1、NZQA registered unit standard2030 version 5Page 4 of 4TitleSchedule and manage preventative maintenance for electrical equipmentLevel5Credits6PurposeThis unit standard is for people in the electrical industry who have responsibility for the development and management of a preventative maintenance pr

2、ogramme for electrical equipment. such programmes are typically used in factories and industrial plants to keep the electrical equipment operating safely and efficiently, minimising unplanned interruptions to production.people credited with this unit standard are able to:develop a preventative maint

3、enance schedule for electrical;manage a preventative maintenance programme for electrical equipment.ClassificationElectrical Engineering > Electrical Installation and MaintenanceAvailable gradeAchievedExplanatory notes1This unit standard has been developed for learning and assessment on-job.2Refe

4、rencesElectricity Act 1992;Electricity (Safety) Regulations 2010;Health and Safety in Employment Act 1992;AS/NZS 3000:2007, Electrical installations (known as the Australian/New Zealand Wiring Rules), including Amendment 1;and all subsequent amendments and replacements.3DefinitionsThe term current r

5、egulations and standards is used in this unit standard to refer to the requirements of the above references.Electrical equipment any equipment, plant, or machinery powered by electricity, and which periodically requires attention in the form of inspection, adjustment, measurement, tuning, overhaul,

6、component replacement, lubrication, or cleaning, so that it may continue to operate safely and efficiently, and in compliance with any legislative requirements.4The maintenance schedule may be a manual paper-based system, or in the form of a computer database. The unit standard is not intended to be

7、 used for assessing computer programming of such a system.Outcomes and evidence requirementsOutcome 1Develop a preventative maintenance schedule for electrical equipment.Evidence requirements1.1Location and equipment drawings, manuals, maintenance records, and specifications are filed in an orderly

8、and systematic fashion.1.2An inventory of electrical equipment in the installation is obtained and/or prepared according to requirements.Rangetypically the inventory will contain item, type, plant number, serial number, model, rating, location, installation date.1.3Preventative maintenance schedule

9、is developed for each item of equipment according to requirements.Rangedevelopment is typically based on information from equipment inventory, manuals, manufacturers specifications, current regulations and standards, plant operating/shut-down schedules, shut-down procedures, past maintenance records

10、, knowledge of safe working practices;a typical schedule will list equipment identification, frequency of maintenance, due date, type of maintenance, reference to instructions and/or checklists, location of spares, special requirements.1.4The schedule incorporates or interfaces with a system of init

11、iating, allocating to available resources, tracking progress, and recording results and costs of maintenance work in accordance with company requirements.1.5An inventory of spare parts is developed from manufacturers' recommendations.Rangetypically this would include type of spare, quantity held

12、 locally, location, re-order level, supplier, cost.1.6The schedule allows for reviews arising from upgrade information from manufacturers.Outcome 2Manage a preventative maintenance programme for electrical equipment.Evidence requirements2.1Trades and other personnel are organised to meet scheduled m

13、aintenance requirements.2.2Shut-down times and periods are arranged to meet the maintenance schedule and other company requirements.2.3Maintenance work is completed in accordance with the maintenance schedule.2.4Maintenance documentation is completed according to the requirements of the maintenance

14、schedule and related company systems.Rangedocumentation may include but is not limited to progress tracking on maintenance charts or programme, follow-up work instructions or recommendations, recording results of tests and measurements, site safety clearances, certifications, reports to management,

15、recording of time and costs.Planned review date31 December 2014 Status information and last date for assessment for superseded versionsProcessVersionDateLast Date for AssessmentRegistration122 April 199431 December 2013Review223 April 199631 December 2013Review328 June 199931 December 2013Review426

16、May 200531 December 2013Rollover and Revision515 March 2012N/AConsent and Moderation Requirements (CMR) reference0003This CMR can be accessed at t.nz/framework/search/index.do.Please noteProviders must be granted consent to assess against standards (accredited) by NZQA, before they

17、 can report credits from assessment against unit standards or deliver courses of study leading to that assessment.Industry Training Organisations must be granted consent to assess against standards by NZQA before they can register credits from assessment against unit standards.Providers and Industry

18、 Training Organisations, which have been granted consent and which are assessing against unit standards must engage with the moderation system that applies to those standards.Requirements for consent to assess and an outline of the moderation system that applies to this standard are outlined in the Consent and Moderation Requirements (CMR). The CMR also includes useful information about special requirements for organisations wishing to develop education and training programmes, such as minimum qualifications for tutors and assessors, and special resource requirements.Com

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
  • 4. 未經(jīng)權益所有人同意不得將文件中的內容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
  • 6. 下載文件中如有侵權或不適當內容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

評論

0/150

提交評論