1、TECHNICAL SPECIFICATIONS FORINSTALLATION OF MECHNICAL EQUIPMENT11.1HIGHLIGHTS OF CONSTRUCTIONConstruction preconditions of Equipment InstallationThe design document and other technical documents are all ready, the construction drawings have been jointly checked up, technique clarification and necess
2、ary technical training shall have been accomplished.Relative foundation and trench work shall have been finished, the concrete strengthshall not be lower than 75% of design strength.1.21.2.11.2.2Acceptance of Equipment FoundationAcceptance of Civil DataQuality certificate.Survey Record and other con
3、struction data shall be ready.Foundation checkingThe position, geometry dimension and quality requirements of the equipment foundation shall comply with the construction drawings and the Code for Construction and Acceptance of Concrete Structures (GB50204-92).Both the foundation surface of the equip
4、ment and the reserved holes of anchor boltsshall be cleaned up, the screw thread and the nut of the embeddedanchor bolt shallbe kept in good condition.The allowable tolerance of equipment foundation dimensions refer to table 1:Table 1ItemsAllowable Tolerance (mm)Coordinate position (Longitudinal & t
5、ransverse)20Elevation of different plane20Plane outline dimension20Plane outline dimension of protruding platform20Dimension of concave hole20Levelness of planePer meter5(Including parts where equipmentwould be installed on the levelground)Total length10PlumbnessPer meter5Total length10Elevation (to
6、p)20Center-to-centerEmbedded anchor bolt( from the top to the2bottom)Central position10Depth20Embedded anchor bolt holePlumbness of theinternal surface of10the hole per meterElevation20Embedded anchor bolt activeCentral position5anchor plateLevelness (anchorboard with slot) per5meterLevelness (ancho
7、r board with screw threaded hole) per meter21.3Unpacking Inspection of EquipmentUnpacking inspection of equipment shall be executed under the supervisionof theOwner s personnel, Contractor shall inspect the following items:Appearance , quantity, specification and model of the equipmentPacking list a
8、nd other technical dada.During the inspection Contractor shall keep all the records.Equipment , spare parts and special tools shall be carefully kept.1.4Installation of Equipment1.4.1Positioning and Aligning of EquipmentThe baseline of installation shall be designated accord with construction drawin
9、g and relating axis, edge line or elevation line before equipment positioning.The allowable tolerance of of the distance from plane installation bench mark to actual foundation axis or between actual shop wall axis and edge line is 20mm.Refer to Table 2 for the allowable tolerance of plane position
10、and elevation of the positioning plane, line or point to bench mark:Table2ItemsAllowable Tolerance (mm)Plane positionElevationWithout mechanical relations with other equipment102010With mechanical relations with otherequipment21Checked itemAllowable Tolerance (mm)Common equipmentEquipments Connected
11、 witMachinesVerticalHorizontalVerticalHorizontalCenter-to-centerD 2000 , 5D 2000 , 10533Elevation55Relative elevation 3Relativeelevation 3Levelnessaxial ,L/1000 radial , 2D/1000axial ,0.6L/1000 radial , 2D/1000PlumbnessH/1000But not more than 30H/1000OrientationMeasure along circumference of baseD 2
12、000,10D2000,15Measure along the circumference of base5The allowable tolerance of equipment installation refers to table 3:Table 31.4.2 Anchor BoltThe Anchor bolt in the reserved hole shall accord with the requirement of construction drawing and design document; the requirement below must be followed
13、 if no other special instructions are available:(1) Anchor bolt shall be vertical in reserved hole free of inclining.(2) The distance between any part of anchor bolt to the hole wall shall be larger than 15mm, and the bolt end shouldnt touch hole bottom.(3) The oil dirt and oxidized surface of ancho
14、r bolt shall be clear away, a little grease shall be applied to the screw thread of the anchor bolt.1.4.31.4.41.4.51.4.6(4) There shall be no distance between the nut and the gasket, and so are the gasket and the pedestal of the equipment.(5) Bolt shall extend out of nut after nut fastening; the exp
15、osed length is about 1/3-2/3 of the diameter value of the bolt.(6) The anchor blot shall be fastened while concrete strength in reserved reachesmore than than 75% designed value, the fastening strength shall be evenly.Iron ShimThe shim size for level adjusting of equipment shall accord with the requ
16、irement of construction drawings or technical documents.The common wedge shim and flat shim shall be selected according to Appendix 5 of the Construction & Acceptance Criterion of Machine & Equipment Installation Works (GB50231-98).GroutingThe grouting between the foundation and pedestal of the equi
17、pment/the reserved hole of the anchor bolt shall comply with the Code for Construction and Acceptance of Concrete Structures (GB50204-92).The grouting place shall be cleaned up before grouting. The concrete grade used for grouting is one grade higher than that used for foundation or ground. Groundin
18、g shouldn t make anchor bolt inclined or affect installing precision of the equipment.The thickness of grouting layer shall accord with design requirement, commonly not less than 25mm.The outer forms shall be laid before grouting, the distance of outer forms from outer edge of equipment base shouldn
19、 t less than 60mm; Float coat shall be applied to the surface after removal of forms.The inner forms shall be laid when complete grouting is not needed under equipment base and grouting layer would bear load of equipment.Assembly of EquipmentThe assembly of equipment shall accord with the requiremen
20、t of construction drawings, technical documents of manufacturer and Code for Construction & Acceptance of Machine & Equipment Installation Works (GB50231-98).Before the equipment assembly, the Contractor shall be familiar with the equipment structure and the technical requirements of equipment assem
21、bly. Recheck and cleaning treating on match dimension, relating precision, match face and sliding face of assembly parts shall be done, and the assembly shall be performed according to marks and assemble sequence.As to equipment or parts have inner cavity, careful check and clearance must be done be
22、fore concealing avoid any foreign substance contained in it.As to oil tank or water tank that difficult to disassembly, check and fix, leakage examination must be done before assembly.Installation of Equipment AccessoriesThe installation of tower and inner parts of equipment shall accord with the re
23、quirement of construction drawings and Code for Construction & Acceptance of Machine & Equipment Installation Works (GB50231-98).The installation of inner parts of pump shall accord with the requirement of construction drawings and Construction, Code for Construction and Acceptance of Compressor, Fa
24、n and Pump Installation Works (GB50275-98).The installation, pressure testing of accessory pipe shall accord with the requirement of construction drawings and Code for Construction and Acceptance of Industrial Piping Works (GB50236-98).The installation of accessory ladder, platform shall accord with
25、 the requirement of construction drawings and Code for Construction and Acceptance of Steel Structure Works (GB50205-95).1.4.7 Equipment TestAfter the installation completed, all the welding seams of pressure vessel shall be checked according to the Assessment on Welding Technology of Pressure Vesse
26、l (JB4708-92) and make record.Pressure experiment shall be performed to pressure container accord with constructing instructions and design requirement after installation.The pressure & leakage test shall be executed according to the Construction Explanation and the Design Requirements after the ins
27、tallation of stove type and familiar equipments that have water double layer.1.4.8 Cleaning and Purging of EquipmentWhen the installation of pump equipment completed, cleaning and purged of such equipment must be carried out according to construction drawings and Construction, Checking and Construct
28、ion, Code for Construction and Acceptance of Compressor, Fan and Pump Installation Works (GB50275-98).The cleaning and purging of static equipment must be performed after installation according to construction drawings and Code for Construction & Acceptance of Machine & Equipment Installation Works (GB50231-98).1.4.9 Test-run of EquipmentThe conditions, contents and procedure shall be ready before equipment test-run, as specified in Code for Construction & Acceptance of Machine & Equipment Installation Works (GB50231-98).Make good test
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 深度學習及自動駕駛應用 課件 第6、7章 基于CNN的自動駕駛場景語義分割理論與實踐、循環(huán)神經(jīng)網(wǎng)絡及自動駕駛車輛換道行為預測
- 污水處理設施管網(wǎng)配套設施合同
- 環(huán)保工程合同模板
- 物流配送計劃生育承諾書模板
- 知識產(chǎn)權許可使用合同解除協(xié)議
- 移動辦公通訊實施方案
- 企業(yè)員工道德提案管理辦法
- 投資權益協(xié)議書
- 親子園幼師聘用合同細則
- 物流公司承運商安全規(guī)范
- 馬工程政治學概論思考題答案
- 關于加強校園欺凌行為預防治理的說明報告
- 汽車露營營地質(zhì)量5c標準等級劃分認定細則(2021版)
- 地理實踐力ppt課件版 地理實踐力 彭春蓮組
- 水對種子發(fā)芽的影響
- GB/T 18942.1-2003高聚物多孔彈性材料壓縮應力應變特性的測定第1部分:低密度材料
- GB/T 12497-2006三相異步電動機經(jīng)濟運行
- GB/T 12402-2000經(jīng)濟類型分類與代碼
- GA 1551.5-2019石油石化系統(tǒng)治安反恐防范要求第5部分:運輸企業(yè)
- 電氣接地電阻測試記錄(通用)
- 氣液兩相流-第1章-緒論課件
評論
0/150
提交評論