項(xiàng)目專項(xiàng)施工方案
濟(jì)南萬(wàn)達(dá)城展示中心及樣板房
外裝修工程施工方案
編制:
審核:
審批:
編制單位:中建八局第一建設(shè)有限公司
日期:2023年04月05日
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù).............................................................................................................................................1
第二章工程概況.............................................................................................................................................2
2.1工程特點(diǎn)..................................................................................................................................................................2
2.2工程建設(shè)概況表......................................................................................................................................................2
2.3施工條件..................................................................................................................................................................3
2.4施工重難點(diǎn)分析及對(duì)策..........................................................................................................................................3
第三章施工管理與人員配置.........................................................................................................................4
3.1項(xiàng)目管理組織機(jī)構(gòu)圖及說(shuō)明....................................................................................................................................4
3.1.1項(xiàng)目管理組織機(jī)構(gòu)圖說(shuō)明.............................................................................................................................4
3.1.2項(xiàng)目主要管理人員.........................................................................................................................................4
3.1.3主要人員工作簡(jiǎn)歷及職責(zé)分工.....................................................................................................................5
3.2項(xiàng)目的質(zhì)量、進(jìn)度、成本及安全文明施工目標(biāo)....................................................................................................7
第四章施工組織及進(jìn)度計(jì)劃.........................................................................................................................8
4.1施工組織總述...........................................................................................................................................................8
4.1.1施工組織的原則.............................................................................................................................................8
4.1.2施工流水段劃分.............................................................................................................................................8
4.2施工進(jìn)度計(jì)劃及說(shuō)明............................................................................................................................................10
4.2.1施工進(jìn)度計(jì)劃.................................................................................................................................................10
4.2.2施工進(jìn)度保障措施.........................................................................................................................................12
4.3與總進(jìn)度計(jì)劃的關(guān)系............................................................................................................................................14
4.4材料封樣與樣板計(jì)劃............................................................................................................................................14
4.4.1材料封樣.......................................................................................................................................................15
4.4.2樣板工程.........................................................................................................................................................15
第五章施工準(zhǔn)備與主要資源配置...............................................................................................................18
5.1施工準(zhǔn)備計(jì)劃........................................................................................................................................................18
5.1.1技術(shù)準(zhǔn)備.......................................................................................................................................................18
項(xiàng)目專項(xiàng)施工方案
5.1.2施工現(xiàn)場(chǎng)準(zhǔn)備...............................................................................................................................................18
5.1.3資金準(zhǔn)備.......................................................................................................................................................18
5.2勞動(dòng)力資源配置計(jì)劃及保證措施........................................................................................................................19
5.3施工機(jī)械與施工機(jī)具配置計(jì)劃及保證措施........................................................................................................19
5.4大宗材料與設(shè)備購(gòu)置計(jì)劃及保證措施................................................................................................................21
5.5主要周轉(zhuǎn)材料計(jì)劃及保證措施............................................................................................................................22
第六章施工技術(shù)與施工工藝.......................................................................................................................24
6.1施工重難點(diǎn)分析....................................................................................................................................................24
6.2測(cè)量放線施工技術(shù)................................................................................................................................................24
6.3預(yù)埋件施工技術(shù)及施工工藝................................................................................................................................28
6.4內(nèi)幕墻隱框玻璃幕墻安裝施工技術(shù)、工藝及技術(shù)保證措施............................................................................30
6.5點(diǎn)式玻璃幕墻異型鋼龍骨整體安裝施工技術(shù)和工藝及技術(shù)保證措施............................................................32
6.6點(diǎn)式幕墻安裝施工技術(shù)和工藝及技術(shù)保證措施................................................................................................34
6.7中間驗(yàn)收和噴淋試驗(yàn)............................................................................................................................................37
6.8竣工驗(yàn)收................................................................................................................................................................38
6.9BIM應(yīng)用................................................................................................................................................................40
6.10新技術(shù)新工藝新設(shè)備應(yīng)用...................................................................................................................................43
第七章質(zhì)量保證措施及質(zhì)保體系...............................................................................................................44
7.1質(zhì)量目標(biāo)管理網(wǎng)絡(luò)及質(zhì)量保證運(yùn)行圖................................................................................................................44
7.2質(zhì)量保證與控制體系............................................................................................................................................47
7.3進(jìn)場(chǎng)主要材料和設(shè)備驗(yàn)收標(biāo)準(zhǔn)..............................................................................................................................59
7.3.1進(jìn)場(chǎng)主要材料和設(shè)備驗(yàn)收總述.....................................................................................................................59
7.3.2重要材料的特定檢測(cè).....................................................................................................................................59
7.4施工技術(shù)和施工工藝質(zhì)量控制要點(diǎn)和驗(yàn)收標(biāo)準(zhǔn)................................................................................................65
7.4.1幕墻四性測(cè)試...............................................................................................................................................65
7.4.2現(xiàn)場(chǎng)淋水試驗(yàn)...............................................................................................................................................67
7.4.3鋼構(gòu)件焊接質(zhì)量測(cè)試...................................................................................................................................67
7.4.4鋁單板氟碳噴涂質(zhì)量測(cè)試...........................................................................................................................67
7.4.5鋼構(gòu)件氟碳噴涂質(zhì)量測(cè)試...........................................................................................................................68
項(xiàng)目專項(xiàng)施工方案
7.5質(zhì)量通病及防治措施............................................................................................................................................68
7.6成品保護(hù)................................................................................................................................................................69
第八章安全施工保證措施...........................................................................................................................71
8.1安全管理保證措施................................................................................................................................................71
8.2施工安全生產(chǎn)總體措施........................................................................................................................................72
8.3現(xiàn)場(chǎng)安全及防護(hù)措施............................................................................................................................................76
8.4重點(diǎn)部位安全防護(hù)措施........................................................................................................................................79
8.5重大危險(xiǎn)源識(shí)別和防治措施................................................................................................................................80
第九章文明施工及環(huán)保綠色施工措施......................................................................................................82
9.1文明施工管理目標(biāo).................................................................................................................................................82
9.2文明施工管理要求.................................................................................................................................................82
9.3文明施工組織措施................................................................................................................................................85
9.4環(huán)保綠色施工措施................................................................................................................................................87
9.5文明工地、治安群防、外圍協(xié)調(diào)措施................................................................................................................88
第十章雨季防風(fēng)、防雷措施.......................................................................................................................91
10.1濟(jì)南市特點(diǎn)...........................................................................................................................................................91
10.2雨季施工措施.......................................................................................................................................................91
10.3防風(fēng)措施...............................................................................................................................................................92
10.4防雷措施...............................................................................................................................................................92
第十一章成品保護(hù)、保養(yǎng)、使用及維護(hù)措施..........................................................................................93
11.1成品保護(hù)概述及成品保護(hù)組織機(jī)構(gòu)..................................................................................................................93
11.2幕墻成品護(hù)措施..................................................................................................................................................93
第十二章質(zhì)量保修措施和質(zhì)量承諾..........................................................................................................97
12.1質(zhì)量保修計(jì)劃........................................................................................................................................................97
12.2保修期限..............................................................................................................................................................97
12.3保修范圍..............................................................................................................................................................97
12.4保修部門..............................................................................................................................................................97
12.5保修文件..............................................................................................................................................................98
12.6保修程序..............................................................................................................................................................98
項(xiàng)目專項(xiàng)施工方案
12.7保修回訪..............................................................................................................................................................98
12.8保修措施..............................................................................................................................................................98
第十三章施工合理化建議和降低成本措施............................................................................................100
13.1施工合理化建議..............................................................................................................................................100
13.2降低成本措施..................................................................................................................................................100
第十四章應(yīng)急預(yù)案.....................................................................................................................................101
14.1應(yīng)急預(yù)案方針與原則........................................................................................................................................101
14.2應(yīng)急預(yù)案的施工組織與應(yīng)急響應(yīng)流程..........................................................................................................101
14.3應(yīng)急處理指揮系統(tǒng)..........................................................................................................................................101
14.4衛(wèi)生防疫應(yīng)急預(yù)案..........................................................................................................................................102
14.5防汛、防火、防爆應(yīng)急預(yù)案..........................................................................................................................102
14.6勞資糾紛事件應(yīng)急流程及措施......................................................................................................................103
14.7突然停電應(yīng)急預(yù)案..........................................................................................................................................104
附件一效果圖.............................................................................................................................................105
附件二深化設(shè)計(jì)圖紙目錄.........................................................................................................................108
附件三典型性深化設(shè)計(jì)圖紙節(jié)點(diǎn)圖........................................................................................................110
附件四施工平面布置圖.............................................................................................................................113
附件五內(nèi)幕強(qiáng)熱工計(jì)算書.........................................................................................................................114
附件六穹頂熱工計(jì)算書.............................................................................................................................137
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
序號(hào)類別文件名稱編號(hào)
國(guó)家行政建設(shè)部2009第87
1《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理辦法》
文件號(hào)
地方行政山東省人民政府令
2山東省建筑安全生產(chǎn)管理規(guī)定
文件第132號(hào)
1建筑幕墻GB/T21086-2007
2金屬與石材幕墻工程技術(shù)規(guī)范JGJ133-2001
3玻璃幕墻工程技術(shù)規(guī)范JGJ102-2003
4建筑玻璃應(yīng)用技術(shù)規(guī)程JGJ113-2015
5小單元建筑幕墻JG/T216-2007
13建筑結(jié)構(gòu)荷載規(guī)范GB50009-2012
14鋼結(jié)構(gòu)設(shè)計(jì)規(guī)范GB50017-2003
15國(guó)家行業(yè)冷彎薄壁型鋼結(jié)構(gòu)技術(shù)規(guī)范GB50018-2002
16規(guī)范鋼結(jié)構(gòu)焊接規(guī)范GB50661-2011
18鋼結(jié)構(gòu)防火涂料GB14907-2002
19建筑設(shè)計(jì)防火規(guī)范GB50016-2014
20建筑防火封堵應(yīng)用技術(shù)規(guī)程CECS154:2003
21建筑抗震設(shè)計(jì)規(guī)范GB50011-2010
22建筑工程抗震設(shè)防分類標(biāo)準(zhǔn)GB50223-2008
23地震震級(jí)的規(guī)定GB17740-1999
24建筑工程預(yù)應(yīng)力施工規(guī)程CECS180:2005
25建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)GB50300-2013
鋼結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范GB50205-2001
工程驗(yàn)收
玻璃幕墻工程質(zhì)量驗(yàn)收標(biāo)準(zhǔn)JGJ/T139-2001
規(guī)范標(biāo)準(zhǔn)
鋁合金結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范GB50576-2010
鋼結(jié)構(gòu)現(xiàn)場(chǎng)檢測(cè)技術(shù)標(biāo)準(zhǔn)GB/T50621-2010
28設(shè)計(jì)文件濟(jì)南萬(wàn)達(dá)城展示中心外裝修工程施工圖紙/
29企業(yè)管理文旅項(xiàng)目施工組織設(shè)計(jì)、施工方案管控辦法2014版
1
項(xiàng)目專項(xiàng)施工方案
30文件萬(wàn)達(dá)茂管控標(biāo)準(zhǔn)2015版
2
項(xiàng)目專項(xiàng)施工方案
第二章工程概況
2.1工程特點(diǎn)
濟(jì)南萬(wàn)達(dá)文化體育旅游城展示中心外裝修面積約13000m2,建筑高度35m,主要分為點(diǎn)式
彩釉玻璃幕墻。為此,我司已成立了針對(duì)此建筑的項(xiàng)目施工團(tuán)隊(duì),根據(jù)合同文件及相關(guān)技術(shù)
要求進(jìn)行了細(xì)心的考量和精心的研究。從設(shè)計(jì)、生產(chǎn)角度進(jìn)行研究;再?gòu)陌踩┕そ嵌冗M(jìn)行
了充分的推敲,以最大程度的掌握建筑師的意圖;從而可確保配合今后深化設(shè)計(jì)的順利開(kāi)展,
保證生產(chǎn)加工的質(zhì)量和現(xiàn)場(chǎng)施工的進(jìn)度,努力將本項(xiàng)目打造成優(yōu)質(zhì)的代表性建筑物。
外立面主要由點(diǎn)式彩釉數(shù)碼打印玻璃幕墻、鋁單板幕墻、雨篷、不銹鋼地彈門、鋁合金
門窗。
2.2工程建設(shè)概況表
工程名稱工程性質(zhì)公建
工程地址總占地面積22.5畝
總裝修面積13000m25建設(shè)單位
設(shè)計(jì)單位項(xiàng)目承包范圍交鑰匙工程
勘察單位質(zhì)量合格,并達(dá)到國(guó)家備案標(biāo)準(zhǔn)
監(jiān)理單位工期131日歷天
總承包單位合同要求安全無(wú)安全事故
本工程用作展示中心、
工程主要功能或用途綠色施工達(dá)到“四節(jié)一環(huán)保”目標(biāo)
樣板房
3
項(xiàng)目專項(xiàng)施工方案
分包單位
2.3施工條件
玻璃幕墻施工前提條件為:1、肥槽回填完成;2、花瓣鋼結(jié)構(gòu)吊裝完成。
2.4施工重難點(diǎn)分析及對(duì)策
1)確保工期是本工程控制的重點(diǎn)之一
本工程異型工程量大,施工水平作業(yè)線較為短。要保證幕墻工期,其科學(xué)規(guī)劃部署施工,
合理高效進(jìn)行施工組織管理,確保工程施工進(jìn)度和工期及質(zhì)量是本工程一大重點(diǎn)。
我公司將充分考慮影響工期的各種因素,編制詳細(xì)、組織合理的施工進(jìn)度計(jì)劃,配備充
足的勞動(dòng)力、建筑材料以及運(yùn)行良好的施工機(jī)械,制定各項(xiàng)施工進(jìn)度計(jì)劃保障措施,各分項(xiàng)
工程分區(qū)分段組織施工,與眾多分包單位簽訂工期目標(biāo),加強(qiáng)總承包工期管理力度,為分包
單位施工創(chuàng)造有利條件,確??傮w及階段性工期目標(biāo)實(shí)現(xiàn)。
2)施工測(cè)量放線是工程控制的重點(diǎn)之二
①總周長(zhǎng)度約200米,高度約20米,分為12個(gè)花瓣系統(tǒng),3個(gè)大區(qū)施工段,如何保證
整個(gè)荷花展示中心放線精度使各施工段正常合攏,仍為幕墻施工的關(guān)鍵。
②本工程由于異型較多,不采用樓板作為標(biāo)高、基準(zhǔn)線的傳遞,如何克服基準(zhǔn)傳遞的
偏差累積,我司計(jì)劃在首尾軸線確認(rèn)無(wú)誤的前提下,利用幕墻公差,在施工場(chǎng)地外處設(shè)立參
照基準(zhǔn)軸線以及在屋頂鋼結(jié)構(gòu)處設(shè)立參照基準(zhǔn)標(biāo)高線,經(jīng)反復(fù)核對(duì)無(wú)誤后,確立為輔助基準(zhǔn)
線,以此來(lái)控制測(cè)量放線的精度從而達(dá)到施工作業(yè)的高質(zhì)量。
③依據(jù)總承包單位的基準(zhǔn)點(diǎn)、線,考慮到溫差對(duì)計(jì)量的誤差,以及地面不平造成的誤差,
我司采用全站儀進(jìn)行復(fù)核相互之間的幾何關(guān)系。搞清楚點(diǎn)線之間的關(guān)系,以及相互間的幾何
尺寸,通過(guò)點(diǎn)線的精度來(lái)提高幕墻施工精度。
④確保門洞口以及變形縫的寬度的前提下,各種累積誤差在大面幕墻內(nèi)消化。
4
項(xiàng)目專項(xiàng)施工方案
第三章施工管理與人員配置
3.1項(xiàng)目管理組織機(jī)構(gòu)圖及說(shuō)明
3.1.1項(xiàng)目管理組織機(jī)構(gòu)圖說(shuō)明
濟(jì)南萬(wàn)達(dá)城展示中心外裝修工程,工程量較大,為了很好地組織施工,我公司給予高度
重視,組成以下施工管理體系:
管理組織機(jī)構(gòu)設(shè)置分企業(yè)保障層、總承包管理層、施工作業(yè)層三個(gè)層次,按照對(duì)人員、
資歷、業(yè)績(jī)的要求設(shè)置關(guān)鍵管理崗位,并配備相關(guān)項(xiàng)目管理人員,使得總包管理與總包實(shí)施
項(xiàng)目由主管部門負(fù)責(zé)管理,項(xiàng)目公共部門負(fù)責(zé)配合,共同做好生產(chǎn)管理和服務(wù)。
按照動(dòng)態(tài)管理、優(yōu)化配置的原則,全部崗位職責(zé)覆蓋項(xiàng)目施工全過(guò)程的管理,在局項(xiàng)目
主管領(lǐng)導(dǎo)下,項(xiàng)目經(jīng)理部以項(xiàng)目經(jīng)理、項(xiàng)目生產(chǎn)經(jīng)理、項(xiàng)目技術(shù)負(fù)責(zé)人、商務(wù)經(jīng)理等組成項(xiàng)
目班子,對(duì)項(xiàng)目進(jìn)行綜合管理。
3.1.2項(xiàng)目主要管理人員
姓名性別年齡學(xué)歷專業(yè)從事本專業(yè)年限職稱擔(dān)任項(xiàng)目職務(wù)備注
男33本科土木工程10年工程師項(xiàng)目經(jīng)理
男38本科土木工程7年工程師項(xiàng)目總工
助理工
男28本科土木工程7年生產(chǎn)經(jīng)理
程師
5
項(xiàng)目專項(xiàng)施工方案
助理工
男30本科土木工程7年商務(wù)經(jīng)理
程師
高級(jí)工
男62大專建筑工程40年質(zhì)量總監(jiān)
程師
助理工
男33??平ㄖこ?0年安全總監(jiān)
程師
助理工
男29本科材料工程4年物資經(jīng)理
程師
助理工專業(yè)工程師、
男23本科土木工程3年
程師測(cè)量工程師
助理工
男29??平ㄖこ?年專業(yè)工程師
程師
助理工
男31專科建筑工程7年試驗(yàn)工程師
程師
助理工
女31本科工程管理8年資料工程師
程師
3.1.3主要人員工作簡(jiǎn)歷及職責(zé)分工
主要人員工作簡(jiǎn)歷
姓名
6
項(xiàng)目專項(xiàng)施工方案
職責(zé)分工
部門人員職責(zé)
項(xiàng)目經(jīng)理李輝全面負(fù)責(zé)相關(guān)各方的協(xié)調(diào)工作
生產(chǎn)經(jīng)理袁壯直接對(duì)現(xiàn)場(chǎng)的施工組織負(fù)責(zé)
項(xiàng)目總工李建峰全面負(fù)責(zé)現(xiàn)場(chǎng)技術(shù)管理
負(fù)責(zé)工人首次進(jìn)場(chǎng)安全教育,組織專項(xiàng)安
安全總監(jiān)王聯(lián)山
全檢查
人員進(jìn)場(chǎng)門禁辦理,日常安全巡查及安全
安全工程師許帥
整改事項(xiàng)驗(yàn)證
安全工程師田志鵬協(xié)調(diào)生活區(qū)住宿,協(xié)調(diào)現(xiàn)場(chǎng)機(jī)械及交通
負(fù)責(zé)洽商各種費(fèi)用、簽證收量,負(fù)責(zé)月報(bào)
商務(wù)經(jīng)理劉凱
量或節(jié)點(diǎn)報(bào)量
負(fù)責(zé)審核材料進(jìn)場(chǎng)申請(qǐng),負(fù)責(zé)按照材料進(jìn)
物資工程師劉文濤場(chǎng)計(jì)劃組織材料進(jìn)場(chǎng),負(fù)責(zé)材料報(bào)驗(yàn)總協(xié)
調(diào)
負(fù)責(zé)審核材料進(jìn)場(chǎng)申請(qǐng),負(fù)責(zé)按照材料進(jìn)
材料工程師部宗洋場(chǎng)計(jì)劃組織材料進(jìn)場(chǎng),負(fù)責(zé)材料報(bào)驗(yàn)總協(xié)
調(diào)
負(fù)責(zé)組織協(xié)調(diào)現(xiàn)場(chǎng)施工
專業(yè)工程師王偉強(qiáng)
負(fù)責(zé)施工現(xiàn)場(chǎng)材料堆場(chǎng)管理
專業(yè)工程師李冰負(fù)責(zé)勞務(wù)資料收集審核管理
負(fù)責(zé)日常安全、質(zhì)量施工管理
專業(yè)工程師劉兵
負(fù)責(zé)技術(shù)交底及安全交底
3.2項(xiàng)目的質(zhì)量、進(jìn)度、成本及安全文明施工目標(biāo)
1.質(zhì)量目標(biāo):達(dá)到國(guó)家質(zhì)量驗(yàn)收標(biāo)準(zhǔn),綜合評(píng)價(jià)指標(biāo)確保優(yōu)良。確保一次驗(yàn)收合格率達(dá)
到100%。
2.安全目標(biāo):無(wú)安全事故。
3.文明施工目標(biāo):達(dá)到濟(jì)南市文明施工工地標(biāo)準(zhǔn)。
7
項(xiàng)目專項(xiàng)施工方案
第四章施工組織及進(jìn)度計(jì)劃
4.1施工組織總述
4.1.1施工組織的原則
1)總體施工進(jìn)度組織原則——控制關(guān)鍵線路上階段性進(jìn)度目標(biāo),以實(shí)現(xiàn)總體工期目標(biāo)。
關(guān)鍵線路:施工關(guān)鍵線路是決定最短工期的施工軌跡,是自始至終應(yīng)該堅(jiān)持的施工主線,項(xiàng)
目經(jīng)理部的施工管理工作以關(guān)鍵線路為中心,其它工作為關(guān)鍵線路讓路、服務(wù)。
2)時(shí)間上的組織原則——嚴(yán)格執(zhí)行招標(biāo)文件的總工期要求和關(guān)鍵節(jié)點(diǎn)工期要求。確保在
規(guī)定的時(shí)間內(nèi)完成全部幕墻工程,并根據(jù)總的的施工進(jìn)度及時(shí)調(diào)整幕墻的施工時(shí)間和施工順
序,幕墻自身施工將整體分成若干個(gè)小的施工區(qū)域,各區(qū)域內(nèi)同時(shí)施工,壓縮施工工期,為
工程順利完工提供條件。
3)空間上的組織原則——平面分區(qū)域,立體分階段。根據(jù)現(xiàn)場(chǎng)的施工條件,按總包的平
面劃分,將本工程劃分成3個(gè)施工區(qū)域,每個(gè)施工區(qū)域內(nèi)各種幕墻系統(tǒng)進(jìn)行流水施工。
4)施工總平面布置原則——堅(jiān)持服從性、全局性、靈活性及可改造性兼顧的原則。我司
的現(xiàn)場(chǎng)平面布置完全服從總包的管理,協(xié)商布置幕墻的辦公室和材料堆放區(qū),針對(duì)工程場(chǎng)地
狹小的特點(diǎn),我司的材料根據(jù)施工進(jìn)度安排材料的運(yùn)輸,杜絕出現(xiàn)大宗材料在現(xiàn)場(chǎng)堆放的現(xiàn)
場(chǎng)。減少現(xiàn)場(chǎng)堆放和運(yùn)輸?shù)膲毫?,為業(yè)主分憂解難。
4.1.2施工流水段劃分
1)施工任務(wù)劃分
①幕墻所有飾面板、構(gòu)配件及鋼結(jié)構(gòu)構(gòu)件均安排在工廠進(jìn)行標(biāo)準(zhǔn)化生產(chǎn)加工成品、半成
品,以保證質(zhì)量、工期。
②現(xiàn)場(chǎng)采用規(guī)范化安裝施工。選用有施工經(jīng)驗(yàn)的施工隊(duì)進(jìn)行現(xiàn)場(chǎng)安裝。
8
項(xiàng)目專項(xiàng)施工方案
2)施工區(qū)劃分為三個(gè)區(qū)
3)施工段劃分
①A區(qū)平分為一個(gè)大施工段
②B區(qū)平分為一個(gè)大施工段
③C區(qū)平分為一個(gè)大施工段
4)施工順序安排
①幕墻施工作業(yè)順序:先結(jié)構(gòu)轉(zhuǎn)接件龍骨安裝,后面材安裝;面材按幕墻形式安裝順序
從下至上,從左至右。
②施工總體順序:先內(nèi)幕墻,再外幕墻,后收口鋁板、門頭、先A區(qū)外幕墻,再B區(qū)外
幕墻,后C區(qū)外幕墻,最后對(duì)接收口。
3.施工總體流程
1)我司在接到幕墻施工通知后馬上組織相關(guān)人員進(jìn)場(chǎng),根據(jù)測(cè)量基點(diǎn)在一周內(nèi)完成幕墻
測(cè)量放線工作,具體技術(shù)要求見(jiàn)測(cè)量放線章節(jié)。在測(cè)量的過(guò)程中,進(jìn)行清理或后補(bǔ)有偏差的
預(yù)埋件。然后進(jìn)行轉(zhuǎn)接件和龍骨的安裝,最后進(jìn)行面材安裝。龍骨和面材在每個(gè)施工區(qū)域內(nèi)
分成幾個(gè)流水施工段進(jìn)行流水施工。
9
項(xiàng)目專項(xiàng)施工方案
2)根據(jù)施工區(qū)域的劃分,現(xiàn)場(chǎng)分成6個(gè)施工團(tuán)隊(duì)分別在各區(qū)域內(nèi)進(jìn)行施工,每個(gè)施工團(tuán)
隊(duì)根據(jù)具體情況分成2-3個(gè)小組,每個(gè)小組8-12人組織施工。
3)本工程所有立面幕墻采用腳手架進(jìn)行施工,室內(nèi)搭設(shè)活動(dòng)腳手架(內(nèi)幕墻),室外搭
設(shè)滿堂架或三排架。
4.施工總平面布置
施工區(qū)域的合理布置是施工組織的重要環(huán)節(jié),將直接關(guān)系到施工進(jìn)度和安全文明施工管
理水平的高低,其主要是通過(guò)立體的整體規(guī)劃,平面的具體安排這兩種基礎(chǔ)手段,達(dá)到施工
區(qū)域安排的合理化、程序化、系統(tǒng)化。這樣不僅有助于簡(jiǎn)化交叉施工的復(fù)雜關(guān)系,而且有利
于綜合管理,便于實(shí)現(xiàn)文明施工的目標(biāo)。
1)平面管理辦法
①施工平面管理由項(xiàng)目經(jīng)理總負(fù)責(zé),由項(xiàng)目技術(shù)負(fù)責(zé)人、施工員、材料部門、機(jī)械管理
部門、后勤組織部門實(shí)施,按平面分片包干管理措施進(jìn)行管理。
②施工現(xiàn)場(chǎng)按照CI標(biāo)準(zhǔn)應(yīng)符合總報(bào)要求。
③按照總體規(guī)劃要求作好平面布置,主要包括:現(xiàn)場(chǎng)辦公區(qū)布置,材料堆放場(chǎng)地布置,
機(jī)具倉(cāng)庫(kù)布置,加工區(qū)的布置。
④施工現(xiàn)場(chǎng)要加強(qiáng)場(chǎng)容管理,做到整齊、干凈、節(jié)約、安全,力求均衡生產(chǎn)。
2)施工平面布置圖
施工平面布置詳見(jiàn)附件。
5.主要施工方法概述
外幕墻外部采用滿堂架或三排架。
幕墻材料垂直運(yùn)輸采用腳手架、馬道人工搬運(yùn)。板塊、玻璃安裝采用電動(dòng)葫蘆吊裝,幕
墻異型龍骨采用吊車安裝。
4.2施工進(jìn)度計(jì)劃及說(shuō)明
4.2.1施工進(jìn)度計(jì)劃
序現(xiàn)場(chǎng)管控計(jì)劃工程
分部工程分項(xiàng)工程項(xiàng)目
號(hào)開(kāi)始周期完成量
1外幕墻安裝第一批2個(gè)內(nèi)花瓣測(cè)量放線2017/4/2532017/4/27
2外幕墻安裝第一批2個(gè)外花瓣測(cè)量放線2017/4/2632017/4/28/
5外幕墻安裝第一批2個(gè)內(nèi)花瓣龍骨安裝2017/4/2792017/5/5
10
項(xiàng)目專項(xiàng)施工方案
6外幕墻安裝第一批2個(gè)外花瓣龍骨安裝2017/4/28102017/5/74100
7外幕墻安裝第一批2個(gè)內(nèi)花瓣爪件放線2017/4/3032017/5/2
8外幕墻安裝第一批2個(gè)外花瓣爪件放線2017/5/132017/5/3
9外幕墻安裝第一批2個(gè)內(nèi)花瓣爪件安裝2017/5/2972017/8/6
10外幕墻安裝第一批2個(gè)外花瓣爪件安裝2017/5/392017/5/11
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五年度教育擔(dān)保合作合同協(xié)議書143篇
- 2024蔬菜種植與銷售一體化合作意向協(xié)議書3篇
- 2025年度Wi-Fi無(wú)線傳感器網(wǎng)絡(luò)應(yīng)用合同3篇
- 痔瘡套扎術(shù)后護(hù)理查房
- 山區(qū)特色產(chǎn)品開(kāi)發(fā)與市場(chǎng)推廣
- 2024微商電商平臺(tái)合作伙伴合作協(xié)議書3篇
- 小班防雷電安全教育課件
- 二零二五年度法律咨詢服務(wù)托管合同
- 二零二五年度環(huán)保節(jié)能設(shè)施安全生產(chǎn)合同范本2篇
- 2024版挖掘機(jī)工程承包協(xié)議標(biāo)準(zhǔn)格式
- 2024年自然資源部所屬事業(yè)單位招聘(208人)歷年高頻難、易錯(cuò)點(diǎn)500題模擬試題附帶答案詳解
- 上海南洋模范2025屆高二生物第一學(xué)期期末檢測(cè)模擬試題含解析
- 《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2019
- 廣東茂名市選聘市屬國(guó)有企業(yè)招聘筆試題庫(kù)2024
- 2025屆高考數(shù)學(xué)一輪復(fù)習(xí)建議-函數(shù)與導(dǎo)數(shù)專題講座課件
- 2024-2030年中國(guó)高性能混凝土行業(yè)銷售規(guī)模與投資盈利預(yù)測(cè)報(bào)告
- 江蘇省常州市教育學(xué)會(huì)2023-2024學(xué)年高一上學(xué)期期末考試化學(xué)試題 (解析版)
- 中醫(yī)兒科護(hù)理課件
- 部編人教版二年級(jí)道德與法治上冊(cè)全冊(cè)教學(xué)設(shè)計(jì)(含反思)
- 2024年數(shù)學(xué)三年級(jí)上冊(cè)乘法分配律基礎(chǔ)練習(xí)題(含答案)
- 中煤電力有限公司招聘筆試題庫(kù)2024
評(píng)論
0/150
提交評(píng)論