施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
一、,煉鋼廠除塵管道加檢測孔及平臺,,,,,,,,,,,,,
1,平臺(1)(2)及支架制作,t,0.643,3-8-36,3953.81,315.79,3036.43,,,2542,203.05,1952.42449,,
,扣除主材費,t,0.643,3-8-36,-2605,,,,,-1675,,,,
2,平臺(1)(2)及支架安裝,t,0.643,3-6-25,618.86,167.18,70,,,398,107.50,45.01,,
,安裝加度超30m人工增加費,人工,107.50,,0.3,,,,,32,,,,
3,平臺踏步梯制作,t,0.068,3-8-43,4145.4,495.98,2970.46,,,282,33.73,201.99128,,
,扣除主材費,t,0.068,3-8-43,-2591,,,,,-176,,,,
4,平臺踏步梯安裝,t,0.068,3-6-29,670.96,176.47,71.44,,,46,12.00,4.85792,,
,安裝加度超30m人工增加費,人工,12.00,,0.3,,,,,4,,,,
5,平臺及踏步梯欄桿制作,t,0.33,3-8-44,3758.25,334.37,2929.96,,,1240,110.34,966.8868,,
,扣除主材費,t,0.33,3-8-44,-2552,,,,,-842,,,,
6,平臺及踏步梯欄桿安裝,t,0.33,3-6-33,818.35,213.62,81.74,,,270,70.49,26.9742,,
,安裝加度超30m人工增加費,人工,70.49,,0.3,,,,,21,,,,
7,金屬構件除銹,t,1.041,3-9-1,124.75,94.74,30.01,,,130,98.62,31.24041,,
8,金屬構件刷防銹漆第一遍,t,1.041,3-9-15,195.93,64.09,131.84,,,204,66.72,137.24544,,
9,金屬構件刷防銹漆第二遍,t,1.041,3-9-16,173.52,61.3,112.22,,,181,63.81,116.82102,,
10,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
11,構件安裝高處作業(yè)用25t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
12,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
,安裝高度超過12m人工機械增加費,人+機,39.12,定額說明,0.1,,,,,4,,,,
13,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,安裝高度超過12m人工機械增加費,人+機,35.62,定額說明,0.1,,,,,4,,,,
,直接工程費(A)合計:,,,,,,,,,3714,923,3483.45156,,
,安裝腳手架搭拆費,人+材,4407,,10.00%,,,,,440.66,,,,
,臨時設施費,A,3714,,0.50%,,,,,18.57,,,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,其它措施費,A,3714,,0.47%,,,,,17.45,,,,
,企業(yè)管理費,A,3714,,2.96%,,,,,109.9,,,,
,計:,,,,,,,,,4300.3,,,,
,工程定額測定費,,4300.3,,0.5‰,,,,,2.15,,,,
,利潤,A,3714,,1.50%,,,,,55.7,,,,
,小計:,,,,,,,,,4358,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,39.76,23.22,60,36.78,,,,1462,,,,
,小計:,,,,,,,,,5820,,,,
,稅金:,,,,17.00%,,,,,989,,,,
,工程合計:,,,,,,,,,6810,元,,,
二、,軋鋼除塵管道加檢測孔及平臺,,,,,,,,,,,,,
1,進出風平臺(1)(2)及支架制作,t,0.944,3-8-36,3953.81,315.79,3036.43,,,3732,298.11,2866.38992,,
,扣除主材費,t,0.944,3-8-36,-2605,,,,,-2459,,,,
2,進出風平臺(1)(2)及支架安裝,t,0.944,3-6-25,618.86,167.18,70,,,584,157.82,66.08,,
3,出風口平臺爬梯制作,t,0.11,3-8-43,4145.4,495.98,2970.46,,,456,54.56,326.7506,,
,扣除主材費,t,0.11,3-8-43,-2591,,,,,-285,,,,
4,出風口平臺爬梯安裝,t,0.11,3-6-29,670.96,176.47,71.44,,,74,19.41,7.8584,,
5,平臺欄桿制作,t,0.223,3-8-44,3758.25,334.37,2929.96,,,838,74.56,653.38108,,
,扣除主材費,t,0.223,3-8-44,-2552,,,,,-569,,,,
6,平臺欄桿安裝,t,0.223,3-6-33,818.35,213.62,81.74,,,182,47.64,18.22802,,
7,金屬構件除銹,t,1.277,3-9-1,124.75,94.74,30.01,,,159,120.98,38.32277,,
8,金屬構件刷防銹漆第一遍,t,1.277,3-9-15,195.93,64.09,131.84,,,250,81.84,168.35968,,
9,金屬構件刷防銹漆第二遍,t,1.277,3-9-16,173.52,61.3,112.22,,,222,78.28,143.30494,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
10,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
11,構件安裝用8t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
12,進出風檢測孔DN80管道短節(jié)安裝,10個,0.4,5-3-123,232.99,87.08,,108.5,,93,34.83,,43.4,
13,進出風檢測孔DN80法蘭安裝,副,4,5-3-264,21.74,9.75,,8.06,,87,39.00,,32.24,
,直接工程費(A)合計:,,,,,,,,,4325,1127,4288.67541,,
,安裝腳手架搭拆費,人+材,5416,,10.00%,,,,,541.57,,,,
,臨時設施費,A,4325,,0.50%,,,,,21.63,,,,
,其它措施費,A,4325,,0.47%,,,,,20.33,,,,
,企業(yè)管理費,A,4325,,2.96%,,,,,128.0,,,,
,計:,,,,,,,,,5036.5,,,,
,工程定額測定費,,5036.5,,0.5‰,,,,,2.52,,,,
,利潤,A,4325,,1.50%,,,,,64.9,,,,
,小計:,,,,,,,,,5104,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,48.54,23.22,60,36.78,,,,1785,,,,
,小計:,,,,,,,,,6889,,,,
,稅金:,,,,17.00%,,,,,1171,,,,
,工程合計:,,,,,,,,,8060,元,,,
三、,煉鐵廠1#爐槽下除塵加檢測孔及平臺,,,,,,,,,,,,,
1,進出風平臺(1)(2)及支架制作,t,0.968,3-8-36,3953.81,315.79,3036.43,,,3827,305.68,2939.26424,,
,扣除主材費,t,0.968,3-8-36,-2605,,,,,-2522,,,,
2,進出風平臺(1)(2)及支架安裝,t,0.968,3-6-25,618.86,167.18,70,,,599,161.83,67.76,,
3,進風口平臺踏步梯制作,t,0.158,3-8-43,4145.4,495.98,2970.46,,,655,78.36,469.33268,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,扣除主材費,t,0.158,3-8-43,-2591,,,,,-409,,,,
4,進風口平臺踏步梯安裝,t,0.158,3-6-29,670.96,176.47,71.44,,,106,27.88,11.28752,,
5,平臺及踏步梯欄桿制作,t,0.225,3-8-44,3758.25,334.37,2929.96,,,846,75.23,659.241,,
,扣除主材費,t,0.225,3-8-44,-2552,,,,,-574,,,,
6,平臺及踏步梯欄桿安裝,t,0.225,3-6-33,818.35,213.62,81.74,,,184,48.06,18.3915,,
7,金屬構件除銹,t,1.351,3-9-1,124.75,94.74,30.01,,,169,127.99,40.54351,,
8,金屬構件刷防銹漆第一遍,t,1.351,3-9-15,195.93,64.09,131.84,,,265,86.59,178.11584,,
9,金屬構件刷防銹漆第二遍,t,1.351,3-9-16,173.52,61.3,112.22,,,234,82.82,151.60922,,
10,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
11,構件安裝用8t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
12,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
13,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,4430,1151,4535.54551,,
,安裝腳手架搭拆費,人+材,5687,,10.00%,,,,,568.69,,,,
,臨時設施費,A,4430,,0.50%,,,,,22.15,,,,
,其它措施費,A,4430,,0.47%,,,,,20.82,,,,
,企業(yè)管理費,A,4430,,2.96%,,,,,131.1,,,,
,計:,,,,,,,,,5172.4,,,,
,工程定額測定費,,5172.4,,0.5‰,,,,,2.59,,,,
,利潤,A,4430,,1.50%,,,,,66.4,,,,
,小計:,,,,,,,,,5241,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,49.59,23.22,60,36.78,,,,1824,,,,
,小計:,,,,,,,,,7065,,,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,稅金:,,,,17.00%,,,,,1201,,,,
,工程合計:,,,,,,,,,8266,元,,,
四、,"煉鐵廠K4,K5皮帶機頭除塵加檢測孔及平臺",,,,,,,,,,,,,
1,進出風平臺(1)(2)及支架(腳板)制作,t,0.97,3-8-36,3953.81,315.79,3036.43,,,3835,306.32,2945.3371,,
,扣除主材費,t,0.97,3-8-36,-2605,,,,,-2527,,,,
2,進出風平臺(1)(2)及支架(腳板)安裝,t,0.97,3-6-25,618.86,167.18,70,,,600,162.16,67.9,,
3,進出風平臺踏步梯及腳板制作(2個),t,0.533,3-8-43,4145.4,495.98,2970.46,,,2209,264.36,1583.25518,,
,扣除主材費,t,0.533,3-8-43,-2591,,,,,-1381,,,,
4,進出風平臺踏步梯及腳板安裝(2個),t,0.533,3-6-29,670.96,176.47,71.44,,,358,94.06,38.07752,,
5,進出風平臺支架及踏步梯腳板脹栓打眼,個,24,實際,10,,,,,240,,,,
,脹栓乙方自購主材費,個,24,實際,2.3,,,,,55,,,,
6,進出風平臺及踏步梯欄桿制作,t,0.184,3-8-44,3758.25,334.37,2929.96,,,692,61.52,539.11264,,
,扣除主材費,t,0.184,3-8-44,-2552,,,,,-470,,,,
7,進出風平臺及踏步梯欄桿安裝,t,0.184,3-6-33,818.35,213.62,81.74,,,151,39.31,15.04016,,
8,金屬構件除銹,t,1.687,3-9-1,124.75,94.74,30.01,,,210,159.83,50.62687,,
9,金屬構件刷防銹漆第一遍,t,1.687,3-9-15,195.93,64.09,131.84,,,331,108.12,222.41408,,
10,金屬構件刷防銹漆第二遍,t,1.687,3-9-16,173.52,61.3,112.22,,,293,103.41,189.31514,,
11,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
12,構件安裝用8t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
13,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
14,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,5646,1456,5651.07869,,
,安裝腳手架搭拆費,人+材,7107,,10.00%,,,,,710.71,,,,
,臨時設施費,A,5646,,0.50%,,,,,28.23,,,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,其它措施費,A,5646,,0.47%,,,,,26.54,,,,
,企業(yè)管理費,A,5646,,2.96%,,,,,167.1,,,,
,計:,,,,,,,,,6578.9,,,,
,工程定額測定費,,6578.9,,0.5‰,,,,,3.29,,,,
,利潤,A,5646,,1.50%,,,,,84.7,,,,
,小計:,,,,,,,,,6667,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,62.70,23.22,60,36.78,,,,2306,,,,
,小計:,,,,,,,,,8973,,,,
,稅金:,,,,17.00%,,,,,1525,,,,
,工程合計:,,,,,,,,,10499,元,,,
五、,"煉鐵廠K4,K5皮帶機尾除塵加檢測孔及平臺",,,,,,,,,,,,,
1,進出風平臺(1)(2)及支架(腳板)制作,t,0.762,3-8-36,3953.81,315.79,3036.43,,,3013,240.63,2313.75966,,
,扣除主材費,t,0.762,3-8-36,-2605,,,,,-1985,,,,
2,進出風平臺(1)(2)及支架(腳板)安裝,t,0.762,3-6-25,618.86,167.18,70,,,472,127.39,53.34,,
3,進出風平臺踏步梯及腳板制作(2個),t,0.368,3-8-43,4145.4,495.98,2970.46,,,1526,182.52,1093.12928,,
,扣除主材費,t,0.368,3-8-43,-2591,,,,,-953,,,,
4,進出風平臺踏步梯及腳板安裝(2個),t,0.368,3-6-29,670.96,176.47,71.44,,,247,64.94,26.28992,,
5,進出風平臺支架及踏步梯腳板脹栓打眼,個,24,實際,10,,,,,240,,,,
,脹栓乙方自購主材費,個,24,實際,2.3,,,,,55,,,,
6,進出風平臺及踏步梯欄桿制作,t,0.15,3-8-44,3758.25,334.37,2929.96,,,564,50.16,439.494,,
,扣除主材費,t,0.15,3-8-44,-2552,,,,,-383,,,,
7,進出風平臺及踏步梯欄桿安裝,t,0.15,3-6-33,818.35,213.62,81.74,,,123,32.04,12.261,,
8,金屬構件除銹,t,1.28,3-9-1,124.75,94.74,30.01,,,160,121.27,38.4128,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
9,金屬構件刷防銹漆第一遍,t,1.28,3-9-15,195.93,64.09,131.84,,,251,82.04,168.7552,,
10,金屬構件刷防銹漆第二遍,t,1.28,3-9-16,173.52,61.3,112.22,,,222,78.46,143.6416,,
11,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
12,構件安裝用8t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
13,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
14,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,4600,1136,4289.08346,,
,安裝腳手架搭拆費,人+材,5425,,10.00%,,,,,542.54,,,,
,臨時設施費,A,4600,,0.50%,,,,,23.00,,,,
,其它措施費,A,4600,,0.47%,,,,,21.62,,,,
,企業(yè)管理費,A,4600,,2.96%,,,,,136.2,,,,
,計:,,,,,,,,,5323.2,,,,
,工程定額測定費,,5323.2,,0.5‰,,,,,2.66,,,,
,利潤,A,4600,,1.50%,,,,,69.0,,,,
,小計:,,,,,,,,,5395,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,48.94,23.22,60,36.78,,,,1800,,,,
,小計:,,,,,,,,,7195,,,,
,稅金:,,,,17.00%,,,,,1223,,,,
,工程合計:,,,,,,,,,8418,元,,,
六、,煉鐵廠2#爐槽下除塵加檢測孔及平臺,,,,,,,,,,,,,
1,出風口平臺(1)(2)及支架(腳板)制作,t,0.804,3-8-36,3953.81,315.79,3036.43,,,3179,253.90,2441.28972,,
,扣除主材費,t,0.804,3-8-36,-2605,,,,,-2094,,,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
2,出風口平臺(1)(2)及支架(腳板)安裝,t,0.804,3-6-25,618.86,167.18,70,,,498,134.41,56.28,,
3,出風口平臺踏步梯及腳板制作(2個),t,0.358,3-8-43,4145.4,495.98,2970.46,,,1484,177.56,1063.42468,,
,扣除主材費,t,0.358,3-8-43,-2591,,,,,-928,,,,
4,出風口平臺踏步梯及腳板安裝(2個),t,0.358,3-6-29,670.96,176.47,71.44,,,240,63.18,25.57552,,
5,出風口平臺支架及踏步梯腳板脹栓打眼,個,12,實際,10,,,,,120,,,,
,脹栓乙方自購主材費,個,12,實際,2.3,,,,,28,,,,
6,出風口平臺及踏步梯欄桿制作,t,0.15,3-8-44,3758.25,334.37,2929.96,,,564,50.16,439.494,,
,扣除主材費,t,0.15,3-8-44,-2552,,,,,-383,,,,
7,出風口平臺及踏步梯欄桿安裝,t,0.15,3-6-33,818.35,213.62,81.74,,,123,32.04,12.261,,
8,進風口平臺(3)(4)及支架(腳板)制作,t,1.274,3-8-36,3953.81,315.79,3036.43,,,5037,402.32,3868.41182,,
,扣除主材費,t,1.274,3-8-36,-2605,,,,,-3319,,,,
9,進風口平臺(3)(4)及支架(腳板)安裝,t,1.274,3-6-25,618.86,167.18,70,,,788,212.99,89.18,,
10,進風口平臺踏步梯及腳板制作(2個),t,0.575,3-8-43,4145.4,495.98,2970.46,,,2384,285.19,1708.0145,,
,扣除主材費,t,0.575,3-8-43,-2591,,,,,-1490,,,,
11,進風口平臺踏步梯及腳板安裝(2個),t,0.575,3-6-29,670.96,176.47,71.44,,,386,101.47,41.078,,
12,進風口平臺支架及踏步梯腳板脹栓打眼,個,16,實際,10,,,,,160,,,,
,脹栓乙方自購主材費,個,16,實際,2.3,,,,,37,,,,
13,進風口平臺及踏步梯欄桿制作,t,0.163,3-8-44,3758.25,334.37,2929.96,,,613,54.50,477.58348,,
,扣除主材費,t,0.163,3-8-44,-2552,,,,,-416,,,,
14,進風口平臺及踏步梯欄桿安裝,t,0.163,3-6-33,818.35,213.62,81.74,,,133,34.82,13.32362,,
8,金屬構件除銹,t,3.324,3-9-1,124.75,94.74,30.01,,,415,314.92,99.75324,,
9,金屬構件刷防銹漆第一遍,t,3.324,3-9-15,195.93,64.09,131.84,,,651,213.04,438.23616,,
10,金屬構件刷防銹漆第二遍,t,3.324,3-9-16,173.52,61.3,112.22,,,577,203.76,373.01928,,
11,平臺制作從大庫領料用拖拉機臺班,個,2,實際,160,60,,,,320,120.00,,,
12,構件安裝用8t吊車進出廠一次,次,2,實際,800,60,,,,1600,120.00,,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
13,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
14,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,10796,2811,11146.92502,,
,安裝腳手架搭拆費,人+材,13958,,10.00%,,,,,1395.81,,,,
,臨時設施費,A,10796,,0.50%,,,,,53.98,,,,
,其它措施費,A,10796,,0.47%,,,,,50.74,,,,
,企業(yè)管理費,A,10796,,2.96%,,,,,319.6,,,,
,計:,,,,,,,,,12616.1,,,,
,工程定額測定費,,12616.1,,0.5‰,,,,,6.31,,,,
,利潤,A,10796,,1.50%,,,,,161.9,,,,
,小計:,,,,,,,,,12784,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,121.07,23.22,60,36.78,,,,4453,,,,
,小計:,,,,,,,,,17237,,,,
,稅金:,,,,17.00%,,,,,2930,,,,
,工程合計:,,,,,,,,,20167,元,,,
七、,煉鐵爐前除塵加檢測孔及平臺,,,,,,,,,,,,,
1,進出風平臺(1)(2)及支架制作,t,0.787,3-8-36,3953.81,315.79,3036.43,,,3112,248.53,2389.67041,,
,扣除主材費,t,0.787,3-8-36,-2605,,,,,-2050,,,,
2,進出風平臺(1)(2)及支架安裝,t,0.787,3-6-25,618.86,167.18,70,,,487,131.57,55.09,,
6,進出風平臺欄桿制作,t,0.151,3-8-44,3758.25,334.37,2929.96,,,567,50.49,442.42396,,
,扣除主材費,t,0.151,3-8-44,-2552,,,,,-385,,,,
7,進出風欄桿安裝,t,0.151,3-6-33,818.35,213.62,81.74,,,124,32.26,12.34274,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
8,金屬構件除銹,t,0.938,3-9-1,124.75,94.74,30.01,,,117,88.87,28.14938,,
9,金屬構件刷防銹漆第一遍,t,0.938,3-9-15,195.93,64.09,131.84,,,184,60.12,123.66592,,
10,金屬構件刷防銹漆第二遍,t,0.938,3-9-16,173.52,61.3,112.22,,,163,57.50,105.26236,,
11,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
12,構件安裝用8t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
13,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
14,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,3368,826,3156.60477,,
,安裝腳手架搭拆費,人+材,3983,,10.00%,,,,,398.28,,,,
,臨時設施費,A,3368,,0.50%,,,,,16.84,,,,
,其它措施費,A,3368,,0.47%,,,,,15.83,,,,
,企業(yè)管理費,A,3368,,2.96%,,,,,99.7,,,,
,計:,,,,,,,,,3898.6,,,,
,工程定額測定費,,3898.6,,0.5‰,,,,,1.95,,,,
,利潤,A,3368,,1.50%,,,,,50.5,,,,
,小計:,,,,,,,,,3951,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,35.58,23.22,60,36.78,,,,1309,,,,
,小計:,,,,,,,,,5260,,,,
,稅金:,,,,17.00%,,,,,894,,,,
,工程合計:,,,,,,,,,6154,元,,,
八、,煉鐵原料一號轉運站除塵加檢測孔及平臺,,,,,,,,,,,,,
1,進出風平臺(1)(2)及支架(腳板)制作,t,0.658,3-8-36,3953.81,315.79,3036.43,,,2602,207.79,1997.97094,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,扣除主材費,t,0.658,3-8-36,-2605,,,,,-1714,,,,
2,進出風平臺(1)(2)及支架(腳板)安裝,t,0.658,3-6-25,618.86,167.18,70,,,407,110.00,46.06,,
3,進出風平臺踏步梯制作(2個),t,0.296,3-8-43,4145.4,495.98,2970.46,,,1227,146.81,879.25616,,
,扣除主材費,t,0.296,3-8-43,-2591,,,,,-767,,,,
4,進出風平臺踏步梯安裝(2個),t,0.296,3-6-29,670.96,176.47,71.44,,,199,52.24,21.14624,,
5,進出風平臺支架梯腳板脹栓打眼,個,16,實際,10,,,,,160,,,,
,脹栓乙方自購主材費,個,16,實際,2.3,,,,,37,,,,
6,進出風平臺及踏步梯欄桿制作,t,0.142,3-8-44,3758.25,334.37,2929.96,,,534,47.48,416.05432,,
,扣除主材費,t,0.142,3-8-44,-2552,,,,,-362,,,,
7,進出風平臺及踏步梯欄桿安裝,t,0.142,3-6-33,818.35,213.62,81.74,,,116,30.33,11.60708,,
8,金屬構件除銹,t,1.096,3-9-1,124.75,94.74,30.01,,,137,103.84,32.89096,,
9,金屬構件刷防銹漆第一遍,t,1.096,3-9-15,195.93,64.09,131.84,,,215,70.24,144.49664,,
10,金屬構件刷防銹漆第二遍,t,1.096,3-9-16,173.52,61.3,112.22,,,190,67.18,122.99312,,
11,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
12,構件安裝用8t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
13,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
14,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,4029,993,3672.47546,,
,安裝腳手架搭拆費,人+材,4665,,10.00%,,,,,466.53,,,,
,臨時設施費,A,4029,,0.50%,,,,,20.15,,,,
,其它措施費,A,4029,,0.47%,,,,,18.94,,,,
,企業(yè)管理費,A,4029,,2.96%,,,,,119.3,,,,
,計:,,,,,,,,,4654.3,,,,
,工程定額測定費,,4654.3,,0.5‰,,,,,2.33,,,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,利潤,A,4029,,1.50%,,,,,60.4,,,,
,小計:,,,,,,,,,4717,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,42.76,23.22,60,36.78,,,,1573,,,,
,小計:,,,,,,,,,6290,,,,
,稅金:,,,,17.00%,,,,,1069,,,,
,工程合計:,,,,,,,,,7359,元,,,
九、,燒結礦料倉除塵加檢測孔及平臺,,,,,,,,,,,,,
1,進出風平臺(1)(2)及支架(腳板)制作,t,0.895,3-8-36,3953.81,315.79,3036.43,,,3539,282.63,2717.60485,,
,扣除主材費,t,0.895,3-8-36,-2605,,,,,-2331,,,,
2,進出風平臺(1)(2)及支架(腳板)安裝,t,0.895,3-6-25,618.86,167.18,70,,,554,149.63,62.65,,
3,進出風平臺踏步梯制作(2個),t,0.43,3-8-43,4145.4,495.98,2970.46,,,1783,213.27,1277.2978,,
,扣除主材費,t,0.43,3-8-43,-2591,,,,,-1114,,,,
4,進出風平臺踏步梯安裝(2個),t,0.43,3-6-29,670.96,176.47,71.44,,,289,75.88,30.7192,,
5,進出風平臺支架腳板脹栓打眼,個,16,實際,10,,,,,160,,,,
,脹栓乙方自購主材費,個,16,實際,2.3,,,,,37,,,,
6,進出風平臺及踏步梯欄桿制作,t,0.19,3-8-44,3758.25,334.37,2929.96,,,714,63.53,556.6924,,
,扣除主材費,t,0.19,3-8-44,-2552,,,,,-485,,,,
7,進出風平臺及踏步梯欄桿安裝,t,0.19,3-6-33,818.35,213.62,81.74,,,155,40.59,15.5306,,
8,金屬構件除銹,t,1.515,3-9-1,124.75,94.74,30.01,,,189,143.53,45.46515,,
9,金屬構件刷防銹漆第一遍,t,1.515,3-9-15,195.93,64.09,131.84,,,297,97.10,199.7376,,
10,金屬構件刷防銹漆第二遍,t,1.515,3-9-16,173.52,61.3,112.22,,,263,92.87,170.0133,,
11,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
12,構件安裝用8t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
13,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
14,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,5098,1316,5075.7109,,
,安裝腳手架搭拆費,人+材,6392,,10.00%,,,,,639.17,,,,
,臨時設施費,A,5098,,0.50%,,,,,25.49,,,,
,其它措施費,A,5098,,0.47%,,,,,23.96,,,,
,企業(yè)管理費,A,5098,,2.96%,,,,,150.9,,,,
,計:,,,,,,,,,5937.8,,,,
,工程定額測定費,,5937.8,,0.5‰,,,,,2.97,,,,
,利潤,A,5098,,1.50%,,,,,76.5,,,,
,小計:,,,,,,,,,6017,,,,
,人工費調價,,數量,定額價,市場價格,價差,,,,,,,,
,調價,,56.67,23.22,60,36.78,,,,2084,,,,
,小計:,,,,,,,,,8102,,,,
,稅金:,,,,17.00%,,,,,1377,,,,
,工程合計:,,,,,,,,,9479,元,,,
十、,10m2電除風加檢測孔及平臺,,,,,,,,,,,,,
1,進風口平臺(1)(2)及支架(腳板)制作,t,1.08,3-8-36,3953.81,315.79,3036.43,,,4270,341.05,3279.3444,,
,扣除主材費,t,1.08,3-8-36,-2605,,,,,-2813,,,,
2,進風口平臺(1)(2)及支架(腳板)安裝,t,1.08,3-6-25,618.86,167.18,70,,,668,180.55,75.6,,
3,進風口平臺踏步梯制作(1個),t,0.346,3-8-43,4145.4,495.98,2970.46,,,1434,171.61,1027.77916,,
,扣除主材費,t,0.346,3-8-43,-2591,,,,,-896,,,,
4,進風口平臺踏步梯安裝(1個),t,0.346,3-6-29,670.96,176.47,71.44,,,232,61.06,24.71824,,
5,進風口平臺爬梯制作,t,0.025,3-8-43,4145.4,495.98,2970.46,,,104,12.40,74.2615,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,扣除主材費,t,0.025,3-8-43,-2591,,,,,-65,,,,
6,進風口平臺爬梯安裝,t,0.025,3-6-29,670.96,176.47,71.44,,,17,4.41,1.786,,
7,進風口平臺支架脹栓打眼,個,12,實際,10,,,,,120,,,,
,脹栓乙方自購主材費,個,12,實際,2.3,,,,,28,,,,
8,進風口平臺及踏步梯欄桿制作,t,0.152,3-8-44,3758.25,334.37,2929.96,,,571,50.82,445.35392,,
,扣除主材費,t,0.152,3-8-44,-2552,,,,,-388,,,,
9,進風口平臺及踏步梯欄桿安裝,t,0.152,3-6-33,818.35,213.62,81.74,,,124,32.47,12.42448,,
10,出風口平臺制作,t,0.19,3-8-36,3953.81,315.79,3036.43,,,751,60.00,576.9217,,
,扣除主材費,t,0.19,3-8-36,-2605,,,,,-495,,,,
11,出風口平臺安裝,t,0.19,3-6-25,618.86,167.18,70,,,118,31.76,13.3,,
12,出風口平臺欄桿制作,t,0.045,3-8-44,3758.25,334.37,2929.96,,,169,15.05,131.8482,,
,扣除主材費,t,0.045,3-8-44,-2552,,,,,-115,,,,
13,出風口平臺欄桿安裝,t,0.045,3-6-33,818.35,213.62,81.74,,,37,9.61,3.6783,,
14,金屬構件除銹,t,1.838,3-9-1,124.75,94.74,30.01,,,229,174.13,55.15838,,
15,金屬構件刷防銹漆第一遍,t,1.838,3-9-15,195.93,64.09,131.84,,,360,117.80,242.32192,,
16,金屬構件刷防銹漆第二遍,t,1.838,3-9-16,173.52,61.3,112.22,,,319,112.67,206.26036,,
17,平臺制作從大庫領料用拖拉機臺班,個,1,實際,160,60,,,,160,60.00,,,
18,構件安裝用25t吊車進出廠一次,次,1,實際,800,60,,,,800,60.00,,,
19,進出風檢測孔DN80管道短節(jié)安裝,10個,0.2,5-3-123,232.99,87.08,,108.5,,47,17.42,,21.7,
20,進出風檢測孔DN80法蘭安裝,副,2,5-3-264,21.74,9.75,,8.06,,43,19.50,,16.12,
,直接工程費(A)合計:,,,,,,,,,5829,1532,6170.75656,,
,安裝腳手架搭拆費,人+材,7703,,10.00%,,,,,770.31,,,,
,臨時設施費,A,5829,,0.50%,,,,,29.15,,,,
,其它措施費,A,5829,,0.47%,,,,,27.40,,,,
施工圖預算表,,,,,,,,,,,,,,
工程編號,,,,,,,,,,,,,,
工程名稱:煉鐵、煉鋼、10m2豎爐、軋鋼除塵管道加檢測孔平臺及梯子,,,,,圖號,,,預算編號,,,,,,
序,工程項目名稱,單位,數量,定額編號,單價,其中,,,,總價,其中,,,
號,,,,,,人工費,材料費,機械費,人工日,,人工費,材料費,機械費,人工日
,企業(yè)管理費,A
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業(yè)或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五版泥漿外運承包合同(含應急處理預案)4篇
- 二零二五版拌合料生產技術標準制定與執(zhí)行合同4篇
- 二零二五年度智能建筑暖通設備采購合同4篇
- 二零二五版門閘安全標準認證服務合同4篇
- 二零二五年度網絡安全年薪制勞動合同4篇
- 二零二五年度沖擊錘施工材料質量檢測合同2篇
- 二零二五年度租賃市場合同糾紛解決策略4篇
- 二零二五年度城市更新改造項目規(guī)劃合同4篇
- 二零二五年度農業(yè)電商數據安全與隱私保護合同樣本3篇
- 2025年度二零二五年度獼猴桃出口貿易代理合同3篇
- 2024年供應鏈安全培訓:深入剖析與應用
- 飛鼠養(yǎng)殖技術指導
- 壞死性筋膜炎
- 整式的加減單元測試題6套
- 股權架構完整
- 山東省泰安市2022年初中學業(yè)水平考試生物試題
- 注塑部質量控制標準全套
- 人教A版高中數學選擇性必修第一冊第二章直線和圓的方程-經典例題及配套練習題含答案解析
- 銀行網點服務禮儀標準培訓課件
- 二年級下冊數學教案 -《數一數(二)》 北師大版
- 晶體三極管資料
評論
0/150
提交評論