鑒定。3.7.8注漿后至開挖前的時間間隔單液水泥漿開挖時
34、間為注漿后8h左右,水泥水玻璃漿為4h左右。3.7.9注漿異?,F(xiàn)象處理發(fā)生串漿現(xiàn)象,即液漿從其他孔中流出時,采用方法:堵塞串漿隔孔注漿;單液注漿水泥漿壓力突然升高,可能發(fā)生了堵管,停機(jī)檢查;水泥與水玻璃雙液漿壓力突然升高,則關(guān)停水玻璃泵,進(jìn)行單液漿或注清水,待泵壓正常時,再進(jìn)行雙液注漿;水泥漿單液或水泥與水玻璃雙液注漿進(jìn)漿量很大,壓力長時間不升高,則應(yīng)調(diào)整漿液濃度及配合比,縮短凝膠時間,進(jìn)行小量低壓力注漿或間歇式注漿,使?jié){液在裂隙中有相對停留時間,以便凝膠,但停留時間不能超過混合漿的凝膠時間,才能避免產(chǎn)生注漿不飽滿。3.8沉降觀測 為了檢測大管棚施工時對周圍環(huán)境的影響及施工完畢后的效果,均須通
35、過沉降觀測進(jìn)行。 在地面上設(shè)K2+441、K2+453斷面,每斷面設(shè)5個觀測樁,當(dāng)大管棚注漿時,經(jīng)觀測,無隆起、上鼓現(xiàn)象發(fā)生。 當(dāng)開挖大管棚范圍段時,經(jīng)觀測有一定的沉降(10cm),如遇山體整體下沉,則可達(dá)到20 cm,這樣考慮一些其它因素,在預(yù)留2530 cm的沉降量后,完全可以滿足隧道施工和安全的要求。3.9事故預(yù)防和處理3.9.1孔的傾斜度開孔時,在土質(zhì)地層中,要低速低壓,以保證孔位的正確。同時在距孔口2m處、開孔1/2處、終孔處用精密水平陀螺儀檢測傾斜度,不合格的,封孔重鉆。3.9.2塌孔若地層中含水量大,或地質(zhì)較差時,易坍孔,可采用兩種方法進(jìn)行預(yù)防。泥漿護(hù)壁法對于地層中含水量不是特別
36、大,地質(zhì)屬于碎石土層時,可用泥漿護(hù)壁。套管護(hù)壁法對于地層中含水量特別大,地質(zhì)屬于碎石層或地下暗河的地段,可采用套管護(hù)壁。此時采用127×4套管,一般的不良地段均可通過。3.10機(jī)具設(shè)備和勞力組織3.10.1需要的機(jī)具設(shè)備大管棚作業(yè)機(jī)具設(shè)備表序號設(shè)備名稱及規(guī)格單位數(shù)量備注一機(jī)電設(shè)備1鉆機(jī)臺2XY-1、XY-1B2汽車臺13交流電焊機(jī)臺14注漿機(jī)臺1序號設(shè)備名稱及規(guī)格單位數(shù)量備注5挖掘機(jī)臺1CAT-320二工具每臺鉆機(jī)1鏈鉗把22管鉗把23大號扳手把24大錘把13.10.2勞力組織分2個工班進(jìn)行作業(yè),每個工班12人,其中:施工指揮1人;施工技術(shù)指導(dǎo)1人;鉆機(jī)司機(jī)2人(負(fù)責(zé)鉆孔、下管);普
37、通工人4人(負(fù)責(zé)裝卸鉆桿、裝接鋼管);電工1人(負(fù)責(zé)供水供電工作);電焊工1人;汽車司機(jī)1人(負(fù)責(zé)運(yùn)料);洞外調(diào)度1人。4.安全措施4.1加強(qiáng)全員安全意識教育;4.2針對本隧道工程長大管棚施工特點(diǎn)和要求,參照有關(guān)規(guī)范制訂規(guī)章制度;4.3加強(qiáng)對圍巖進(jìn)行動態(tài)監(jiān)控量測,實(shí)行信息化管理,科學(xué)地組織施工;4.4拆卸鉆桿時,要有統(tǒng)一指揮、明確聯(lián)絡(luò)信號,扳鉗卡鉆方向正確,防止管鉗用扳手傷人;4.5鋼管內(nèi)注漿時,操作人員應(yīng)戴口罩、眼鏡和膠手套。4.6要有良好的照明條件。5.結(jié)論5.1 可采用XY-1、XY-1B型的輕便鉆機(jī)。其最大開孔直徑為130mm,最大鉆孔深度為120m。適宜在碎石土層中進(jìn)行大管棚鉆孔,同
38、時由于重量輕、分解性強(qiáng),便于搬遷,適合于平原或山區(qū)工作。5.2管棚長度控制在25m以內(nèi)(實(shí)際按24m施工)為好。如按設(shè)計(jì)的30m長度進(jìn)行施工,由于管棚過長,鉆孔、下管等工序都費(fèi)時費(fèi)力,效率低下;同時管棚的傾斜度、掉鉆量也很難控制。5.3在粘土含量大的碎石土層中,壓漿效果不理想 。因?yàn)檎惩帘容^密實(shí),漿液不易擴(kuò)散,其擴(kuò)散半徑較小。不能形成一個完整的具有一定厚度的砼加固圈。5.4 建議開挖工作室時,開挖輪廓線不進(jìn)行擴(kuò)大,而是在圍巖開挖后,即初噴35cm厚的混凝土,作為支護(hù),不設(shè)鋼格柵支撐(在確保安全的前提下)。待管棚施工完畢后,再進(jìn)行安設(shè)。這樣可以減少施工投入。5.5大管棚應(yīng)伸入巖石層不少于3m。這樣,在山體滑動時,管棚可以分擔(dān)一部分荷載,從而避免全部荷載都壓在初期支護(hù)上,造成大的下沉和嚴(yán)重變形。 5.6大管棚的接頭必須在縱向上錯開。否則,接頭設(shè)在同一斷面上,極易出現(xiàn)安全隱患。6相關(guān)知識點(diǎn) 6.1采用長度小于10m的小鋼管稱
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 現(xiàn)代商業(yè)房屋買賣合同
- 產(chǎn)品供貨合同范本(32篇)
- 離婚房產(chǎn)協(xié)議書
- 純?nèi)斯趧?wù)分包合同
- 環(huán)保設(shè)備銷售安裝維修服務(wù)合同
- 合伙人股份轉(zhuǎn)讓協(xié)議書
- 居間合同服務(wù)協(xié)議書
- 煤炭銷售居間合同樣本
- 環(huán)境監(jiān)測數(shù)據(jù)服務(wù)平臺供應(yīng)合同
- 房屋征收補(bǔ)償安置協(xié)議書
- 教學(xué)課件-電力系統(tǒng)的MATLAB-SIMULINK仿真與應(yīng)用(王晶)
- GB/T 26189.2-2024工作場所照明第2部分:室外作業(yè)場所的安全保障照明要求
- 新教科版一年級科學(xué)下冊第一單元《身邊的物體》全部課件(共7課時)
- 鹽城江蘇鹽城市住房和城鄉(xiāng)建設(shè)局直屬事業(yè)單位市政府投資工程集中建設(shè)管理中心招聘4人筆試歷年參考題庫附帶答案詳解
- 醫(yī)院教學(xué)秘書培訓(xùn)
- 2025江蘇常州西太湖科技產(chǎn)業(yè)園管委會事業(yè)單位招聘8人歷年高頻重點(diǎn)提升(共500題)附帶答案詳解
- 2025年北京控股集團(tuán)有限公司招聘筆試參考題庫含答案解析
- 小學(xué)教室衛(wèi)生管理
- 信息技術(shù)必修一《數(shù)據(jù)與計(jì)算》第三章第三節(jié)《數(shù)據(jù)分析報(bào)告與應(yīng)用》說課稿
- 體育科學(xué)急救知識
- 工程項(xiàng)目建設(shè)流程
評論
0/150
提交評論