綜合房建工程項目
端錨式懸挑架施工方案
(格式最終版)
編制:
審核:
批準:
綜合安置用房工程項目端錨式懸挑架施工方案
目錄
第1章編制依據(jù).........................................................................................1
第2章工程概況.........................................................................................2
2.1工程建設(shè)概況一覽表........................................................................2
2.2設(shè)計概況............................................................................................3
2.2.1建筑結(jié)構(gòu)概況.................................................................................................3
2.2.2懸挑架設(shè)計概況.............................................................................................4
2.2.3腳手架材料選擇.............................................................................................7
2.2.4腳手架計算模型選擇.....................................................................................8
2.3工程施工條件....................................................................................8
第3章施工安排.........................................................................................9
3.1項目管理組織....................................................................................9
3.2項目管理目標....................................................................................9
3.3各項資源供應(yīng)方式..........................................................................10
3.3.1勞務(wù)資源安排一覽表...................................................................................10
3.3.2工程用大宗物資供應(yīng)安排一覽表...............................................................10
3.3.3施工周轉(zhuǎn)工具采購供應(yīng)安排一覽表...........................................................10
3.4施工流水段的劃分及施工工藝流程..............................................10
3.4.1施工流水段的劃分.......................................................................................10
3.4.2施工工藝流程...............................................................................................10
3.5工程施工重點和難點分析及應(yīng)對措施..........................................11
3.6新技術(shù)應(yīng)用要求..............................................................................12
第4章施工進度計劃...............................................................................13
第5章施工準備與資源配置計劃...........................................................14
5.1施工準備計劃..................................................................................14
5.1.1技術(shù)準備.......................................................................................................14
I
綜合安置用房工程項目端錨式懸挑架施工方案
5.1.2現(xiàn)場準備.......................................................................................................15
5.2資源配置計劃..................................................................................16
5.2.1勞動力配置計劃...........................................................................................16
5.2.2工程用成品、半成品需要量計劃...............................................................16
5.2.3生產(chǎn)工藝設(shè)備需要量計劃...........................................................................16
5.2.4工程施工主要周轉(zhuǎn)材料配置計劃...............................................................16
5.2.5施工機具配置計劃.......................................................................................17
5.2.6測量設(shè)備配置計劃.......................................................................................17
第6章施工方法及工藝要求...................................................................18
6.1方案及技術(shù)參數(shù)..............................................................................18
6.2施工工藝流程..................................................................................20
6.2.1腳手架搭設(shè)流程...........................................................................................20
6.2.2腳手架拆除流程...........................................................................................22
6.3懸挑細節(jié)部位..................................................................................23
6.3.1常規(guī)部位.......................................................................................................23
6.3.2飄窗部位.......................................................................................................25
6.3.3典型三排立桿部位.......................................................................................26
6.3.4典型四排立桿部位.......................................................................................27
6.3.5典型陽臺/線條處普通工字鋼設(shè)置..............................................................28
6.3.6夾縫處兩側(cè)端錨(無拉桿)設(shè)置...............................................................28
6.4施工要點..........................................................................................29
6.4.1搭設(shè)要求.......................................................................................................29
6.4.2立桿構(gòu)造要求...............................................................................................29
6.4.3縱向水平桿(大橫桿)構(gòu)造要求...............................................................30
6.4.4橫向水平桿(小橫桿)搭設(shè).......................................................................30
6.4.5腳手板搭設(shè)...................................................................................................30
6.4.6掃地桿搭設(shè)...................................................................................................31
6.4.7連墻件搭設(shè)...................................................................................................31
6.4.8門洞搭設(shè).......................................................................................................33
6.4.9剪刀撐與橫向斜撐.......................................................................................34
6.4.10斜(過)道設(shè)置.........................................................................................34
6.4.11防護設(shè)置.....................................................................................................34
II
綜合安置用房工程項目端錨式懸挑架施工方案
6.4.12層間軟硬隔離設(shè)置.....................................................................................36
6.4.13施工電梯部位設(shè)置.....................................................................................36
6.4.14塔吊附墻部位設(shè)置.....................................................................................37
6.5腳手架檢查驗收與交底..................................................................37
6.5.1驗收標準.......................................................................................................37
6.5.2驗收程序.......................................................................................................42
6.5.3驗收內(nèi)容.......................................................................................................43
6.5.4驗收人員.......................................................................................................43
6.6腳手架安全保障措施......................................................................43
6.6.1腳手架搭設(shè)安全技術(shù)措施...........................................................................43
6.6.2注意事項.......................................................................................................47
6.6.3腳手架拆除...................................................................................................47
6.6.4日常監(jiān)測.......................................................................................................48
第7章陽臺設(shè)備平臺處及邊梁無抗扭筋處加強專項措施..................50
第8章各項管理計劃...............................................................................51
8.1綠色施工管理計劃..........................................................................51
8.2進度管理計劃..................................................................................51
8.3質(zhì)量管理計劃..................................................................................51
8.3.1工程施工質(zhì)量分解目標...............................................................................51
8.3.2項目質(zhì)量管理的組織機構(gòu)并明確職責(zé).......................................................52
8.3.3確定質(zhì)量控制點...........................................................................................52
8.3.4現(xiàn)場質(zhì)量管理制度.......................................................................................53
8.3.5質(zhì)量保證措施...............................................................................................54
8.4安全及職業(yè)健康管理計劃..............................................................55
8.4.1職業(yè)健康安全管理目標...............................................................................55
8.4.2現(xiàn)場職業(yè)健康安全管理組織機構(gòu)和職責(zé)分工...........................................55
8.4.3職業(yè)健康安全重大危險源...........................................................................57
8.4.4職業(yè)健康安全資源配置計劃.......................................................................57
8.4.5專項施工安全方案編制計劃.......................................................................58
8.4.6施工現(xiàn)場安全生產(chǎn)管理制度.......................................................................58
III
綜合安置用房工程項目端錨式懸挑架施工方案
8.4.7職業(yè)健康安全保證措施...............................................................................58
8.5成品保護計劃..................................................................................59
8.5.1成品保護管理目標.......................................................................................59
8.5.2成品和設(shè)備保護的組織機構(gòu)與職責(zé)...........................................................59
8.5.3成品和設(shè)備保護的管理制度.......................................................................60
8.5.4成品和設(shè)備保護措施...................................................................................60
第9章應(yīng)急預(yù)案.......................................................................................61
9.1應(yīng)急指揮機構(gòu)及職責(zé)......................................................................61
9.2事故風(fēng)險分析..................................................................................61
9.3應(yīng)急救援程序..................................................................................63
9.4應(yīng)急處置措施..................................................................................63
9.5應(yīng)急物資準備..................................................................................65
9.6應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練..........................................................65
第10章計算書和相關(guān)圖紙.....................................................................68
10.1計算書............................................................................................68
10.1.12250mm懸挑工字鋼(雙排立桿)計算書...............................................68
10.1.22500mm懸挑工字鋼(三排立桿)計算書...............................................68
10.1.33040mm懸挑工字鋼(三排立桿)計算書...............................................68
10.1.43040mm懸挑工字鋼(四排立桿)計算書...............................................68
10.1.53400mm(五立桿)擱置主梁計算書........................................................68
10.1.6大線條處陽臺普通工字鋼(總長4050mm)懸挑計算書......................68
10.1.78#/11#樓北側(cè)設(shè)備平臺普通工字鋼(總長7000mm,加10#槽鋼斜撐)
懸挑計算書.............................................................................................................68
10.1.8南側(cè)飄窗處陽角計算書.............................................................................68
10.2圖紙................................................................................................68
10.2.1FT-11#樓懸挑工字鋼平面布置圖.............................................................68
10.2.2FT-22#樓懸挑工字鋼平面布置圖.............................................................68
10.2.3FT-33#樓懸挑工字鋼平面布置圖.............................................................68
10.2.4FT-44/5/6#樓懸挑工字鋼平面布置圖.......................................................68
IV
綜合安置用房工程項目端錨式懸挑架施工方案
10.2.5FT-57/13#樓懸挑工字鋼平面布置圖........................................................68
10.2.6FT-68#樓懸挑工字鋼平面布置圖.............................................................68
10.2.7FT-711#樓懸挑工字鋼平面布置圖...........................................................68
10.2.8FT-8梁相對標高-1.4部位懸挑架搭設(shè)示意圖.........................................68
10.2.9FT-9剖面圖及節(jié)點詳圖(一)................................................................68
10.2.10FT-10剖面圖及節(jié)點詳圖(二)............................................................68
10.2.11FT-11構(gòu)件詳圖(一)............................................................................68
10.2.12FT-12構(gòu)件詳圖(二)............................................................................68
10.2.13FT-13端錨主梁及拉桿設(shè)置節(jié)點圖........................................................68
10.2.14FT-14螺栓套筒預(yù)埋圖............................................................................68
V
綜合安置用房工程項目端錨式懸挑架施工方案
第1章編制依據(jù)
表1.1-1編制依據(jù)
序號類別文件名稱編號
危險性較大的分部分項工程安全管
1國家行政文件住建部令第37號
理規(guī)定
關(guān)于實施《危險性較大的分部分項
建辦質(zhì)〔2018〕31
2國家行政文件工程安全管理規(guī)定》有關(guān)問題的通
號
知
3國家行政文件建設(shè)工程安全生產(chǎn)管理條例國務(wù)院第393號令
4國家行政文件中華人民共和國安全生產(chǎn)法主席令9屆第70號
建筑施工扣件式鋼管腳手架安全技
5國家行業(yè)規(guī)范JGJ130-2011
術(shù)規(guī)范
6國家行業(yè)規(guī)范建筑施工高處作業(yè)安全技術(shù)規(guī)范JGJ80-2016
7國家行業(yè)規(guī)范施工現(xiàn)場臨時用電安全技術(shù)規(guī)范JGJ46-2005
8國家標準建筑施工腳手架安全技術(shù)統(tǒng)一標準GB51210-2016
9國家標準鋼結(jié)構(gòu)設(shè)計標準GB50017-2017
10國家標準建筑結(jié)構(gòu)可靠性設(shè)計統(tǒng)一標準GB50068-2018
11國家標準建筑結(jié)構(gòu)荷載規(guī)范GB50009-2012
12國家標準建設(shè)工程施工現(xiàn)場供用電安全規(guī)范GB50194-2014
13國家標準鋼結(jié)構(gòu)工程施工質(zhì)量驗收標準GB50205-2020
14國家標準鋼結(jié)構(gòu)工程施工規(guī)范GB50755-2012
15國家標準鋼結(jié)構(gòu)焊接規(guī)范GB50661-2011
16國家行業(yè)規(guī)范建筑施工安全檢查標準JGJ59-2011
建筑施工懸挑式鋼管腳手架安全技
17地方標準DGJ32/J121-2011
術(shù)規(guī)程
18地方標準浙江省扣件式建筑腳手架用鋼管DB33/588-2005
19企業(yè)管理文件技術(shù)質(zhì)量管理手冊CSCEC8SH-JS-2018
ZJQ08-SGJB003-
20企業(yè)技術(shù)標準腳手架安全技術(shù)標準
2017
項目施工合同、施工組織設(shè)計、工
21其他/
程施工圖紙、招投標文件
1
綜合安置用房工程項目端錨式懸挑架施工方案
第2章工程概況
2.1工程建設(shè)概況一覽表
表2.1-1工程建設(shè)概況
工程建設(shè)概況
工程名稱xx綜合安置用房工程工程業(yè)態(tài)
14棟16+1、17+1層住宅,2
寧波市奉化區(qū)方橋區(qū)域,
棟1層公變,1棟1層專變,1-
工程規(guī)模工程地址東環(huán)北路以東,恒興東路
2層商業(yè)用房,1棟1層門衛(wèi)以
以北,恒盛路以南
及1層地下室。
總占地面積53916㎡總建筑面積161555.84㎡
結(jié)構(gòu)形式框架剪力墻結(jié)構(gòu)基礎(chǔ)形式樁承臺基礎(chǔ)
屋面形式平屋面外墻形式真石漆外墻
建設(shè)單位項目承包范圍施工總承包
主體結(jié)構(gòu)、砌筑、抹灰及
設(shè)計單位主要分包工程
其他零星工作
勘察單位質(zhì)量一次性驗收合格
監(jiān)理單位合同工期714日歷天
總承包單位中國建筑第x工程局有限公司要求安全合格
分包單位科技無
工程主要功
地下一層為車庫及工具間,地上為住宅及底層商業(yè)
能或用途
項目場地位于寧波市奉化區(qū)方橋街道東環(huán)北路與恒興東路交叉口東北側(cè),其
南側(cè)約55.50m為恒興東路;西側(cè)約42.4m處為機場路高架;北側(cè)約17.1m為恒盛
路??傆玫孛娣e為53916m2,總建筑面積1615525.84m2,地上建筑面積
115430.81m2,地下建筑面積46125.03m2
地上為18棟高層住宅,1棟1層專變,1-2層商業(yè)用房,1棟1層門衛(wèi),其中
1#~6#為16+1F,建筑高度為50.8m,7#~14#為17+1F,建筑高度為53.7m;地下室
僅1F,為車庫及工具間等。
2
綜合安置用房工程項目端錨式懸挑架施工方案
圖2.1-1項目效果圖
2.2設(shè)計概況
2.2.1建筑結(jié)構(gòu)概況
表2.2-1建筑結(jié)構(gòu)概況
序
項目內(nèi)容
號
地上鋼筋混凝土框架-剪力墻結(jié)構(gòu)
1結(jié)構(gòu)形式地下室鋼筋混凝土框架-剪力墻結(jié)構(gòu)
基礎(chǔ)樁基礎(chǔ)+筏板基礎(chǔ)
2結(jié)構(gòu)設(shè)計使用年限50年
3抗震設(shè)防類別重點設(shè)防類(乙類)
4結(jié)構(gòu)安全等級二級
5地基基礎(chǔ)設(shè)計等級乙級
6建筑抗震設(shè)防類別丙類
7地下室防水等級二級
8人防設(shè)計等級甲類核6常6級
總建
筑面161555.84㎡
積
地下
室高5.4m(地下室僅1F)
度
包含高層
樓棟1#2#3#4#5#6#7#8#9#10#11#12#13#14#
正負4.94.94.94.94.94.94.94.94.94.94.94.94.94.9
零00000000000000
建筑
1717171717171818181818181818
層數(shù)
建筑
50.50.50.50.50.50.53.53.53.53.53.53.53.53.
高度
88888877777777
(m)
3
綜合安置用房工程項目端錨式懸挑架施工方案
圖2.2-1高層住宅結(jié)構(gòu)示意
2.2.2懸挑架設(shè)計概況
本工程施工階段外腳手架采用落地式雙排腳手架+懸挑腳手架的搭設(shè)形式,本
方案僅為1-6#、7#、8#、11#、13#樓型鋼懸挑腳手架設(shè)計及施工方案。本工程外
腳手架主要是作為主體結(jié)構(gòu)施工階段的操作架兼安全維護和裝修階段施工及其維
護,不得用作支模架或其他超載使用。
1、設(shè)計思路
結(jié)合本工程結(jié)構(gòu)特點,以及經(jīng)濟適用,安全可靠應(yīng)充分考慮以下幾點:
(1)架體的結(jié)構(gòu)設(shè)計,力求做到結(jié)構(gòu)要安全可靠,造價經(jīng)濟合理。
(2)選用材料時,力求做到常見通用、可周轉(zhuǎn)利用,便于保養(yǎng)維修。
(3)結(jié)構(gòu)選型時,力求做到受力明確,構(gòu)造措施到位,安拆方便,便于檢查
驗收,鋼管材料進場宜選擇φ48×3.5mm鋼管。
綜合以上幾點,腳手架的搭設(shè),還必須符合JGJ59-2011檢查標準要求,要符
合相關(guān)文明標化工地的有關(guān)標準。
懸挑架由專業(yè)單位制作,進場的挑架有檢測試驗報告、合格證,詳附件。對
進場材料進行驗收。材料驗收內(nèi)容包括:工字鋼梁、鋼板厚度、耳板尺寸、焊縫
質(zhì)量、拉桿、螺桿(螺桿為10.9級高強度等級)。驗收應(yīng)按節(jié)驗收表進行驗收。
2、設(shè)計概況
(1)本工程1#、2#、3#、4#、5#、6#樓為16+1層高層住宅,14層以下搭設(shè)
落地式雙排鋼管扣件腳手架,從14層樓板(標高37.9)開始采用懸挑腳手架,搭
設(shè)至炮樓頂面(標高55.2),高度17.3m。
4
綜合安置用房工程項目端錨式懸挑架施工方案
(2)本工程7#、8#、11#、13#樓為17+1層高層住宅,15層以下搭設(shè)落地式
雙排鋼管扣件腳手架,從15層樓板(標高40.8)開始采用懸挑腳手架,搭設(shè)至炮
樓頂面(標高58.1),高度17.3m。
圖2.2-2端錨上拉式懸挑架示意圖
5
綜合安置用房工程項目端錨式懸挑架施工方案
圖2.2-3懸挑架分段立面圖
表2.2-2腳手架分段表
樓棟架體類型結(jié)構(gòu)樓層及標高搭設(shè)高度備注
落地20m雙鋼管立
樓(標準落地式鋼管腳手架1~13層頂39.6m
1-6#桿
層高2.9m)
第一次懸挑14~炮樓頂17.4m(局端錨式懸挑架
6
綜合安置用房工程項目端錨式懸挑架施工方案
部18.8m)
落地20m雙鋼管立
7#、8#、落地式鋼管腳手架1~14層頂42.5m
11#、13#樓桿
(標準層高17.4m(局
2.9m)第一次懸挑15~炮樓頂端錨式懸挑架
部18.8m)
2.2.3腳手架材料選擇
l、進場搭設(shè)架主材料由專業(yè)廠家加工制作,所有進場搭設(shè)材料均應(yīng)有合格證
和檢驗報告;所有材料必須進場驗收、復(fù)驗。
2、腳手架選用架設(shè)鋼管外徑48mm,壁厚3.5mm,鋼材強度等級Q235-A,鋼
管表面應(yīng)平直光滑,不應(yīng)有裂紋、分層、壓痕、劃道和硬彎,新用的鋼管要有出
廠合格證。腳手架施工前必須將入場鋼管取樣,送有相關(guān)國家資質(zhì)的試驗單位,
進行鋼管抗彎、抗拉等力學(xué)試驗,試驗結(jié)果滿足設(shè)計要求后,方可在施工中使用。
3、本工程鋼管腳手架的搭設(shè)使用可鍛鑄造扣件,應(yīng)符合建設(shè)部《鋼管腳手扣
件標準》JGJ130-2011的要求,由有扣件生產(chǎn)許可證的生產(chǎn)廠家提供,不得有裂紋、
氣孔、縮松、砂眼等鍛造缺陷,扣件的規(guī)格應(yīng)與鋼管相匹配,貼和面應(yīng)平整,活
動部位靈活,夾緊鋼管時開口處最小距離不小于5mm。鋼管螺栓擰緊力矩達
65N.m時不得破壞。如使用舊扣件時,扣件必須取樣送有相關(guān)國家資質(zhì)的試驗單
位,進行扣件抗滑力等試驗,試驗結(jié)果滿足設(shè)計要求后方可在施工中使用。
4、腳手板、腳手片采用符合有關(guān)要求。
5、安全網(wǎng)采用密目式安全網(wǎng),網(wǎng)目應(yīng)滿足2000目/100cm2,做耐貫穿試驗
不穿透,1.6×1.8m的單張網(wǎng)重量在3kg以上,顏色應(yīng)滿足環(huán)境效果要求,選用綠
色。要求阻燃,使用的安全網(wǎng)必須有產(chǎn)品生產(chǎn)許可證和質(zhì)量合格證,以及由建筑
安全監(jiān)督管理部門發(fā)放的準用證。
6、連墻件做法:本工程連墻件采用預(yù)埋鋼管與外架連接的方法。
7、所有挑梁尾端采用螺栓錨固焊接,挑梁均采用Φ24的拉桿斜拉(計算時按Φ
22計算),斜拉上錨固點為框架梁、剪力墻板。長度大于2.25米處斜拉桿采用雙
拉桿。
用件連接的螺栓應(yīng)符合現(xiàn)行國家標準《六角頭螺栓》(GB/T5782)的規(guī)定,
其機械性能應(yīng)符合現(xiàn)行國家標準《緊固件機械性能螺栓、螺釘和螺絲》(GB/T3089)
的規(guī)定。
制作懸挑承力鋼梁等的焊接材料應(yīng)與主體金屬材料的技術(shù)性能相適應(yīng)。手工
焊接采用的焊條,應(yīng)符合現(xiàn)行國家標準《碳鋼焊條》(GB/T5117)和《低合金鋼
焊條》(GB/T5118)的規(guī)定,自動焊和半自動焊所采用的焊絲和焊劑,應(yīng)符合現(xiàn)
行國家標準《埋弧焊用碳鋼焊絲和焊劑》(GB/T5293)和《低合金鋼埋弧焊用焊
劑》(GB/T12470)的規(guī)定。
8、懸挑梁與拉桿采用Φ24銷栓連接(驗算時按Φ22計算)。拉桿與建筑物、
7
綜合安置用房工程項目端錨式懸挑架施工方案
型鋼連接鋼板與建筑物,采用Φ24螺栓連接。
2.2.4腳手架計算模型選擇
結(jié)合本工程結(jié)構(gòu)形式、實際施工特點,構(gòu)筑物四周搭設(shè)落地式結(jié)合懸挑式、
全封閉的扣件式雙排鋼管腳手架。此架為一架二用,既用于裝修施工,同時兼作
安全防護。
各棟樓號懸挑腳手架平面布置圖均在附圖中詳細畫出,詳見附圖。圖中對不
同樓棟、不同規(guī)則尺寸的工字鋼做了分類,具體詳見附圖工字鋼材料統(tǒng)計表。根
據(jù)表中各材料對比,結(jié)合預(yù)埋位置,選取以下部位及長度工字鋼作為計算代表:
(1)大面積采用1.2m、1.3m、1.5m、1.6m、1.7m、1.8m、1.9m、2.0m、
2.1m、2.25m等長度的工字鋼作為懸挑主梁,其上作用2根立桿,選取最不利情況
2.25m進行計算;
(2)部分區(qū)域采用2m、2.1m、2.2m、2.25m、2.5m、2.7m、3.04m等長度的
工字鋼作為懸挑主梁,其上作用3根立桿,選取最不利情況3.04m進行1次計算,
同時為確定雙拉桿設(shè)置界限,選取2.5m進行1次計算;
(注:經(jīng)計算,2.5m主梁單根拉桿計算可通過,但考慮到保險性,特要求>
2.25m主梁需設(shè)置雙拉桿)
(3)部分區(qū)域采用2.9m、3.04m等長度的工字鋼作為懸挑主梁,其上作用4
根立桿,選取最不利情況3.04m進行1次計算;
(4)陽角情況選取1#樓西南側(cè)飄窗部位進行1次計算;
(5)部分大線條處設(shè)置普通懸挑工字鋼作為主梁、單根工字鋼長度4.05m,
進行1次計算;
(6)8#、11#樓北側(cè)設(shè)備平臺處梁過于小,高度僅為350,且未設(shè)計梁底筋,
不便作為端錨懸挑工字鋼錨固端,因此此處設(shè)置普通懸挑工字鋼作為主梁、單根
工字鋼長度7m,進行1次計算;
(7)夾縫處最不利條件為1#樓15-19/J-K軸處,此處兩側(cè)端錨(無拉桿)工
字鋼長度為3.4m,其上設(shè)置5根立桿,此處進行1次計算。
2.3工程施工條件
1、現(xiàn)場施工道路通暢,材料堆場硬化;
2、懸挑架主梁生產(chǎn)單位按圖紙加固成套架體材料;
3、鋼管、扣件及小型安裝設(shè)備齊全;
4、架體搭設(shè)人員三級教育并持證上崗;
5、13層頂(1-6#樓)或14層頂(7#、8#、11#、13#樓)邊梁及柱中預(yù)埋φ26
金屬套管,套管中心距樓板面或梁面200mm。以便拆模板后,安裝懸挑承力鋼梁;
8
綜合安置用房工程項目端錨式懸挑架施工方案
第3章施工安排
3.1項目管理組織
序號管理職務(wù)姓名職稱(資質(zhì))職責(zé)和權(quán)限
項目質(zhì)量、安全、成本、進度的第一責(zé)
1項目經(jīng)理胡建衛(wèi)工程師
任人
負責(zé)型鋼懸挑架施工方案編制,并上報
2項目總工陳琪工程師公司相關(guān)部門履行審批手續(xù),審批完成
后對施工人員進行方案交底。
1、全面負責(zé)懸挑架質(zhì)量的過程監(jiān)督工作。
2、組織對項目管理人員的質(zhì)量教育,提
3質(zhì)量總監(jiān)楊光才工程師高全員質(zhì)量意識。
3、參與懸挑架的質(zhì)量檢查,發(fā)現(xiàn)問題下
達整改通知單,并對整改情況進行驗證。
1、對接地方安全監(jiān)管部門,傳達并督促
工程部落實地方安全監(jiān)管部門對懸挑架
工程的要求。
2、組織懸挑架工程的相關(guān)分包隊伍進行
4安全總監(jiān)麻永吉工程師安全交底。
3、對懸挑架搭設(shè)的過程安全管控。
4、參與對懸挑架工程的驗收。
5、組織懸挑架安裝與拆除的相關(guān)安全工
作。
1、負責(zé)對總包方的工程結(jié)算管理和現(xiàn)場
簽證管理。
5商務(wù)經(jīng)理楊麗君工程師2、負責(zé)對分包方的結(jié)算和簽證管理。
3、按合同約定及時收取工程款。
4、組織項目成本分析,提出改進意見。
負責(zé)懸挑架工程相關(guān)進出場物資的管理。
6物資部經(jīng)理毛凱永工程師組織對型鋼、鋼管、高強螺栓等材料的
進場檢驗驗收。
3.2項目管理目標
項目管理目標名稱目標值
工期滿足合同
質(zhì)量目標一次性驗收合格
安全文明目標合格
綠色施工目標合格
科技目標無
9
綜合安置用房工程項目端錨式懸挑架施工方案
3.3各項資源供應(yīng)方式
3.3.1勞務(wù)資源安排一覽表
施工項目資質(zhì)開始施建設(shè)分包分包商選責(zé)任
專業(yè)施工隊名稱
名稱要求工時間工期方式擇方式人
奉化安置上海德占建筑工程有限主勞毛凱
/2019.5714d招標
房項目公司務(wù)永
奉化安置上海綠驍企業(yè)發(fā)展有限主勞毛凱
/2019.5714d招標
房項目公司務(wù)永
3.3.2工程用大宗物資供應(yīng)安排一覽表
要求進場時
物資名稱采購單位擬選供應(yīng)商采購地點責(zé)任人
間
18#工字鋼承
力梁及配套項目自購/奉化2021.4毛凱永
材料
3.3.3施工周轉(zhuǎn)工具采購供應(yīng)安排一覽表
周轉(zhuǎn)工具名要求進場時計劃出場時
估計數(shù)量提供方式責(zé)任人
稱間間
鋼管66500m租賃2021.42021.9毛凱永
直角扣件72072個租賃2021.42021.9毛凱永
對接扣件9145個租賃2021.42021.9毛凱永
旋轉(zhuǎn)扣件2744個租賃2021.42021.9毛凱永
鋼笆片9750個租賃2021.42021.9毛凱永
3.4施工流水段的劃分及施工工藝流程
3.4.1施工流水段的劃分
表3.4-1腳手架分段表
樓棟架體類型結(jié)構(gòu)樓層及標高搭設(shè)高度備注
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 農(nóng)業(yè)生物多樣性生物技術(shù)考核試卷
- 火力發(fā)電廠安全生產(chǎn)與應(yīng)急預(yù)案考核試卷
- 微生物檢驗實驗設(shè)計應(yīng)該考慮的因素試題及答案
- 2025年【機修鉗工(技師)】模擬考試題及答案
- 消費金融資產(chǎn)質(zhì)量管理與催收策略考核試卷
- 玩具制造業(yè)的綠色制造挑戰(zhàn)考核試卷
- 煉油廠設(shè)備安裝與調(diào)試的技術(shù)要求考核試卷
- 項目決策工具與技術(shù)的運用考核試題及答案
- 磷肥生產(chǎn)過程中的工藝安全評價考核試卷
- 電動機制造中的電機繞組技術(shù)創(chuàng)新考核試卷
- SAP軟件FICO模塊常用增強之一:固定資產(chǎn)的屏幕增強
- 醫(yī)院門診登記本
- 如愿二聲部合唱簡譜文檔
- GB/T 1531-2020銅及銅合金毛細管
- GB/T 12785-2002潛水電泵試驗方法
- 機械制圖國家標準
- 汽車吊起重吊裝方案-
- 陰囊疾病超聲診斷課件
- 信息資產(chǎn)及分級管理程序
- 信用修復(fù)授權(quán)委托書
- 危大工程驗收記錄表(腳手架工程)
評論
0/150
提交評論