項(xiàng)目專項(xiàng)施工方案
錦榮國際2#、3#樓外幕墻工程
施工組織設(shè)計(jì)
編制單位:xx裝飾股份有限公司
編制人:
審核人:
審批人:
日期:
-0-
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù)..............................................................................................................................................1
第二章工程概況..............................................................................................................................................3
2.1工程建設(shè)概況表..............................................................................................................................................3
2.2設(shè)計(jì)概況..........................................................................................................................................................3
幕墻系統(tǒng)類型.....................................................................................................................................................4
2.3工程施工條件..................................................................................................................................................6
第三章施工安排..............................................................................................................................................8
3.1項(xiàng)目管理組織..................................................................................................................................................8
3.2項(xiàng)目管理目標(biāo)..................................................................................................................................................9
3.3各項(xiàng)資源供應(yīng)方式........................................................................................................................................10
3.3.1勞務(wù)資源安排一覽表...........................................................................................................................10
3.3.2工程用大宗物資供應(yīng)安排一覽表........................................................................................................10
3.3.3大型機(jī)械設(shè)備采購供應(yīng)安排一覽表....................................................................................................11
3.4施工流水段的劃分及施工工藝流程............................................................................................................11
3.4.1施工流水段的劃分...............................................................................................................................11
3.4.2施工工藝流程.......................................................................................................................................11
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施........................................................................................................12
3.5.1材料采購的控制...................................................................................................................................12
3.5.2幕墻鋼骨架焊接、防腐的措施及控制................................................................................................13
施工防火的控制.................................................................................................................................14
3.5.4測量放線的控制...................................................................................................................................14
3.5.5隱蔽工程的控制...................................................................................................................................15
3.5.6打膠密封施工的控制...........................................................................................................................15
3.5.7明框幕墻裝飾扣蓋水平、垂直度的控制............................................................................................15
3.5.8幕墻施工安全防護(hù)的管理....................................................................................................................16
第四章施工進(jìn)度計(jì)劃.....................................................................................................................................16
第五章施工準(zhǔn)備與資源配置計(jì)劃..................................................................................................................18
-1-
項(xiàng)目專項(xiàng)施工方案
5.1施工準(zhǔn)備計(jì)劃................................................................................................................................................18
5.1.1技術(shù)準(zhǔn)備...............................................................................................................................................18
5.1.2現(xiàn)場準(zhǔn)備...............................................................................................................................................19
5.2資源配置計(jì)劃................................................................................................................................................20
5.2.1勞動力配置計(jì)劃...................................................................................................................................20
5.2.2工程用原材料需要量計(jì)劃....................................................................................................................20
5.2.3工程用成品、半成品需要量計(jì)劃........................................................................................................20
5.2.4生產(chǎn)工藝設(shè)備需要量計(jì)劃....................................................................................................................20
5.2.5工程施工主要周轉(zhuǎn)材料配置計(jì)劃........................................................................................................21
5.2.6施工機(jī)具配置計(jì)劃...............................................................................................................................21
5.2.7測量計(jì)量儀器配置計(jì)劃.......................................................................................................................21
第六章施工方法及工藝要求..........................................................................................................................23
6.1幕墻吊籃施工................................................................................................................................................23
6.1.1幕墻吊籃概況.......................................................................................................................................23
6.1.2幕墻吊籃施工工藝...............................................................................................................................26
6.1.3吊籃施工注意事項(xiàng)...............................................................................................................................38
6.1.4吊籃施工安全保證措施.......................................................................................................................42
6.2測量放線........................................................................................................................................................47
6.2.1控制部署...............................................................................................................................................47
6.2.2室外控網(wǎng)的布設(shè)...................................................................................................................................48
6.2.3室內(nèi)施工平面控制網(wǎng)的布設(shè)................................................................................................................48
6.2.4高程控制測量.......................................................................................................................................50
6.2.5注意事項(xiàng)...............................................................................................................................................54
6.3埋件施工........................................................................................................................................................56
6.3.1預(yù)埋件施工...........................................................................................................................................56
6.3.2后置埋件施工.......................................................................................................................................58
6.4玻璃幕墻系統(tǒng)施工........................................................................................................................................61
6.4.1玻璃幕墻系統(tǒng)介紹...............................................................................................................................61
6.4.2施工前準(zhǔn)備工作...................................................................................................................................63
6.4.3施工工藝流程.......................................................................................................................................65
-2-
項(xiàng)目專項(xiàng)施工方案
6.4.4施工要點(diǎn)...............................................................................................................................................66
6.5鋁板幕墻施工................................................................................................................................................72
6.5.1鋁板幕墻系統(tǒng)介紹...............................................................................................................................72
6.5.2施工工藝流程.......................................................................................................................................73
6.5.3施工要點(diǎn)...............................................................................................................................................73
6.6鋁合金門窗系統(tǒng)施工....................................................................................................................................79
6.6.1施工工藝流程.......................................................................................................................................79
6.6.2工藝說明...............................................................................................................................................82
6.6.3質(zhì)量控制及質(zhì)量要求...........................................................................................................................83
6.7防雷施工........................................................................................................................................................84
6.7.1防雷安裝工藝概述...............................................................................................................................84
6.7.2防雷安裝...............................................................................................................................................84
6.8鋁板雨棚系統(tǒng)施工........................................................................................................................................86
6.8.1施工工藝流程.......................................................................................................................................86
6.8.2施工要點(diǎn)...............................................................................................................................................86
6.9幕墻防火施工................................................................................................................................................87
6.9.1幕墻防火設(shè)計(jì).......................................................................................................................................87
6.9.2層間防火施工工藝...............................................................................................................................87
第七章進(jìn)度管理計(jì)劃.....................................................................................................................................88
7.1確定施工進(jìn)度控制點(diǎn)....................................................................................................................................89
7.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工............................................................................................................89
7.3進(jìn)度管理措施................................................................................................................................................89
第八章質(zhì)量管理計(jì)劃.....................................................................................................................................93
8.1質(zhì)量控制目標(biāo)分解........................................................................................................................................93
8.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工................................................................................................................93
8.3確定質(zhì)量控制點(diǎn)............................................................................................................................................94
8.4質(zhì)量保證措施................................................................................................................................................94
第九章安全管理計(jì)劃...................................................................................................................................108
9.1職業(yè)健康安全管理分解目標(biāo)......................................................................................................................108
-3-
項(xiàng)目專項(xiàng)施工方案
9.2安全管理組織機(jī)構(gòu)和職責(zé)分工..................................................................................................................108
9.3職業(yè)健康安全重大危險(xiǎn)源..........................................................................................................................108
9.4職業(yè)健康安全資源配置計(jì)劃......................................................................................................................109
9.5安全生產(chǎn)管理制度......................................................................................................................................109
9.6安全生產(chǎn)保證措施......................................................................................................................................110
第十章環(huán)境管理計(jì)劃...................................................................................................................................147
10.1環(huán)境管理目標(biāo)............................................................................................................................................147
10.2環(huán)境管理組織機(jī)構(gòu)和職責(zé)分工................................................................................................................147
10.3重大環(huán)境因素清單....................................................................................................................................147
10.4環(huán)境保護(hù)資源配置計(jì)劃............................................................................................................................147
10.5環(huán)境保護(hù)措施............................................................................................................................................148
10.6噪聲污染控制措施..................................................................................................................................148
10.7光污染控制措施........................................................................................................................................148
10.8周邊地下管線及建筑物、綠化帶保護(hù)措施..............................................................................................149
10.9施工廢棄物處理.........................................................................................................................................150
第十一章綠色施工管理計(jì)劃........................................................................................................................151
11.1綠色施工組織機(jī)構(gòu)和職責(zé)分工................................................................................................................151
11.2綠色施工實(shí)施措施....................................................................................................................................151
11.3綠色施工評價(jià)............................................................................................................................................152
第十二章成品保護(hù)管理計(jì)劃........................................................................................................................152
12.1成品保護(hù)管理組織和職責(zé)分工................................................................................................................152
12.2成品保護(hù)計(jì)劃及保證措施........................................................................................................................152
12.2.1生產(chǎn)加工階段成品保護(hù)措施............................................................................................................152
12.2.2包裝階段成品保護(hù)措施...................................................................................................................156
12.2.3運(yùn)輸過程中成品保護(hù)措施...............................................................................................................157
12.2.4裝卸過程中的成品保護(hù)措施............................................................................................................159
12.2.5現(xiàn)場存儲的成品保護(hù)措施...............................................................................................................159
12.2.6施工過程中的成品保護(hù)措施............................................................................................................161
12.2.7施工完成后幕墻的保護(hù)...................................................................................................................162
-4-
項(xiàng)目專項(xiàng)施工方案
第十三章應(yīng)急預(yù)案.......................................................................................................................................164
13.1事故類型和危害程度分析........................................................................................................................164
13.2組織機(jī)構(gòu)及職責(zé)分工................................................................................................................................164
13.3預(yù)防與預(yù)警................................................................................................................................................164
13.3.1危險(xiǎn)源監(jiān)控.......................................................................................................................................165
13.3.2預(yù)警行動...........................................................................................................................................165
13.4信息報(bào)告程序............................................................................................................................................167
13.5應(yīng)急處置....................................................................................................................................................167
13.5.1相應(yīng)分級...........................................................................................................................................167
13.5.2響應(yīng)程序...........................................................................................................................................168
13.5.3處置措施...........................................................................................................................................168
第十四章計(jì)算書和相關(guān)圖紙..........................................................................................................................174
14.1吊籃專項(xiàng)方案計(jì)算書................................................................................................................................174
14.2吊籃布置圖................................................................................................................................................187
14.3吊籃搭設(shè)示意圖........................................................................................................................................188
附圖......................................................................................................................................................................190
-5-
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
序號類別文件名稱編號
1建筑工程安全生產(chǎn)管理?xiàng)l例國務(wù)院令第393號
中華人民共和國住
國家行政文件危險(xiǎn)性較大的分部分項(xiàng)工程安
2房和城鄉(xiāng)建設(shè)部令
全管理規(guī)定
第37號文
3建筑幕墻GB/T21086-2007
建筑幕墻氣密、水密、抗風(fēng)壓
4GB/T15227-2007
性能檢測方法
5金屬與石材幕墻工程技術(shù)規(guī)范JGJ133-2001
6玻璃幕墻工程技術(shù)規(guī)范JGJ102-2003
7建筑玻璃應(yīng)用技術(shù)規(guī)程JGJ113-2015
8高層民用建筑鋼結(jié)構(gòu)技術(shù)規(guī)程JGJ99-2015
9混凝土結(jié)構(gòu)后錨固技術(shù)規(guī)程JGJ145-2013
10硅酮和改性硅酮建筑密封膠GB/T14683-2017
11工程測量規(guī)范GB50026-2007
12建筑結(jié)構(gòu)荷載規(guī)范GB50009-2012
建筑裝飾裝修工程質(zhì)量驗(yàn)收規(guī)
13GB50210-2018
范
建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)
14GB50300-2013
準(zhǔn)
國家行業(yè)規(guī)范
建筑節(jié)能工程施工質(zhì)量驗(yàn)收規(guī)
15GB50411-2007
范
16玻璃幕墻工程質(zhì)量檢驗(yàn)標(biāo)準(zhǔn)JGJ/T139-2001
17建筑施工安全檢查標(biāo)準(zhǔn)JGJ59-2011
施工現(xiàn)場臨時用電安全技術(shù)規(guī)
18JGJ46-2005
范
建設(shè)工程施工現(xiàn)場消防安全技GB50720-2011
19
術(shù)規(guī)范
建筑施工高處作業(yè)安全技術(shù)規(guī)
20JGJ80-2016
范
建筑施工工具式腳手架安全技
21JGJ202-2010
術(shù)規(guī)范
22高處作業(yè)吊籃GB/T19155-2017
施工現(xiàn)場機(jī)械設(shè)備檢查技術(shù)規(guī)
23JGJ160-2016
范
1
項(xiàng)目專項(xiàng)施工方案
24錦榮國際工程幕墻施工合同/
合同
25錦榮國際工程施工總承包合同/
26錦榮國際工程幕墻施工圖紙/
設(shè)計(jì)文件
27錦榮國際工程施工圖紙/
28招投標(biāo)文件錦榮國際工程幕墻招投標(biāo)文件/
29質(zhì)量管理制度/
企業(yè)管理文件
30總承包管理實(shí)施指南/
2
項(xiàng)目專項(xiàng)施工方案
第二章工程概況
2.1工程建設(shè)概況表
工程名稱工程性質(zhì)公用建筑
建設(shè)規(guī)模27743.34萬元工程地址
總占地面積46801.44㎡總建筑面積243501.35㎡
主體工程、發(fā)包人分包土方工程范圍
外的土方開挖清理;土方回填等、防
項(xiàng)目承包范
建設(shè)單位水工程、樓內(nèi)二次結(jié)構(gòu)、內(nèi)裝飾工程、
圍
門窗工程、水電安裝工程、弱電工程
等
主要分包工
設(shè)計(jì)單位2#、3#樓幕墻
程
勘察單位質(zhì)量合格
合同
監(jiān)理單位工期180天
要求
總承包單位安全鄭州市安全文明工地
工程主要功本工程地下兩層,主要為車庫和設(shè)備用房,地上共有7棟單體,其
能或用途中1#~3#樓為商業(yè)型公寓樓,5#、6#樓為辦公樓、7#、8#樓為商業(yè)樓。
2.2設(shè)計(jì)概況
建筑高度:
標(biāo)高
樓號建筑層數(shù)幕墻裝飾高度
2#1159.74米
3#1158.70米
建筑主體結(jié)構(gòu)形式:建筑主體結(jié)構(gòu)形式為框架-剪力墻結(jié)構(gòu),裙房為框架結(jié)構(gòu)
建筑所在區(qū)域的地面粗糙度類型:C類
基本風(fēng)壓:W0=0.45KN/m2;基本雪壓:S0=0.4KN/m2;
設(shè)計(jì)等級要求:幕墻結(jié)構(gòu)的安全等級為二級,結(jié)構(gòu)設(shè)計(jì)使用年限25年(預(yù)
埋件設(shè)計(jì)使用年限50年,后置埋件設(shè)計(jì)使用年限30年),建筑耐火等級一級,
為二類防雷建筑物;
建筑物抗震設(shè)防烈度:7度重點(diǎn)設(shè)防設(shè)計(jì)基本地震加速度值0.1g,設(shè)計(jì)
地震分組第二組;場地類別:Ⅱ類;
本工程各建筑物用途及類別:
3
項(xiàng)目專項(xiàng)施工方案
該項(xiàng)目是豫發(fā)集團(tuán)在空港CBD打造的首個商務(wù)綜合體項(xiàng)目,集精品酒店、5A
甲級寫字樓、LOFT公寓(挑高5.09米)、精裝酒店式公寓、商業(yè)于一體的商務(wù)
綜合體項(xiàng)目,總占地70.2畝,總建筑面積24.35萬㎡,地上建筑面積15.92萬
㎡,分別由1#樓、2#樓、3#樓、5#樓、6#樓、7#樓、8#樓組成
工程范圍及幕墻形式:玻璃幕墻、鋁板幕墻、鋁合金格柵、穿孔鋁板、室內(nèi)
欄桿等。
我司二標(biāo)段施工范圍:錦榮國際外立面2#、3#樓幕墻工程。
幕墻概況:
本工程幕墻型式主要為玻璃幕墻和鋁板幕墻,玻璃和鋁板頂兼有鋁合金格柵、
百葉等,2#和3#樓均由裙樓和塔樓組成。
2.2.1幕墻系統(tǒng)類型
系統(tǒng)類別幕墻系統(tǒng)說明
玻璃幕墻立面,明隱框結(jié)合形式。玻璃通過結(jié)構(gòu)膠及鋁框連接
在主體鋼結(jié)構(gòu)上,面材采用6mm(LOW-E)+12A+6mm中空鋼化玻璃,
系統(tǒng)1:玻璃顏色根據(jù)建筑師和業(yè)主封樣確定;豎向龍骨采用140x70x2.5mm
幕墻(主樓位鋁合金立柱,層間采用雙支點(diǎn)鏈接(12.6#槽鋼、M12*120不銹
置)鋼螺栓組),梁間采用2.0mm鋁單板做背襯板;型材室外可視
面采用氟碳噴涂處理,室內(nèi)可視面采用粉末噴涂處理,不可視
面采用陽極氧化處理,顏色根據(jù)建筑師和業(yè)主封樣確定;
本工程裙樓玻璃幕墻采用明框效果,合金牌號及狀態(tài)號為
6063-T5,采用了標(biāo)準(zhǔn)的明框玻璃幕墻的做法,明框裝飾條正面
尺寸為70mm,出玻璃面25mm。立柱采用140x70x2.5mm鋁合金
立柱;橫梁為80*80鋁合金型材;橫梁與立柱彈簧銷固定,鋁
系統(tǒng)2:玻璃型材室外可視面采用氟碳噴涂處理,室內(nèi)可視面采用粉末噴涂
幕墻(裙樓位處理,不可視面采用陽極氧化處理,顏色根據(jù)建筑師和業(yè)主封
置)樣確定,梁間采用2.0mm鋁單板做背襯板;面材根據(jù)不同功能
分別采用10mm(超白LOW-E)+12A+10mm(超白)中空鋼化玻璃、
10mm(超白LOW-E)+12A+10mm(超白)浮點(diǎn)玻璃、8mm(超白
LOW-E)+12A+8mm中空鋼化玻璃、8mm(超白LOW-E)+12A+8mm(超
白)中空鋼化玻璃(以上均有業(yè)主封樣)等;
本工程裙樓鋁合金格柵幕墻,立柱采用80x40x5mm厚熱鍍鋅鋼
系統(tǒng)3:裙樓
龍骨;鋁合金型材邊框,兩側(cè)與豎向鋼管鏈接,下上用鍍鋅鐵
鋁合金格柵
皮固定,邊框與格柵用不銹鋼螺絲鏈接固定;
4
項(xiàng)目專項(xiàng)施工方案
系統(tǒng)類別幕墻系統(tǒng)說明
首層門為有框鋁合金地彈門,門扇玻璃為6mm(超白
LOW-E)+12A+6mm(超白)中空鋼化玻璃,地彈門的門扇的左右邊
系統(tǒng)4:鋁合框和上邊框的寬度做成一致,為100mm,下邊框的寬度做到250mm。
金地彈門門拉手采用通高拉手,拉手采用Φ38x2.5mm斷絲不銹鋼管,通
過8mm厚的不銹鋼片與上下框固定(門拉手封樣確定)。門扇
四周的縫隙必須裝防塵毛刷。地面至門框頂高2.7m;
個別立面使用鋁合金平開門,地面至門框頂高2.7m。玻璃為
6mm(超白LOW-E)+12A+6mm(超白)。鋁合金地彈門選55系列隔熱
系統(tǒng)5:鋁合
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五年度倉儲物流供應(yīng)鏈管理與運(yùn)輸服務(wù)合同3篇
- 2024版土地免租租賃合同范本
- 二零二五年度旋挖鉆機(jī)在城市地鐵建設(shè)中的應(yīng)用合同3篇
- 二零二五年度豪華家裝主材代購服務(wù)協(xié)議3篇
- 專業(yè)版融資擔(dān)保協(xié)議2024年版詳盡條款一
- 2024年電商渠道聯(lián)合運(yùn)營協(xié)議版B版
- 二零二五年度甲乙雙方合作供應(yīng)新能源設(shè)備協(xié)議2篇
- 二零二五版汽車行業(yè)人才培訓(xùn)股份購買與就業(yè)服務(wù)合同3篇
- 2024新疆瓜果種植基地與電商平臺合作分紅協(xié)議3篇
- 二零二五版礦產(chǎn)廢石采購及再生利用合作協(xié)議3篇
- 米-伊林《十萬個為什么》閱讀練習(xí)+答案
- 碎屑巖油藏注水水質(zhì)指標(biāo)及分析方法
- 【S洲際酒店婚禮策劃方案設(shè)計(jì)6800字(論文)】
- 醫(yī)養(yǎng)康養(yǎng)園項(xiàng)目商業(yè)計(jì)劃書
- 《穿越迷宮》課件
- 《C語言從入門到精通》培訓(xùn)教程課件
- 2023年中國半導(dǎo)體行業(yè)薪酬及股權(quán)激勵白皮書
- 2024年Minitab全面培訓(xùn)教程
- 社區(qū)電動車棚新(擴(kuò))建及修建充電車棚施工方案(純方案-)
- 項(xiàng)目推進(jìn)與成果交付情況總結(jié)與評估
- 鐵路項(xiàng)目征地拆遷工作體會課件
評論
0/150
提交評論