![ta路基邊溝施工方案_第1頁](http://file2.renrendoc.com/fileroot_temp3/2021-10/25/286ebdd2-9747-4899-968c-a6efb930ba65/286ebdd2-9747-4899-968c-a6efb930ba651.gif)
![ta路基邊溝施工方案_第2頁](http://file2.renrendoc.com/fileroot_temp3/2021-10/25/286ebdd2-9747-4899-968c-a6efb930ba65/286ebdd2-9747-4899-968c-a6efb930ba652.gif)
![ta路基邊溝施工方案_第3頁](http://file2.renrendoc.com/fileroot_temp3/2021-10/25/286ebdd2-9747-4899-968c-a6efb930ba65/286ebdd2-9747-4899-968c-a6efb930ba653.gif)
![ta路基邊溝施工方案_第4頁](http://file2.renrendoc.com/fileroot_temp3/2021-10/25/286ebdd2-9747-4899-968c-a6efb930ba65/286ebdd2-9747-4899-968c-a6efb930ba654.gif)
![ta路基邊溝施工方案_第5頁](http://file2.renrendoc.com/fileroot_temp3/2021-10/25/286ebdd2-9747-4899-968c-a6efb930ba65/286ebdd2-9747-4899-968c-a6efb930ba655.gif)
版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請進(jìn)行舉報或認(rèn)領(lǐng)
文檔簡介
1、recovery and treatment in a timely manner. at the time of construction, should be taken to prevent dust and mud spill leak, measures such as the sewage outflow, vehicles stained with dirt, construction waste someone to clean up, to avoid polluting the environment 3.2 night arrangements of noise emit
2、ted by construction equipment, mixer noise emitted by machinery and equipment next to foam for noise control to prevent noise pollution of the surrounding environment. 3.3 construction managers and construction personnel, special operations personnel listing jobs, site operators, leaders, managers,
3、operators, wearing a helmet is divided into red, blue and yellow species. 3.4 site construction and companys comprehensive evaluation, check scores published examination results issued on a regular basis. 4, construction site environmental protection measures in order to protect and improve the livi
4、ng environment and the ecological environment, prevent construction and operation of pollution and nuisance, safeguard the health of residents and workers near the construction area, promoting the development of socialist construction, environmental protection must be the construction site. 4.1 dail
5、y by the deputy project manager, construction, safety officer for the afternoon the second comprehensive self test, where a violation of the provisions of the environment protection in construction site must be promptly identified and corrective action, made by construction workers on the day of the
6、 construction of the log on post records. 4.2 monthly by the department of projects to be checked, according to the environmental protection in construction site inspection, evaluation criteria for inspection score, fill in the score sheet as the basis for site evaluation of safe production and civi
7、lized. during the inspection, do not meet the environmental requirements of the three (people, time, and measures) modification, implementation and review review the duties specified. 4.3 4.3.1 pollution prevention measures in construction site clean up rubbish, used motor vehicle shipments, no free
8、 air dispersion caused by dust. construction of refuse to be cleaned up to a designated location, no feel free to pile up, cleaned up and when adequate water to reduce dust. 4.3.2 earthmoving construction site entrances and set the car wash, and arrange for someone to clean up tire, not wheel dirt i
9、nto other roads, affecting the city clean. 4.3.3 construction road construction site before construction ready plans and setting, make full use of red line layout, arrangement of temporary construction road, grass-roots energising, pavement paving the way coke button, fine aggregate, and water at al
10、l times, reduce road dust. 4.3.4 construction when the protection of urban public facilities have been built, reasonable arrangements within the lot of construction organization, construction on the normal life of the residents and to minimize the impact of leisure. 4.3.5 easy cloud of fine material
11、we will continue to improve the companys internal control system, and steady improvement in ability to manage and control, optimize business processes, to ensure smooth processes, responsibilities in place; to further strengthen internal controls, play a control post independent oversight role of ev
12、aluation complying with third-party responsibility; to actively make use of internal audit tools detect potential management, streamline, standardize related transactions, strengthening operations in accordance with law. deepening the information management to ensure full communication zero resistan
13、ce. to constantly perfect erp, and bfs+, and pi, and mis, and scm, information system based construction, full integration information system, achieved information resources shared; to expand portal system application of breadth and depth, play information system on enterprise of assistant role; to
14、perfect daily run maintenance operation of records, promote problem reasons analysis and system handover; to strengthening bfs+, and erp, and scm, technology application of training, improve employees application information system of capacity and level. humanistic care to ensure zero. to strengthen
15、ing humanities care, continues to foster company wind clear, and gas are, and heart shun of culture atmosphere; strengthening love helped trapped, care difficult employees; carried out style activities, rich employees life; strengthening health and labour protection, organization career health medic
16、al, control career against; continues to implementation psychological warning prevention system, training employees health of character, and stable of mood and enterprising of attitude, created friendly fraternity of humanities environment. to strengthen risk management, ensure that the business of
17、zero risk. to strengthened business plans management, will business business plans cover to all level, ensure the business can control in control; to close concern financial, and coal electric linkage, and energy-saving scheduling, national policy trends, strengthening track, active should; to imple
18、mentation state-owned assets method, further specification business financial management; to perfect risk tube control system, achieved risk recognition, and measure, and assessment, and report, and control feedback of closed ring management, improve risk prevention capacity. to further standardize
19、trading, and strive to achieve according to law, standardize and fair. innovation of performance management, to ensure that potential employees zero fly. to strengthen performance management, process control, enhance employee evaluation and levels of effective communication to improve performance ma
20、nagement. to further quantify and refine employee standards . work, full play party, and branch, and members in five type enterprise construction in the of core role, and fighting fortress role and pioneer model role; to continues to strengthening four good leadership construction, full play levels
21、cadres in enterprise development in the監(jiān)表3-1山東省龍口至青島公路萊西(沈海高速)至城陽段土建工程施工技術(shù)方案報審表承包單位:青島路橋建設(shè)集團有限公司 合同號:一.監(jiān)理單位:海南海通公路工程咨詢監(jiān)理有限公司 編號:.致駐地監(jiān)理工程師: 孫平德先生 現(xiàn)上報 路基邊溝施工方案 施工技術(shù)方案,請予審查和批準(zhǔn)。附件:路基邊溝排水施工方案承包人(簽名): .承包單位(簽章): 年 月 日駐地監(jiān)理工程師意見(附審核記錄):駐地監(jiān)理工程師(簽名): .駐地監(jiān)理工程師辦公室(簽章): 年 月 日recovery and treatment in a timely ma
22、nner. at the time of construction, should be taken to prevent dust and mud spill leak, measures such as the sewage outflow, vehicles stained with dirt, construction waste someone to clean up, to avoid polluting the environment 3.2 night arrangements of noise emitted by construction equipment, mixer
23、noise emitted by machinery and equipment next to foam for noise control to prevent noise pollution of the surrounding environment. 3.3 construction managers and construction personnel, special operations personnel listing jobs, site operators, leaders, managers, operators, wearing a helmet is divide
24、d into red, blue and yellow species. 3.4 site construction and companys comprehensive evaluation, check scores published examination results issued on a regular basis. 4, construction site environmental protection measures in order to protect and improve the living environment and the ecological env
25、ironment, prevent construction and operation of pollution and nuisance, safeguard the health of residents and workers near the construction area, promoting the development of socialist construction, environmental protection must be the construction site. 4.1 daily by the deputy project manager, cons
26、truction, safety officer for the afternoon the second comprehensive self test, where a violation of the provisions of the environment protection in construction site must be promptly identified and corrective action, made by construction workers on the day of the construction of the log on post reco
27、rds. 4.2 monthly by the department of projects to be checked, according to the environmental protection in construction site inspection, evaluation criteria for inspection score, fill in the score sheet as the basis for site evaluation of safe production and civilized. during the inspection, do not
28、meet the environmental requirements of the three (people, time, and measures) modification, implementation and review review the duties specified. 4.3 4.3.1 pollution prevention measures in construction site clean up rubbish, used motor vehicle shipments, no free air dispersion caused by dust. const
29、ruction of refuse to be cleaned up to a designated location, no feel free to pile up, cleaned up and when adequate water to reduce dust. 4.3.2 earthmoving construction site entrances and set the car wash, and arrange for someone to clean up tire, not wheel dirt into other roads, affecting the city c
30、lean. 4.3.3 construction road construction site before construction ready plans and setting, make full use of red line layout, arrangement of temporary construction road, grass-roots energising, pavement paving the way coke button, fine aggregate, and water at all times, reduce road dust. 4.3.4 cons
31、truction when the protection of urban public facilities have been built, reasonable arrangements within the lot of construction organization, construction on the normal life of the residents and to minimize the impact of leisure. 4.3.5 easy cloud of fine materialof backbone backbone role; to full st
32、rengthening members youth work, full play youth employees in company development in the of force role; to improve independent commission against corruption work level, strengthening on enterprise business key link of effectiveness monitored. , and maintain stability. to further strengthen publicity
33、and education, improve the overall legal system. we must strengthen safety management, establish and improve the education, supervision, and evaluation as one of the traffic safety management mechanism. to conscientiously sum up the olympic security controls, promoting integrated management to a hig
34、her level, higher standards, a higher level of development. employees, today is lunar calendar on december 24, the ox bell is about to ring, at this time of year, we clearly feel the pulse of the xx power generation company to flourish, to more clearly hear xx power generation companies mature and s
35、ymmetry breathing. recalling past one another across a railing, we are enthusiastic and full of confidence. future development opportunities, we more exciting fight more spirited. employees, let us together across 2013 full of challenges and opportunities, to create a green, low-cost operation, full
36、 of humane care of a world-class power generation company and work hard! the occasion of the spring festival, my sincere wish that you and the families of the staff in the new year, good health, happy, happy17龍口-青島公路萊西(沈海高速)至城陽段第一合同段路基邊溝施工方案青島路橋建設(shè)集團有限公司龍青高速公路土建一標(biāo)段項目經(jīng)理部龍青高速公路土建一標(biāo)段 路基邊溝施工方案路基邊溝施工方案一、編
37、制依據(jù)1、土建一標(biāo)段兩階段施工圖設(shè)計、山東省高速公路施工標(biāo)準(zhǔn)化建設(shè)指南。2、公路路基施工技術(shù)規(guī)范(jtg f102006)、公路工程質(zhì)量檢驗評定標(biāo)準(zhǔn)第一冊(jtg f80/12004),以及交通部發(fā)布現(xiàn)行的相關(guān)技術(shù)規(guī)范、驗收評定標(biāo)準(zhǔn)。3、公司管理、設(shè)備、技術(shù)力量及綜合施工能力。4、我單位進(jìn)行現(xiàn)場勘查的施工區(qū)域自然因素,沿線交通情況及現(xiàn)場施工條件。 5、上級部門下發(fā)的相關(guān)文件要求。二、 編制原則1、 嚴(yán)格遵照業(yè)主、總監(jiān)辦、駐地辦對土建一標(biāo)段施工質(zhì)量控制、工期控制的原則要求,結(jié)合工程實際進(jìn)行編制。2、嚴(yán)格遵守各有關(guān)設(shè)計圖紙、設(shè)計規(guī)范、施工規(guī)范、安全規(guī)程和質(zhì)量評定與驗收標(biāo)準(zhǔn)。3、嚴(yán)格遵守招標(biāo)文件各項
38、條款要求,認(rèn)真貫徹業(yè)主和監(jiān)理工程師及其授權(quán)人或代表的指示、指令和要求。4、遵循“安全第一”的原則,嚴(yán)格遵照、遵守國家、山東省和當(dāng)?shù)卣P(guān)于施工安全、工地治安人員安全、勞動保護、土地使用與管理及環(huán)境保護等方面的具體規(guī)定和技術(shù)標(biāo)準(zhǔn)。三、工程概況第一合同段起點樁號k67+133,終點樁號k75+470,全長8.337km,有路基、橋涵、路面工程。本合同段全線為雙向四車道高速公路,瀝青混凝土路面,設(shè)計時速為120公里,主線路基全寬為28m,雙向四車道,采用整體式斷面。其橫斷面布置為:0.75米(土路肩)+3.5米(硬路肩)+23.75米(行車道)+0.75米(路緣帶)+3米(中央分隔帶)+0.75米(
39、路緣帶)+ 23.75米(行車道)+3.5米(硬路肩)+0.75米(土路肩),正常路拱為2%,土路肩橫坡為4%。本合同段路基排水工程主要類型有:路堤排水溝、路塹邊溝、路塹滲溝、檢查井、截水溝等。 主要工程量為: 四、施工準(zhǔn)備工作1、管理方面準(zhǔn)備工作認(rèn)真學(xué)習(xí)和掌握合同 條款及國家的各種法律、法規(guī),響應(yīng)招標(biāo)文件的要求,并建立健全各種規(guī)章制度。組織高效精干、管理系統(tǒng)化、規(guī)范化的施工隊伍,選配強有力的指揮領(lǐng)導(dǎo)班子、技術(shù)業(yè)務(wù)人員和施工力量,強化施工隊伍的技術(shù)培訓(xùn)。堅持質(zhì)量第一的指導(dǎo)思想,建立工程質(zhì)量終身制的全面質(zhì)量管理體制,堅持安全第一,確保施工安全。對路基工程配備的施工人員和機械設(shè)備的數(shù)量根據(jù)工程數(shù)量
40、進(jìn)行詳細(xì)優(yōu)化計算,并按照最不利的情況進(jìn)行配備,確保各種資源的合理配備和利用,確保工程進(jìn)度。2、技術(shù)準(zhǔn)備工作 在全面熟悉設(shè)計文件、設(shè)計交底和技術(shù)規(guī)范的基礎(chǔ)上,進(jìn)行現(xiàn)場勘測和施工調(diào)查,對各種場地及施工便道進(jìn)行調(diào)查,以便更好為施工生產(chǎn)服務(wù)。設(shè)立工地試驗室,配備滿足施工需要的試驗檢測儀器和設(shè)備,配足配齊試驗人員,按監(jiān)理工程師要求,建立施工技術(shù)檔案,專人負(fù)責(zé)。施工前進(jìn)行現(xiàn)場施工測量,其內(nèi)容包括導(dǎo)線、中線及高程的復(fù)測,水準(zhǔn)點復(fù)查與增設(shè),橫斷面的測量與繪制等。準(zhǔn)確定出路基中線、坡角、路基邊線以及防護坡道的位置,做好標(biāo)記,標(biāo)明其輪廓。施工中嚴(yán)格復(fù)測、復(fù)核制度,確保填筑位置準(zhǔn)確。(4)施工前選取一處位于工作面中
41、間的位置,整平,用來安置拌和機和施工材料,砂子、水泥存放處要進(jìn)行混凝土硬化。采取集中拌合,拌好的砂漿通過三輪車?yán)┕がF(xiàn)場。3、機械設(shè)備根據(jù)施工進(jìn)度安排合理配制各種機具的進(jìn)場計劃,配齊作業(yè)段所需的挖掘機、運輸車輛、拌合設(shè)備、計量及檢測設(shè)備等,確保機械及檢測儀器的完好。機械設(shè)備見下表:序設(shè)備 名稱規(guī)格型號進(jìn)場進(jìn)場日期性能狀況擬用何處號數(shù)量(臺)1挖掘機cat320d12014年4月31日良好本標(biāo)段2 挖掘機dh300lc-712014年4月31日良好本標(biāo)段3拌和機50l12014年4月31日良好本標(biāo)段4運輸車xs222j22014年4月31日良好本標(biāo)段5發(fā)電機25kw22014年4月31日良好本
42、標(biāo)段6灑水車12014年4月31日良好本標(biāo)段7自卸車52014年4月31日良好本標(biāo)段8三輪車12014年4月31日良好本標(biāo)段檢測設(shè)備見下表:序號儀器設(shè)備名稱規(guī)格型號單 位數(shù) 量1全站儀gpt-3100n臺12全站儀gts-102n臺13水準(zhǔn)儀dsz2臺24水準(zhǔn)儀na728臺15水準(zhǔn)儀sokkic30ii臺16磅秤、臺秤級臺17鋼尺50m把38靠尺2m把2五、施工方法和施工工藝流程1、路塹邊溝施工(1)施工條件 當(dāng)路槽開挖至底部標(biāo)高時(兩側(cè)綠化平臺預(yù)留),依據(jù)圖紙開挖施工縱橫向排水滲溝,路塹邊溝施工和滲溝及滲溝檢查進(jìn)一起施工,且沿著流水面從低往高處施工,預(yù)留一側(cè)綠化平臺。 (2)邊溝構(gòu)造我部路塹
43、邊溝設(shè)計較為復(fù)雜,底部有滲溝及滲溝檢查井,靠路基一側(cè)有約10cm碎石濾水層包邊,緊靠綠化平臺邊溝側(cè)墻每5米設(shè)置一斜度5%的5cmpvc綠化平臺泄水管。邊溝設(shè)計尺寸為:寬度60cm、墻厚40cm、底部厚度30cm、深度根據(jù)地形條件深度約為90cm左右。邊溝構(gòu)造材料:溝底及側(cè)墻為m7.5漿砌片石、側(cè)墻頂蓋以13cm厚c30砼臺帽、蓋板為預(yù)制c30鋼筋砼(15cm厚、50cm寬、86cm長)。(3)施工技術(shù)a、基槽開挖由于開挖基槽為變截面:滲溝基槽及邊溝基槽,所以分兩次開挖較好。開挖時必須從下游向上游開挖,避免在雨天開挖或開挖后被雨水浸泡。第一次開挖:在路槽開挖基本到位后放樣邊溝開挖線,每10m設(shè)置
44、一開挖控制樁,人工配合挖機開挖,本次開挖到滲溝頂處(邊溝流水面下45cm)。本次開挖后不清底。第二次開挖:本次開挖滲溝基槽,必須仔細(xì)到位,避免超挖,杜絕回填,采用小型挖機配合人工進(jìn)行,開挖斷面底部為60cm寬、15cm高矩形,上部為頂寬80cm、底寬60cm的梯形。本次開挖后需對開挖斷面全部進(jìn)行人工休整清理,休整時要按照設(shè)計圖紙及規(guī)范要求修整滲溝,且必須清理全部浮土。 滲溝休整時提前按照滲溝尺寸加工一滲溝框架模型,用直徑12mm的鋼筋按照基槽開挖尺寸加工一個框架,每個休整工人一個,以便使?jié)B溝基槽尺寸滿足設(shè)計及規(guī)范要求。休整完畢后及時進(jìn)行自檢檢查,檢查合格后報監(jiān)理工程師驗收,驗收合格后方可進(jìn)行下
45、步施工。b、滲溝施工滲溝底部為c25鋪底砼厚15cm,做成兩側(cè)向內(nèi)15%的v字形。頂部標(biāo)高要嚴(yán)格按照設(shè)計流水坡進(jìn)行,杜絕產(chǎn)生回流現(xiàn)象。鋪底砼頂部安裝內(nèi)徑為20cm,壁厚為6mm的夾砂玻璃管,玻璃管縱向間隔30cm開孔,外側(cè)包裹滲水土工布,滲水土工布包裹時盡量減少接頭,搭接時寬度必須大于2cm;滲溝外側(cè)必須包裹反濾土工布。滲溝排水管及反濾土工布安設(shè)好后及時用碎石回填,所施工碎石在施工前進(jìn)行篩選和水洗,粒徑為25cm(靠近溝壁處為23cm、靠近排水溝為35cm)。滲溝施工時所用碎石進(jìn)場后必須堆放處地面必須硬化,且必須覆蓋嚴(yán)實,以免污染,土工布和夾砂玻璃管要墊設(shè)且進(jìn)行有效覆蓋,避免雨淋及暴曬。c、m
46、7.5漿砌片石施工材料要求:片石的厚度應(yīng)不小于150mm。用作鑲面的片石,應(yīng)選擇表面較平整、尺寸較大者,應(yīng)稍加修整。片石抗壓強度要求大于30mpa,片石要求質(zhì)地堅硬、密實、耐久、無裂紋、無風(fēng)化,在使用時要沖洗干凈,保證片石的清潔。片石使用前,工地試驗室進(jìn)行強度檢測,并上報試驗監(jiān)理工程師驗收合格后才能使用。砂漿:砂漿所用的水泥、砂、石料均應(yīng)符合規(guī)范要求,通過試驗監(jiān)理工程師的檢測后方能使用。砌筑時所用砂漿為m7.5水泥砂漿,其配合比應(yīng)通過試驗確定,砂漿應(yīng)具有適當(dāng)?shù)牧鲃有院土己玫暮鸵仔?。砂漿采用強制式攪拌機拌制,現(xiàn)場應(yīng)有砂漿配合比及磅秤。水泥及其他材料堆放場地必須進(jìn)行硬化,硬化厚度不小于10cm,堆
47、放距離周圍地面要保持一定高度,且四周必須設(shè)置攔水埂,防止因雨水或潮濕造成水泥浪費。從原材料場地計量磅秤拌和機料斗處必須有運送車行走道路,且道路較為平暢無坡度,片石砌筑:底部厚度30cm,盡量選用大塊片石一層砌筑,側(cè)墻厚度僅為40cm,豎向盡量搭接咬合,砌筑時底部和測量必須一起砌筑,盡量避免分開砌筑,杜絕底部砌石和墻身出現(xiàn)水平接縫。每15m左右預(yù)留一伸縮縫。側(cè)墻砌筑時,一次砌筑到位,頂部最高處不能侵入臺帽。漿砌底部時,最下層砂漿塌落度宜采用高值,坐漿砌筑,坐底片石及時鋪設(shè)。較大的片石應(yīng)用于下層,安砌時應(yīng)選取形狀及尺寸較為合適的片石,尖銳突出部分應(yīng)敲除。豎縫較寬時,應(yīng)在砂漿中塞以小石塊,不得在片石
48、下面用高于砂漿砌縫的小石片支墊。為底部漿砌片石與側(cè)墻片石咬合,宜一次砌筑成型。在鋪底側(cè)墻位置預(yù)留好接茬石,應(yīng)使其體積露出一半左右。砌筑時必須掛線施工,選用的石料應(yīng)質(zhì)地堅硬、不易風(fēng)化、無裂紋。砌筑時,外漏面要預(yù)留2cm左右的空縫備作勾縫之用。砌筑完成后,要對其表面勾縫,勾縫嵌入砌縫內(nèi)2cm深,勾縫寬度為1.2cm1.5cm。勾縫砂漿宜用細(xì)砂,不得過粗,砂漿標(biāo)號應(yīng)高于砌體砂漿標(biāo)號。對已砌筑的漿砌片石,及時覆蓋土工布進(jìn)行灑水養(yǎng)生,保持土工布濕潤,養(yǎng)生期限不少于7天。 d、臺帽施工臺帽高度13cm,寬度40cm,臺帽背墻高度15cm。臺帽施工應(yīng)在墻身砌筑完后及時進(jìn)行,以加強連接,采用組裝好的定型模板一
49、次成型。模板采用竹膠板,模板采用14拉桿螺栓連接,在臺帽中間處設(shè)置一道,外側(cè)采用兩根48鋼管橫向設(shè)置,在模板拼縫處用雙面膠帶,以防止漏漿。e、蓋板安裝邊溝蓋板厚度為15cm,寬度50cm,長度86cm。在小型預(yù)制場集中生產(chǎn),統(tǒng)一安裝。安裝時為使蓋板放置平穩(wěn),應(yīng)在蓋板底部墊設(shè)10mm厚的水泥砂漿。蓋板安裝要求板縫間距均勻。注意在制作、運輸及安裝過程中要求不得損壞蓋板。2、急流槽施工急流槽用于截水溝與路堤邊溝銜接,每級臺階高度30cm,截水溝厚度為30cm,采用m7.5漿砌片石砌筑而成。急流槽根據(jù)地形地勢不同,盡量順勢而成,但是流水坡度盡量采取一致,例如若截水溝土埂基底橫坡陡于1:5時,沿地面開挖
50、0.51.0m寬的臺階。根據(jù)截水溝匯水量不同,截水溝采用形式也不同,i圖用于匯水量較大,匯水坡度較陡的路段;反之采用ii型。急流槽砌筑時從低處向高處逐層逐臺階砌筑,砌筑時必須提前計算臺階數(shù)量,及流水坡度,使之成型美觀。漿砌片石砌筑要求同排水溝要求一樣。 3、路堤排水溝施工路堤排水溝根據(jù)地形不同、地質(zhì)不同、匯水面積不同共有7種型號。i型水溝用于一般填方路段;ii型水溝用于適用于個別排水困難,須將路堤邊溝抬起于地面之上地段;iii型水溝適用于溝底縱坡較緩的填方地段;iv型水溝適用于低洼積水,改河改溝與邊溝公用,排水不暢無出水口地段。v型水溝適用于路基外側(cè)臨水路段,攔水埂高度不小于0.5m;土路段。
51、i、ii、iii、v型排水溝為預(yù)制塊安裝,預(yù)制塊在小型預(yù)制件集中一制作,統(tǒng)一安裝,安裝縫隙要嚴(yán)密均勻,尺寸符合設(shè)計及規(guī)范要求。施工工藝及要求:a、測量放樣按照設(shè)計圖紙或是說明現(xiàn)場準(zhǔn)確放樣,放樣后根據(jù)地形地貌復(fù)核排水溝縱向線性及流水坡度。 b、基槽開挖水溝基槽開挖時必須按照設(shè)計位置及標(biāo)高進(jìn)行,開挖方式采用人工配合挖機。基槽開挖必須仔細(xì)到位,避免超挖欠挖現(xiàn)象,預(yù)留510cm人工清理,休整時要按照設(shè)計圖紙及規(guī)范要求必須清理全部浮土。 人工休整時提前按照邊溝尺寸加工一框架模型,每個休整工人一個,以便使基槽尺寸滿足設(shè)計及規(guī)范要求。休整完畢后及時進(jìn)行自檢檢查,檢查合格后報監(jiān)理工程師驗收,驗收合格后方可進(jìn)行
52、下步施工。c、砂漿墊層施工預(yù)制板安裝或漿砌片石前之前在底部鋪設(shè)砂漿墊層(厚度為4cm或10cm)。因為砂漿墊層部分在斜坡上,因此砂漿塌落度盡可能采用低值,以便在斜坡上更好的施工。鋪設(shè)時必須控制好厚度及平整度,以免保證流水?dāng)嗝娉叽缂邦A(yù)制板安裝。砂漿墊層施工完畢后應(yīng)盡快安裝水溝預(yù)制板。d、預(yù)制板安裝水溝采用c30砼預(yù)制板拼裝而成,預(yù)制板安裝要求接縫要緊密,且縫隙間距均勻,每1020m作為一安裝單元,定位放線,保證線性平順、尺寸滿足設(shè)計要求。e、漿砌片石施工ivvii水溝為m7.5漿砌片石砌筑,砌筑時必須采用定位框架,每1020m作為一施工單元,掛線施工。砌筑要求同路塹邊溝。4、截水溝施工本段截水溝
53、、急流槽工程溝槽開挖采用挖掘機開挖、人工配合清理修整,砂漿用拌和機現(xiàn)場拌制,砌筑用坐漿法砌片石。施工工藝(1)開工前組織施工人員認(rèn)真熟悉設(shè)計文件,進(jìn)行技術(shù)交底,以確保工程質(zhì)量。(2)測量放線:依照經(jīng)監(jiān)理審批的橋線控制點,放出截水溝、急流槽的開挖線,并用石灰標(biāo)出開挖輪廊線,確保超欠挖能控制在允許范圍內(nèi)。(3)溝槽開挖用小斗挖掘機開挖初步成型,人工進(jìn)行掛線修整,開挖過程中樣架嚴(yán)格控制其溝槽尺寸。溝槽開挖至設(shè)計尺寸后,經(jīng)監(jiān)理工程師檢查,其平面位置尺寸大小、地質(zhì)情況均符合設(shè)計要求后,即進(jìn)行下一步施工。(4)砌筑施工采用坐漿法分段砌筑,砂漿飽滿,砂漿經(jīng)拌灰機拌合后,人工挑至漿砌工作面。片石抗壓強度嚴(yán)格控
54、制在30mpa以上,片石厚度不得小于150mm,片石表面較平整,不平整的片石不用于面石砌筑。砂漿用m7.5砂漿,水泥、砂、水等建筑材料均采用經(jīng)檢驗合格的材料,現(xiàn)場拌制的砂漿必須在2小時內(nèi)使用完畢,已凝結(jié)的砂漿嚴(yán)禁使用。砌筑前,對石料必須澆水濕潤,表面有泥土、水銹的石塊,清除干凈后用于施工,砌體每15m設(shè)沉降縫。砌筑順序為先坐漿鋪底石,后砌溝邊,采用分段支樣架掛線,先砌面石,跟隨砌腹石,分層砌筑。砌筑片石時,大面朝下,小面朝上放置以保證砌體穩(wěn)固,石塊之間砌縫控制在20mm,最大不超過40mm,砌塊之間用砂漿填塞飽滿,避免形成瞎縫,用小石頭填塞時,應(yīng)用砂漿包裹石塊固圍,石塊砌縫應(yīng)互相錯開,以免形成
55、通縫。砌筑溝底時,縱坡大于1:4的溝底。 勾縫采用凹縫,勾縫應(yīng)嵌于砌縫內(nèi)20mm深,縫槽深度不足時,必須鑿夠深度后再勾縫。溝頂砌體應(yīng)平順,線條流暢,采用m10號砂漿抹面厚度24cm。砌筑過程及砌筑完工都必須隨時注意澆水養(yǎng)護,完工后養(yǎng)護期保持在7天以上。六、質(zhì)量控制措施1、質(zhì)量目標(biāo)質(zhì)量目標(biāo):本工程一次檢驗合格率100%,優(yōu)良率90%以上,確保工程驗交達(dá)到優(yōu)良標(biāo)準(zhǔn),確保省部級優(yōu)良工程。2、質(zhì)量保證體系針對本合同工程特點和質(zhì)量目標(biāo),建立以項目經(jīng)理為第一責(zé)任人的質(zhì)量保證體系,項目經(jīng)理代表我處對本工程質(zhì)量負(fù)責(zé),各施工隊負(fù)責(zé)人對所承擔(dān)的項目工程質(zhì)量負(fù)責(zé);同時,把工程創(chuàng)優(yōu)目標(biāo)分解到各部門,進(jìn)行方針目標(biāo)管理,
56、并且建立以班組為基礎(chǔ),技術(shù)人員為核心的qc小組,完善全面質(zhì)量管理體系。3、控制措施成立工地試驗室,并配備土工、水質(zhì)、砼、砂漿、鋼材、水泥等試驗所需的儀器設(shè)備,以試驗數(shù)據(jù)作依據(jù),嚴(yán)把原材料質(zhì)量關(guān),達(dá)不到質(zhì)量標(biāo)準(zhǔn)的原材料嚴(yán)禁用于本工程;以試驗結(jié)果指導(dǎo)施工生產(chǎn),尤其要嚴(yán)格砼、砂漿生產(chǎn)時的計量工作,并接受監(jiān)理工程師的指導(dǎo)和檢查。 實行物資采購供應(yīng)責(zé)任制,把好進(jìn)貨和驗收質(zhì)量關(guān),收貨時對材料進(jìn)行嚴(yán)格的質(zhì)量檢查驗收,拒絕接收不符合要求的材料。 加強檢測試驗手段,充分發(fā)揮中心試驗室的技術(shù)優(yōu)勢和職能作用,對原材料、半成品、成品進(jìn)行質(zhì)量檢測,杜絕不符合設(shè)計標(biāo)準(zhǔn)、無產(chǎn)品合格證產(chǎn)品進(jìn)場。 依據(jù)工程材料試驗結(jié)果,對不合格物資必須及時采取隔離、標(biāo)識,以防誤用。 砌石工程中,精心
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 施工方案對工程建設(shè)的經(jīng)濟效益分析
- 跨學(xué)科視角下的情感教育實踐研究
- 音色感知在小學(xué)音樂欣賞中的重要性及其教學(xué)方法
- 藝術(shù)設(shè)計與宗教文化的互動商業(yè)空間的創(chuàng)新之路
- DB3715T 71-2025楊樹退化林修復(fù)技術(shù)規(guī)程
- 二手設(shè)備轉(zhuǎn)讓合同模板
- 2025年雜志宣傳合作協(xié)議(合同)
- 個人房屋買賣合同模板大全
- 二手房銷售合同模板大全
- 個人信用借款擔(dān)保合同范本
- 安全開發(fā)流程培訓(xùn)文件課件
- 三年內(nèi)無重大違法記錄聲明
- 第六章-主成分分析法
- 2024簡單的租房合同樣本下載
- 2025屆浙江省杭州七縣高三第一次調(diào)研測試生物試卷含解析
- 2022版義務(wù)教育(歷史)課程標(biāo)準(zhǔn)(附課標(biāo)解讀)
- 中國慢性腎臟病早期評價與管理指南2023
- 新人教版五年級上冊數(shù)學(xué)應(yīng)用題大全及答案
- 【家庭教育】0-3歲嬰幼兒早教訓(xùn)練方案
- 國家中長期科技發(fā)展規(guī)劃(2021-2035)
- 建筑工人實名制管理制度及實施方案
評論
0/150
提交評論