防坍塌專項安全施工方案實用文檔(實用文檔,可以直接使用,可編輯優(yōu)秀版資料,歡迎下載)
官田隧道防坍塌專項安全施工方案防坍塌專項安全施工方案實用文檔(實用文檔,可以直接使用,可編輯優(yōu)秀版資料,歡迎下載)一、編制依據(jù)1、《中華人民共和國安全生產(chǎn)法》;2、《官田隧道兩階段施工設(shè)計圖》;3、《龍巖漳永高速公路A1標施工組織設(shè)計》;4、《公路工程安全施工規(guī)范》;5、龍巖漳永高速公路有限責任公司《安全生產(chǎn)管理制度》(試行版);6、《中鐵十二局集團龍巖漳永A1合同段危險源辯識》;7、官田隧道施工地段實際情況。二、工程概況中鐵十二局集團龍巖漳永高速公路A1合同段位于龍巖地區(qū)漳平市官田鄉(xiāng)石門村界內(nèi)。線路起點里程K50+193,終點里程K53+900,線路總長3。707Km.其中官田隧道進口段左線總長6139m(本合同段內(nèi)長3356m),右線總長6151m(本合同段內(nèi)長3358m),距隧道進口1730m處右洞右側(cè)設(shè)置圓形斷面通風豎井一座。本工程主線采用雙向四車道高速公路技術(shù)標準設(shè)計。設(shè)計速度采用80Km/h,設(shè)計荷載為:公路-Ⅰ級。分離式路基單幅寬度12.25m,隧道主洞凈高5m,凈寬10.25m.其中行車道寬度為2*3。75m;緊急停車帶凈高5m,凈寬13m;車行橫洞(橫洞變電所)凈高5m,凈寬4。5m;人行橫通道凈高2.5m,凈寬2m.三、地形地貌、工程地質(zhì)、水文地質(zhì)1、地形地貌本項目區(qū)屬福建省中南部,戴云山脈西南部山麓,測區(qū)海拔千米以上山峰54座,其中福鼎尖1504米,為華安境內(nèi)最高峰(位于湖林鄉(xiāng)與安溪縣交界處)。沿線主要的地貌單元有構(gòu)造剝蝕低山丘陵地貌.官田隧道區(qū)屬低山地貌,地形起伏較大。隧道范圍內(nèi)中線高程203~958.3m,最大高差約755。3m,山體自然坡度35?!?0.,植被發(fā)育。進、出口均處于山前傾斜地帶,山坡處于基本穩(wěn)定狀態(tài)。2、工程地質(zhì)工程所在地覆蓋層為第四系坡積成因(Qd1)粉質(zhì)粘土、含礫粉質(zhì)粘土、碎石等,下伏基巖為三疊系上統(tǒng)文賓山組(T3w)砂巖、粉砂巖、三疊系下統(tǒng)溪口組(T1x)砂巖及侏羅系上統(tǒng)南園組(J3n)凝灰熔巖、燕山期花崗巖等。HYPERLINK\l”_Toc181413389”地質(zhì)構(gòu)造及地震動參數(shù):斷層:隧址區(qū)左側(cè)發(fā)育有F16區(qū)域性大斷裂,該斷裂距隧道出口最近距離約45m,其走向與隧道軸線走向大致呈30。交角,受該斷裂影響,發(fā)育有次生正斷裂F1及F3;其中F1斷層產(chǎn)狀約60.∠75。,與路線大致交于ZK51+145(k51+080)處,斷層上盤為三疊系文賓山組(T3w)鈣質(zhì)膠結(jié)砂巖,上盤巖層產(chǎn)狀為100.∠27。;下盤為三疊系溪口組(T1x)硅質(zhì)膠結(jié)砂巖,下盤巖層產(chǎn)狀270?!?6.。F3斷層與路線大致交于ZK56+140(K56+080)處,該斷層為正斷層,產(chǎn)狀為60。∠80。,上下盤均為三疊系文賓山組(T3w)鈣質(zhì)膠結(jié)砂巖,上盤巖層產(chǎn)狀為56。∠24.,下盤巖層產(chǎn)狀為113.∠68。。褶皺:隧址區(qū)巖層產(chǎn)狀變化大,在三疊系文賓山組(T3w)地層中發(fā)育有一背斜及向斜,背斜核部大致位于ZK53+300~ZK53+380(K53+290~K53+370)段,漳州翼巖層產(chǎn)狀為290?!?3。,永安翼巖層產(chǎn)狀為40。∠17。,巖性為砂巖、粉砂巖;向斜核部位于ZK54+250~ZK54+380(K54+200~K54+360)段,州翼巖層產(chǎn)狀為0.-290?!?7。,永安翼巖層產(chǎn)狀為125?!?1。,巖性為砂巖、粉砂巖。不整合接觸:隧址區(qū)地層主要為三疊系溪口組(T1X)及三疊系文賓山組(T3w)地層,出口地段為花崗巖及凝灰熔巖,三疊系溪口組(T1X)巖性主要為硅質(zhì)膠結(jié)砂巖,巖質(zhì)硬,三疊系文賓山組(T3w)巖性主要為鈣質(zhì)膠結(jié)砂巖,夾泥質(zhì)砂巖、粉砂巖,兩者在ZK52+(K52+)、ZK52+090(K52+780)處呈不整合接觸。3、水文地質(zhì)地表水主要為沖溝地段中的水,其水位及流量受季節(jié)控制明顯,具補給快、排泄快的特點,地下水主要為基巖中的裂隙水,下伏基巖節(jié)理裂隙較發(fā)育,但多呈閉合狀,連通性較差,多充填泥質(zhì),裂隙水主要靠大氣降水補給,以沿裂隙滲流形式或受地形切割排出地表,由于隧道較長,山體較高,匯水面積大,地下水水量較豐富。4、不良地質(zhì)地段官田隧道出口段K51+105處穿越F1斷層,斷層巖體破碎,自穩(wěn)能力差,集中降雨狀態(tài)下洞室內(nèi)呈淋雨狀或點滴狀出水,可能產(chǎn)生突水、突泥。因此,確保隧道安全通過地質(zhì)災(zāi)害地段是本工程的難點.四、控制措施官田隧道左線長3358m,右線長3356m,各級圍巖地段施工時首先做好相應(yīng)的超前支護措施,并在開挖后及時施作初期支護。施工過程中嚴格控制超、欠挖,初期支護及時可靠。施工過程中加強監(jiān)控量測,及時處理分析量測數(shù)據(jù),反饋指導(dǎo)設(shè)計、施工。隧道開挖后洞渣運至棄土場或作為路基填方,禁止堆于河道.1、隧道工程總體施工方案隧道工程施工總體施工順序為:施工準備→測量放樣→洞頂截水溝→明洞及洞口工程→超前支護→洞身開挖→初期支護→仰拱、填充及整平層砼施工→防水層施工→二次襯砌→路面施工→溝槽施工(靠路面?zhèn)?→隧道裝飾→清理退場→竣工交驗。保持各工序均衡施工。洞身開挖支護后及時施做仰拱及回填,拱墻二次襯砌滯后開挖面一定距離平行施工,管溝滯后拱墻襯砌一定距離平行施工,隨后施工路面等.隧道采用新奧法施工,采用機械化配套施工,無軌運輸,建立以裝載機、挖掘機、全斷面襯砌模板臺車、自動計量拌合站、砼輸送車、輸送泵、自卸汽車為主要特征的大型機械設(shè)備配套施工體系,實現(xiàn)一系列機械化作業(yè)線的有機配合,嚴格機械設(shè)備管、用、養(yǎng)、修制度。隧道開挖過程中采用TSP203地質(zhì)探測儀、超前鉆孔或地質(zhì)雷達等手段進行探測和超前地質(zhì)預(yù)報,堅持“預(yù)防為主”原則,做好預(yù)防的施工措施,加強圍巖監(jiān)控量測,及時進行信息反饋,指導(dǎo)施工,保證施工安全。2、隧道開挖防坍塌控制措施(1)洞口邊仰坡及明洞洞口及明洞施工工藝見圖4-2—1“隧道明洞施工工藝框圖測量放線測量放線挖洞門基礎(chǔ)報驗立模報驗?zāi)0迮_車就位立模綁扎鋼筋測量復(fù)查拱墻砼施工拆模、養(yǎng)生邊墻基礎(chǔ)砼施工砼制備砼制備鋼筋預(yù)制測量放線挖明洞仰拱及基礎(chǔ)報驗綁扎鋼筋立模報驗仰拱及邊墻基砼施工鋼筋預(yù)制砼制備不合格不合格不合格不合格合格合格合格合格合格不合格回填及坡面處理防水層施作報驗圖4-2—①洞頂截水溝隧道明洞、洞門開挖前,首先施工洞口邊仰坡外的截水溝,以避免對邊坡沖刷,導(dǎo)致邊坡落石、失穩(wěn)坍塌。截水溝設(shè)置在洞口仰坡和地面交接線5m以外,采用人工開挖,基底夯實整平,溝身施工,截水溝采用C20混凝土澆筑。截水溝根據(jù)實際地形調(diào)整,將地表水引入隧道左右側(cè)溝谷。②邊仰坡施工洞口工程施工前,先檢查邊、仰坡以上的山坡穩(wěn)定情況,清除懸石、處理危石.施工期間實施不間斷監(jiān)測和防護。結(jié)合現(xiàn)場地形,邊、仰坡及早做好坡面防護。隧道開挖應(yīng)力求早進洞,避免出現(xiàn)深路塹或高邊坡,盡量減少對山體的破壞,防止水土流失。隧道出口邊仰坡圍巖均為土質(zhì)及軟巖,采用人工配合反鏟由上而下進行.遇個別較大孤石或少量硬質(zhì)巖,風鉆打眼、微藥量解體,風鎬修鑿輪廓,不得擾動邊坡,影響邊坡穩(wěn)定.裝載機或挖掘機裝碴,自卸汽車運碴。邊仰坡刷坡自上而下分層開挖,每層高度2~3m,分層進行錨桿網(wǎng)噴支護。做好坡面噴砼防護層與原坡面銜接,防止坡面風化,引起水土流失、導(dǎo)致邊仰坡防護受到損壞.③明洞及洞門結(jié)構(gòu)施工a明洞、洞門土石方開挖至洞口大管棚護拱鋼拱架拱底標高時,人工開挖基坑,施工護拱鋼拱架,架設(shè)護拱施工暗洞超前大管棚注漿后,進入正洞施工,正洞開挖與明洞下半部分土石方開挖同時進行.b明洞、洞門土石方開挖至路面設(shè)計標高時,轉(zhuǎn)為人工開挖,由人工挖出明洞仰拱及洞門基礎(chǔ),明洞基礎(chǔ)盡可能挖至基巖面,并將基巖面挖成臺階狀,超挖部分利用漿砌片石回填后方可做明洞結(jié)構(gòu),施工時,如明洞基礎(chǔ)未能落到穩(wěn)固基礎(chǔ)上時,明洞基礎(chǔ)按設(shè)計要求進行地基處理,保證承載力滿足設(shè)計要求.c明洞及洞門結(jié)構(gòu)施工,應(yīng)符合以下要求及條件:1、洞門施工放樣位置準確。2、洞門基礎(chǔ)必須置于穩(wěn)固的地基上,并滿足設(shè)計承載力(達不到要求時采用換填)。基坑內(nèi)廢渣、雜物等須清除干凈,報請監(jiān)理工程師驗收合格后,方可進行下道工序。3、明洞襯砌與暗洞交界必須設(shè)沉降縫分開澆注,模板臺車長度多于部分向洞門段調(diào)節(jié)。4、洞門建筑完成后,應(yīng)檢查與確保仰坡坡頂?shù)慕厮疁霞奥穳q排水系統(tǒng)的完好與連通。④明洞砼灌注外模采用大塊鋼模板,插入式振搗器振搗.隧道明洞小于模板臺車長度的一次性整體式進行灌注,大于模板臺車的分次施工,盡量減少施工縫的數(shù)量,防止明洞洞身滲水。澆筑砼必須對稱分層澆筑,每層厚度都不超過振動棒長的1.25倍,振搗密實又不超振。在明洞與隧道正洞洞內(nèi)接頭處要設(shè)變形縫.⑤鋪設(shè)防水層在明洞的模筑砼達到規(guī)定的強度以后開始進行防水層施作.隧道明洞的拱頂部分采用EVA防水板與無紡?fù)凉げ?。在防水層鋪設(shè)前,必須將拱墻背的灰塵污垢和積水清除干凈,用砂漿抹平,然后才能鋪設(shè)防水層與無紡?fù)凉げ?。⑥拱頂回填a在已澆筑的拱頂作好防水層,即采用碎石土進行回填.b拱部回填應(yīng)對稱分層夯實,每層厚度不宜大于0.3m,其兩側(cè)回填的土面高差不得大于0.5m,回填至拱齊平后,分層填筑至設(shè)計標高。c明洞拱部回填時須待拱圈混凝土達到設(shè)計強度的100%,采用小型夯機夯實。d回填土頂部采用50cm厚粘土隔水層.(2)、暗洞各級圍巖開挖方法Ⅴ級圍巖地段采用CD法施工,用“φ108管棚+注漿”預(yù)支護,在保證安全作業(yè)的前提下可采用“小導(dǎo)管+注漿”預(yù)支護.施工順序見圖4—IV級圍巖采用上下臺階施工,開挖方式詳見圖4—Ⅲ級圍巖段采用采用全斷面施工,開挖方式詳見圖4-V、IV級圍巖段以“管超前、嚴注漿、短進尺、弱爆破、強支護、勤量測、早成環(huán)”穩(wěn)扎穩(wěn)打為原則,Ⅲ級圍巖段以大斷面,機械化快速施工為原則,隧道開挖后及時支護.分部開挖時必須嚴格按設(shè)計要求進行超前管棚、超前錨桿等預(yù)支護,開挖后及時進行初期支護,并根據(jù)監(jiān)控量測結(jié)果及時調(diào)整施工方法及支護參數(shù)。開挖循環(huán)進尺應(yīng)和支護參數(shù)相匹配,短進尺、多循環(huán),支護緊跟開挖,并及時施做仰拱,及時形成支護閉合環(huán).圖4-2-1圖4—2—圖4-2-3Ⅲ(3)、鉆爆設(shè)計①鉆爆方案隧道采用光面爆破,合理選擇周邊眼間距及周邊眼的最小抵抗線,輔助炮眼交錯均勻布置,掏槽炮眼加深15cm。采用乳化炸藥間隔裝藥,導(dǎo)暴索連接,藥量沿炮眼全長均勻分布。非電毫秒雷管微差有序起爆。②鉆爆參數(shù)的選擇爆破參數(shù)參照表4—1,Ⅳ、Ⅴ級圍巖參照軟巖、中硬巖,Ⅲ級圍巖參照中硬巖參數(shù)。隧道圍巖以Ⅲ級圍巖為主,Ⅳ級圍巖采用臺階法開挖爆破設(shè)計見圖4-2-1;Ⅲ級圍巖全斷面法開挖爆破設(shè)計見圖4-2—表4—1光面爆破參數(shù)表巖石種類周邊眼間距E(cm)周邊眼最小抵抗線W(cm)相對距E/W周邊眼裝藥參數(shù)(kg/m)循環(huán)進尺(m)硬巖60~7080~900。8~1.00.25~0。33。5~4中硬巖50~6070~800.8~1。00。2~0。252軟巖40~5060~700。5~0.80。07~0.120。8~1圖4—3圖4—3③掏槽方式采用中空直眼掏槽.為保證掏槽效果,設(shè)置2~3個中空眼,掏槽眼裝藥量適當加大,非電毫秒微差爆破。④裝藥結(jié)構(gòu)及堵塞方式周邊眼用小直徑藥卷間隔裝藥,其他眼用常藥卷間隔裝藥,炮泥堵塞,堵塞長度不小于30cm。(4)、洞身開挖控制方案及效果檢查a嚴格控制測量放樣,保證投點準確,開挖輪廓線及鉆眼位置全部在掌子面上標出,按點位司鉆,為鉆眼提供技術(shù)保障。b嚴格控制周邊眼間距,打眼作業(yè)技術(shù)人員跟班嚴格控制鉆桿外插角,按要求嚴格控制裝藥量,全程控制隧道超欠挖,減少對圍巖擾動。c檢查超欠挖,爆破銜接臺階不大于15cm,開挖輪廓圓順。d檢查開挖面平整度及爆破進尺,爆出石碴塊度適合裝碴要求。e周邊炮眼痕跡保存率,硬巖≥90%,中硬巖≥70%,并在開挖輪廓面上均勻分布。3、出碴運輸控制措施本隧道開挖采用無軌運輸,隧道開挖土石方直接運至臨時棄碴場或直接將合格材料運至碎石場加工成碎石。4、初期支護控制措施隧道采用復(fù)合式襯砌結(jié)構(gòu),初期支護以錨桿、鋼筋網(wǎng)、鋼拱架、型鋼拱架、噴砼,超前支護采用大管棚、注漿小導(dǎo)管和超前錨桿.(1)、大管棚施工施工采用水平地質(zhì)鉆機鉆孔,用機械將管棚頂入,注漿泵注漿.具體方法如下:①施作套拱洞口段在洞外明暗洞交界處架立工字鋼套拱,用連接筋焊接成整體,套拱在明洞外廓線以外,緊貼掌子面施作.在鋼支撐上以設(shè)計大管棚間距安裝孔口導(dǎo)向鋼管,與管棚位置方向一致,然后澆注砼包裹鋼支撐和導(dǎo)向管.套拱完成后,噴射C20砼15cm厚封閉周圍仰坡面,作為注漿時的止?jié){墻。②搭設(shè)鉆孔平臺架、安裝鉆機用方木搭設(shè)鉆孔平臺架,平臺上滿鋪木板,搭設(shè)牢固,以防鉆孔時鉆機晃動。施工時可保留洞口或洞內(nèi)下半部分土石方,減少平臺架設(shè)高度,具體方法根據(jù)現(xiàn)場施工實際情況選定。③鉆孔采用GY-50水平地質(zhì)鉆機,從導(dǎo)向管向內(nèi)鉆入。④安裝大管棚管棚鋼管由機械頂進,鋼管節(jié)段間用絲扣連接,絲扣長15cm,頂進時,鋼管接頭錯開。管棚頂?shù)轿缓?鋼管與導(dǎo)向管間隙用速凝水泥或其它堵塞嚴密,以防注漿冒出。堵塞時預(yù)留進漿孔和排氣孔。⑤注漿漿液采用注漿機灌注,當排氣孔流出漿液后,關(guān)閉排氣孔繼續(xù)灌注漿,達到設(shè)計注漿量或注漿壓力時,穩(wěn)定3~5分鐘后停止注漿。施工過程中,為了防止注漿過程中發(fā)生串漿,每鉆完一個孔,隨即就安設(shè)該孔的鋼管并注漿,然后再進行下一孔的施工。(2)、超前小導(dǎo)管施工施工工藝(見圖4-4小導(dǎo)管注漿施工示意圖)。漿液準備漿液準備不合格補孔注漿注漿效果檢查進入下一道工序合格孔口處理注漿口防護噴砼封閉噴測量放線鉆孔清孔安裝小導(dǎo)管是否小導(dǎo)管制作圖4—4超前注漿小導(dǎo)管施工工藝框圖①測量放樣:按拱部120°范圍,在掌子面上按設(shè)計環(huán)向間距準確定位布設(shè)管孔位置,用紅油漆標記。②鉆孔:采用鑿巖機鉆孔,孔深4m,外插角5°~7°、10°~15°。③清孔及檢查:用φ18彎頭鋼管通入高壓風吹凈孔中石屑及細小石塊,利于漿液與巖壁充分接觸,并檢查孔深。④鋼管插入及孔口密封處理:鉆孔完成后,再將鉆桿換成特殊釬尾,用專用頂頭將導(dǎo)管頂入孔中,注意保護鋼管尾部不被損壞,以便與高壓注漿管連接.在鋼管末端除焊φ8加勁箍外,再用膠泥麻筋纏箍成楔形以便鋼管頂進管孔后使其外壁與孔內(nèi)巖壁間隙堵塞嚴密。鋼管尾端外露足夠長度,并與鋼架焊接牢固.⑤注漿:采用水泥漿液,對于富水段采用雙液漿,貧水段采用單液漿,水泥漿水灰比為1:1,水玻璃濃度35波美度,水玻璃模數(shù)2.4。按規(guī)范要求配置漿液,注漿采用注漿機壓注,注漿壓力為0。5~1。0Mpa,注漿終壓為2。5Mpa,當排氣孔流出漿液后,關(guān)閉排氣孔,繼續(xù)注漿,達到設(shè)計注漿量或注漿終壓時,穩(wěn)定10min后停止注漿。開挖時應(yīng)保留1.5~2.0m的止?jié){墻,防止下一次注漿時孔口跑漿。注漿參數(shù)通過現(xiàn)場試驗按實際情況確定,注漿量按施工實際情況作相應(yīng)調(diào)整。(3)、錨桿控制措施①砂漿(藥卷)錨桿施工手持風鉆造孔,用羊角氣泵膠管倒插式注漿,漿滿后快速插入錨桿到埋設(shè)長度,然后用半干硬砂漿封實孔口,用楔子固定錨桿,并安裝墊板,上好螺帽,錨桿埋設(shè)后24h以內(nèi)不許碰撞,不許懸掛重物,錨桿砂漿摻膨脹及早強劑,以提高其早期強度,埋設(shè)24h后,擰緊螺母,使墊板緊貼巖石。②Φ50中空注漿錨桿施工用風鉆鉆孔,高壓風清孔,插入錨桿并安設(shè)止?jié){塞,利用注漿泵注漿,待水泥漿終凝后安設(shè)孔口墊板.(4)、鋼拱架控制措施①制作:按設(shè)計尺寸在洞外下料分節(jié)冷彎制作,相鄰節(jié)間用螺栓連接牢靠,洞外加工后試拼檢查.②安裝:橫向和高程為±3cm,垂直度±1°,拱架間距嚴格按設(shè)計要求架設(shè)。鋼拱架的下端設(shè)在穩(wěn)固的地層上,拱腳高度低于上部開挖底線以下15~20cm。拱腳開挖超深時,加設(shè)鋼板或砼墊塊.③鋼筋網(wǎng)鋪設(shè)鋼筋網(wǎng)在洞外分片制作,人工鋪設(shè),利用錨桿和釬釘連接牢固,安裝時搭接長度不小于10cm。鋼筋網(wǎng)噴砼保護層厚度不小于2cm。(5)、初期支護施工技術(shù)措施①開挖后及時初噴,出碴后及時復(fù)噴.噴砼平整度兩米直尺靠量,凹凸不大于5cm。②錨桿在孔中位置居中,桿體露出巖面長度不大于噴層厚度,錨桿孔內(nèi)水泥漿飽滿密實,錨桿墊板與孔口砼密貼??拙嗾`差小于150mm,保持錨孔順直,鉆孔深度及直徑與桿體相匹配。③超前小導(dǎo)管的縱向搭接長度≮1。0m,與線路方向大致平行。孔位偏差≯10cm,鋼管外露長度≯20cm。注漿前做好準備工作以及機具設(shè)備和管路系統(tǒng)的檢修工作。④鋼拱架在初噴砼后及時安裝,要全部被噴射砼覆蓋,鋼架與圍巖之間的間隙應(yīng)噴密實,保護層厚度不小于4cm。5、噴射砼控制措施噴射砼施工工藝圖見圖4—5。細骨料細骨料粗骨料水泥水攪拌機噴射機噴嘴壓縮空氣速凝劑噴射面圖4—5噴射砼施工工藝圖⑴噴射前處理危石,檢查開挖斷面凈空尺寸,當受噴面有涌水、淋水、集中出水點時,先進行引排水處理。⑵用高壓風水沖洗受噴面,設(shè)置控制噴砼厚度的標志。噴射作業(yè)分段、分片、分層,由下而上進行,有較大凹洼處,先噴射填平。⑶噴嘴垂直于巖面,距受噴面0.8~1。2m,呈螺旋移動,風壓0.5~0。7MPa。液態(tài)速凝劑由自動計量在噴嘴處摻入。6、仰拱、填充控制措施仰拱及隧底填充施工在隧道底部開挖支護完成后,及時全幅分段施工,為確保洞內(nèi)交通不中斷,采用仰拱棧橋方式.⑴仰拱從仰拱開挖到灌筑砼之間,隧道受力是處于最不穩(wěn)定狀態(tài),根據(jù)情況開挖仰拱會產(chǎn)生邊墻擠出和下沉,圍巖條件差時,迅速灌筑砼,用仰拱閉合斷面。仰拱與掌子面的距離要求:Ⅴ級圍巖≤35m;Ⅳ級圍巖≤50m。仰拱施工前,先將隧底虛碴、雜物、積水等清除干凈。施工前先復(fù)核仰拱斷面尺寸,不允許出現(xiàn)欠挖,超挖部分采用同級砼回填.仰拱分段施工,鋼筋在洞外預(yù)制,澆筑采用仰拱移動邊模由中心向兩側(cè)對稱施工,一次完成,仰拱砼采用插入式振搗器,加強振搗,保證砼施工質(zhì)量。仰拱施工與掘進工作平行進行,為解決仰拱施工和其他工序的干擾問題,自制仰拱棧橋渡車,形成立體交叉平行作業(yè)體系,減少施工干擾.仰拱棧橋示意圖見圖4.9。圖4。9仰拱棧橋示意圖⑵仰拱填充仰拱混凝土達到設(shè)計強度70%后,方可灌筑隧底填充混凝土。隧道仰拱上部填充砼施工前先清洗仰拱上虛碴及雜物,排除積水。填充砼表面要求平整,橫坡、縱坡與設(shè)計一致。7、施工測量在隧道施工中,及時準確地進行施工測量,能很好地控制好隧道走向及超欠挖。施工測量嚴格執(zhí)行“三級復(fù)核制”。隧道開挖和襯砌放樣都嚴格使用經(jīng)監(jiān)理工程師批準的洞口投點、導(dǎo)線點(或置鏡點)和水準基點??刂茰y量采用GPS全球定位系統(tǒng),確保隧道貫通誤差在規(guī)范要求范圍內(nèi),開挖400m進行一次高精度復(fù)核測量,使準確進行隧道控制(導(dǎo)線)測量得到保障。(1)監(jiān)控量測、超前地質(zhì)預(yù)報①監(jiān)控量測監(jiān)控量測是監(jiān)視圍巖和支護穩(wěn)定性的重要手段,是判斷設(shè)計、施工是否正確合理的主要依據(jù),是監(jiān)視施工是否安全可靠的眼睛.②施工監(jiān)測項目監(jiān)測項目為:地質(zhì)與初期支護觀察,水平凈空收斂量測,拱頂下沉量測,錨桿抗拔力等,必要時選測其他項目。③量測頻率與結(jié)束標準量測頻率:量測頻率根據(jù)監(jiān)測數(shù)據(jù)的變化情況而定。結(jié)束標準:一般地段,收斂速度>5mm/d時,圍巖處于急劇變化狀態(tài),加強初期支護系統(tǒng)。收斂速度<0.2mm/d時,圍巖趨于穩(wěn)定.④監(jiān)測數(shù)據(jù)的統(tǒng)計分析與信息反饋a隧道周邊允許位移值的制定利用隧道周邊允許位移值對本隧道的拱頂下沉、凈空收斂位移值進行管理。b監(jiān)測項目管理基準根據(jù)監(jiān)測結(jié)果所處的管理階段來選擇監(jiān)測頻率:一般Ⅲ級管理階段監(jiān)測頻率可放寬些;Ⅱ級管理階段則應(yīng)注意加密監(jiān)測次數(shù);Ⅰ級管理階段則應(yīng)加強監(jiān)測,通常監(jiān)測頻率為1-2次/天或更多。c監(jiān)控量測信息化施工根據(jù)量測所獲得的信息分析判斷圍巖、支護的穩(wěn)定性,及時反饋信息,指導(dǎo)施工。d超前地質(zhì)預(yù)探預(yù)報與地質(zhì)素描對洞口潛埋段及洞身圍巖較差地段采用TSP203地質(zhì)超前預(yù)報系統(tǒng),進行地質(zhì)預(yù)測,如發(fā)現(xiàn)異常,及時改變施工方案,采取措施,預(yù)防事故發(fā)生。利用地質(zhì)素描判斷工作面前方短距離范圍的地質(zhì)狀況。根據(jù)地質(zhì)素描的內(nèi)容,作出開挖面前方較短距離的巖體穩(wěn)定性評價。8、隧道過斷裂帶控制措施(1)、隧道斷裂帶工程概況根據(jù)設(shè)計圖紙顯示,官田隧道出口段K51+140處穿越F1斷層,斷層巖體破碎,自穩(wěn)能力差,集中降雨狀態(tài)下洞室內(nèi)呈淋雨狀或點滴狀出水,可能產(chǎn)生突水、突泥。(2)、防止坍方的對策①加強地質(zhì)超前預(yù)報,探明地質(zhì)構(gòu)造帶和水文情況,不盲目按原設(shè)計圍巖級別掘進;加強掌子面地質(zhì)描述,防止因節(jié)理裂隙發(fā)育引起的局部失穩(wěn),尤其是在斷層破碎帶處,嚴格施工程序,地質(zhì)預(yù)報先行,預(yù)加固可靠,支護及時,開挖方法合適,二襯適當緊跟。②采用超前水平鉆孔結(jié)合地震回波反射法確定破碎帶位置、范圍和預(yù)報巖體情況,準確把握斷裂構(gòu)造具體位置以及地下水情況。③采用超前全斷面帷幕注漿方案對破碎帶段進行加固和堵水處理,注漿漿液采用水泥漿液,水灰比1.0~1.5;注漿壓力以中壓為主,一般采用2.5~3倍靜水壓力;具體根據(jù)現(xiàn)場測定水壓確定。④短進尺掘進,減小藥量和減少爆破頻率,控制光爆效果,確保安全。a采用控制爆破,盡量減少對圍巖的擾動.b開挖成型后及時噴砼進行初期支護,步步為營。c開挖后自穩(wěn)能力差的地段應(yīng)采用超前支護或超前加固前方圍巖,即堅持先護頂后開挖的原則組織施工。d縮短各臺階開挖長度,使初期支護盡早封閉成環(huán)。⑤保證初期支護質(zhì)量a初期支護應(yīng)嚴格按設(shè)計和施工規(guī)范施工,確保支護質(zhì)量.b提高開挖質(zhì)量是保證支護質(zhì)量的關(guān)鍵,凡爆破成型不良地段應(yīng)考慮超前支護.c噴射混凝土與圍巖密貼,并保證噴混凝土強度,鋼架背后不允許有空洞,不許填片石和木材,噴混凝土將鋼架完全覆蓋。d鋼架間距符合設(shè)計,安裝位置正確,保證接頭處的等強連接,鋼架置于基巖面上,若拱腳為軟巖必須處理加固。e錨桿孔的長度、間距符合設(shè)計要求,保證桿孔內(nèi)的砂漿飽滿.f施工過程中對圍巖及支護結(jié)構(gòu)進行變形量測,根據(jù)數(shù)據(jù)結(jié)合觀察報告正確分析和支護的穩(wěn)定性,并采取正確對策。g對變形超限的初期支護要及時進行加固。h初期支護變形穩(wěn)定后應(yīng)立即進行二次襯砌,對自穩(wěn)能力很差圍巖,圍巖變形測出異常且無收斂趨勢時,提前施作二次襯砌,二次襯砌中,采取增設(shè)鋼筋和提高砼強度等措施.⑥圍巖含水地段先治水,后施工。⑦加強施工過程控制:a施工過程中每一開挖工班配一名工程師跟班,確保各種措施、技術(shù)交底的落實,保證標準化作業(yè)。b開挖過程中配經(jīng)驗豐富的地質(zhì)工程師24小時輪流值班,及時監(jiān)控地質(zhì)變化情況,指導(dǎo)現(xiàn)場施工.c領(lǐng)導(dǎo)重視是關(guān)鍵,在軟弱不穩(wěn)定圍巖地段施工,安排主要領(lǐng)導(dǎo)輪流值班,及時解決現(xiàn)場出現(xiàn)的問題。d嚴格施工紀律。防坍的施工方案一經(jīng)討論確定,操作人員必須嚴格執(zhí)行,不得私自變動.否則,無論后果如何,都要視為嚴重違章,對其進行嚴肅處理。五、隧道坍塌事故應(yīng)急預(yù)案1、指導(dǎo)思想對發(fā)生的隧道掌子面坍塌、涌水事故采取應(yīng)急措施,使事故造成的人員傷亡和財產(chǎn)損失降到最低限度,制定本預(yù)案。2、成立隧道掌子面坍塌、涌水事故處理領(lǐng)導(dǎo)小組組長:張銳:副組長:張冬生:組員:李先乾董曉亮肖騎彭新澤劉建平張志川3、應(yīng)急預(yù)案⑴、一旦發(fā)生隧道掌子面坍塌、涌水事故,最先發(fā)現(xiàn)的人應(yīng)立即打告知張銳。⑵、張銳立即負責現(xiàn)場總指揮,進行現(xiàn)場自救工作。⑶、由現(xiàn)場安全員負責打“120"通知華安縣醫(yī)療急救中心,報告事故的地點,傷害的程度,受傷人員的狀態(tài)。⑷、視情節(jié)的輕重,立即進行自救,對摔傷人員進行簡單止血和包扎。4、隧道坍塌方處理措施⑴、處理坍塌方的一般步驟和方法①防止坍方擴大范圍坍方發(fā)生后,首先應(yīng)防止坍方繼續(xù)擴大:A在坍方范圍頂部、側(cè)壁上的危石及大裂縫,應(yīng)先行清除或錨固;B對坍方范圍前后原有的支護進行加固,以防止坍方擴大;C在坍塌方范圍內(nèi)架設(shè)支撐或噴射混凝土,必要時加設(shè)錨桿;D加快襯砌。對坍方兩端應(yīng)盡快作好局部襯砌,以保證坍塌方不再擴大。②處理坍塌措施A如坍塌體積較小,且坍方范圍內(nèi)已進行了噴錨,或已架設(shè)好較為牢固的構(gòu)件支撐,可由兩端或一端先上后下地逐步清除坍渣,隨挖隨噴射混凝土,架設(shè)臨時構(gòu)件支撐支頂;B如坍塌體積較大,或地表已下沉,或因坍體堵塞,無法進入坍方范圍進行支護時,則可注漿加固坍方體,然后用“穿"的辦法在坍體內(nèi)進行開挖、襯砌;C處理坍塌方的同時,應(yīng)加強排水,即“治坍先治水”。⑵、處理坍塌常用支護方式①噴錨處理采用噴錨處理較大型坍方,較之采用架設(shè)支撐,更加安全、快速,且省工省料.A由外而內(nèi)、由上而下,逐段隨清坍渣隨向巖壁噴射一薄層砂漿,然后再噴射混凝土?;炷烈朔謱訃娚?,每層厚5cmB噴射1—2層混凝土后,可隨即加設(shè)錨桿再噴射混凝土;C坍渣的清除后,隨即做好襯砌.②構(gòu)件支撐處理A在坍體不太高、坍穴略呈錐形、坍壁不太松散的情況下,使用人字架支撐,支撐材質(zhì)可為型鋼與錨桿焊接;B當坍體較高,但坍體兩側(cè)壁形狀較整齊,且側(cè)向壓力不大時,可按垂直于隧道中線的方向架設(shè)橫向排架。先將坍體頂?shù)氖瞧?,鋪上橫梁,再在其上架設(shè)排架。排架間距根據(jù)坍穴圍巖情況而定,一般為1~2mC當坍塌方較大,且圍巖壓力也較大時,宜在坍方范圍內(nèi)全部用縱向棚支撐.先將坍渣頂部適當扒平,沿隧道中線方向平行設(shè)置縱地梁數(shù)根(地梁下預(yù)鋪橫梁),于縱地梁上按照導(dǎo)坑支撐的形式以1m左右的間距架設(shè)箱形棚架。以后逐層向上架設(shè)至坍方頂部,用填塞木塞緊。隨著坍渣的清除,加設(shè)立柱,并以縱撐撐牢.支撐材質(zhì)可為紅松,最小頭直徑不小于180D當坍塌方直至地表而深度不大時(小于10m),可設(shè)置井箍。由地面向下逐步清除坍渣,隨即架設(shè)箍架支撐。箍架的形式可為多邊形、矩形或方形,視坍穴的形狀而定,架距不大于1m當塌方較深時,則可先將進口至坍方體頂面一段箍好,不進行清理坍渣,而在洞內(nèi)采用穿過坍方體的施工方法.E坍塌空成斜孔時,處理方法根據(jù)斜度而定,傾角≤30°時,可按斜井的施工方法進行出渣及支撐;傾角≥35°時,運用井箍支撐及由上而下地清渣.⑶、襯砌措施與回填方法①襯砌施工坍方體清除過程中,隨著坍方體的清除,襯砌及時跟進,必要時,通過設(shè)計變更,增加仰拱(如果原設(shè)計上無),快速成環(huán)、封閉。在坍穴位最高處兩端襯砌接頭處預(yù)留回填及進出料孔。如坍塌方范圍的圍巖不穩(wěn)定,在處理坍塌方中有繼續(xù)坍方可能時,可在坍方范圍內(nèi)選擇適當位置做坍體保拱,以掩護施工操作,保證安全。護拱上用碎渣鋪填2m②坍體回填坍方體清除后,拱背先用漿砌片石回填2~3m厚,其上再用干砌片石回填,回填高度應(yīng)盡量填滿坍穴范圍,坍體內(nèi)木撐盡量拆除;在坍穴護拱與拱圈間應(yīng)全部回填密實,坍穴護拱以上回填厚度可根據(jù)具體情況而定,但不小于2m;如坍塌方范圍高大,在坍穴內(nèi)進行回填操作不便時,可選擇適當位置另行開鑿專供回填的坑道;如坍塌方直達地表,除按規(guī)定做好拱部回填外,另用一般土石回填夯實至距地表5、預(yù)防坍塌、涌水措施做好地質(zhì)預(yù)報,勤檢查,嚴格遵循“短進尺、弱爆破、早封閉、勤量測”的十二字原則施工。(一)、建立完善質(zhì)量管理制度,嚴格按照規(guī)范施工,嚴懲違章行為。(二)、對施工過程中發(fā)現(xiàn)的設(shè)計地質(zhì)不相符,而圍巖自穩(wěn)力極差,極容易坍塌地段,以及原有塌方地段加強監(jiān)控量測,防止引起坍塌.(三)、對圍巖情況與設(shè)計不符的時候,要立即與設(shè)計單位聯(lián)系,變更設(shè)計,調(diào)整支護參數(shù)。(四)、支護相對穩(wěn)定后,及時向監(jiān)理部、設(shè)計院上報,根據(jù)現(xiàn)場實際地質(zhì)情況采取相應(yīng)的變更設(shè)計施工支護措施,以防止隧道坍塌,確保施工人員安全及施工生產(chǎn)順利進行。、(五)、加強量測管理,及時反饋信息,施工員、量測人員每天必須檢查初期支護變形情況,為調(diào)整圍巖支護、爆破參數(shù)提供依據(jù),以確保工程結(jié)構(gòu)安全和作業(yè)人員人身安全。(六)、在洞內(nèi)安設(shè)安全逃生通道(直徑為80cm的鋼管,長度大于50米),位于掌子面與襯砌段之間,防止坍方事故造成人員傷亡.6、善后工作⑴、現(xiàn)場其他人員負責現(xiàn)場的清理,保障通道暢通,使救護車直達事發(fā)地點。⑵、搶救工作結(jié)束后,設(shè)專人保護現(xiàn)場,以便查明事故的原因。⑶、項目部經(jīng)理立即組織調(diào)查組,對事故現(xiàn)場進行調(diào)查,收集事故當事人和現(xiàn)場人員的陳述和證詞,開分析會查明直接和間接原因,確定事故的性質(zhì)和責任者.⑷、開事故現(xiàn)場會,教育廣大員工提高自身的安全意識,為確保安全生產(chǎn),杜絕類似事故再次發(fā)生.7、隧道發(fā)生坍塌部位和存在的征兆隧道坍塌一般由地質(zhì)差,斷面大和施工不當?shù)仍蛞穑鹛降闹饕蛉缦拢?一)、斷面帶及楔形部位坍方(二)、地面覆蓋過薄地段塌方,其中主要發(fā)生在沿河傍山淺埋、偏壓地段溝谷淺埋地段和丘陵淺埋地段。(三)、正洞與輔助坑道或避難坑道處坍塌;(四)、洞口地段支撐不當引起坍塌;(五)、工作面出現(xiàn)掉塊、掉碴、落石、初期支護面有新裂縫,初期支護結(jié)構(gòu)變形,有異常響聲等是發(fā)生坍塌前的一般現(xiàn)象。8、應(yīng)急響應(yīng)(一)、現(xiàn)場發(fā)生事故險情或發(fā)生事故時,現(xiàn)場安全員、領(lǐng)工員或工班長,必須立即組織人員撤離可能坍塌危險區(qū),在撤離時,應(yīng)保持秩序,危險部位先撤出的原則。嚴禁出現(xiàn)亂擁,亂擠的現(xiàn)象,以防止其它的意外事故的發(fā)生。同時報告應(yīng)急救援小組。(二)、所有人員撤出坍塌危險區(qū)域后,現(xiàn)場值班員在安全位置負責觀察圍巖的變化情況,同時設(shè)置安全警戒,防止其它人員進出危險區(qū)域。(三)、當發(fā)生事故時,現(xiàn)場值班領(lǐng)導(dǎo)應(yīng)采取相應(yīng)措施管制事態(tài)蔓延或擴大,并組織現(xiàn)場臨時救援。(四)、指揮部接到事故報告后,應(yīng)立即啟動應(yīng)急準備預(yù)案,組織有關(guān)人員、設(shè)備、設(shè)施及器材,趕赴現(xiàn)場采取有效措施搶救人員,防止事態(tài)蔓延和擴大,與此同時:1、事故發(fā)生后,應(yīng)通過或立即報告上級領(lǐng)導(dǎo),監(jiān)理處,任何人不得瞞報、緩報、謊報或者授意他人瞞報、緩報、謊報。2、若事態(tài)不能有效控制,在應(yīng)急救援小組統(tǒng)一指揮下,立即向當?shù)赜嘘P(guān)部門求援,必要時疏散人員。9、現(xiàn)場救援工程搶險(一)、迅速查明事故險情和人員受傷情況,防止搶救過程中發(fā)生再次事故,并迅速搶救傷員。(二)、處理坍方要及時迅速,詳細觀測坍方范圍、形狀、坍穴、地質(zhì)、水文情況,制定出處理方案,再進行處理;情況不明時,不可盲目冒險施工。(三)、對未坍方地段進行加固防止坍方發(fā)展,并進行密切監(jiān)控,確保穩(wěn)定方可對坍塌堆積體進行處理.(四)、當坍方仍有發(fā)展,先將頂部情況摸清處理妥當進行下部施工。處理坍方盡量不放炮,在坍穴內(nèi)工作,設(shè)置遇險時安全撤離通道。10、應(yīng)急處理措施(一)、當發(fā)生人員傷亡時,立即采取緊急救援工作,救援時必須2人以上進行防護,在確保救援人員無生命安全威脅的情況下進行挽救工作;若坍塌繼續(xù)無法救援時,則在安全位置守候待命,以便及時進行挽救,挽救過程中一定要保證挽救人員的生命安全,防止坍塌損害進一步擴大。(二)、塌方可能對受害者造成兩種嚴重的后果:一是土埋窒息,迅速造成死亡;二是土方石塊壓埋肢體,引起擠壓綜合癥。石塊土方壓埋肢體時間較長,大腿等肌肉豐滿處細胞易壞死,產(chǎn)生有毒物質(zhì),人一旦被救出,肢體重壓解除,毒素就進行入血液循環(huán),會引起急性腎功能衰竭。其表現(xiàn)為傷部邊緣出現(xiàn)紅班,肢體腫脹,傷員口干舌燥,惡心嘔吐,厭食、煩躁亂動,因此塌方要及時挽救。(三)、救出險境,挽救全身被土埋者,根據(jù)傷員所處的方向、確定部位,先挖去頭部的土物,使被埋者盡量露出頭部,迅速清潔其口中,鼻周圍的泥土,保持呼吸暢通,進行口對口呼氣,然后再挖出身體其他部位。(四)、對呼吸、心臟停止者,應(yīng)立即進行口對口人工呼吸、胸外擠壓。(五)對各種外傷進行現(xiàn)場處理。(六)、如果局部肢體受到擠壓,在局部解除壓力后,應(yīng)立即用夾板將傷肢牢牢地固定住,嚴禁不必要有肢體活動,傷部稍大暴露在涼爽空氣中。(七)、當搶救出傷員時,根據(jù)傷員人數(shù)、受傷程度,由醫(yī)務(wù)人員在現(xiàn)場采取相應(yīng)的救治措施,采取“先重后輕”的原則,及時將傷員送到醫(yī)院進行搶救、治療.(八)、若坍塌特別嚴重,自身救援能力有限時,應(yīng)立即上報地方政府或相關(guān)救助部門,請求緊急救援,同時做好相關(guān)配合救援工作.(九)、現(xiàn)場采取與坍塌程度及范圍相應(yīng)的的施工技術(shù)措施,控制坍塌的進一步發(fā)展,盡快恢復(fù)正常施工生產(chǎn).11、應(yīng)急結(jié)束事故險情得到有效控制,人員已全部被救,財產(chǎn)得到最大限度的保護后,應(yīng)急搶險救援工作結(jié)束.事故事件應(yīng)急救援工作流程圖搶救人員到位搶救人員到位接警信息反饋警情判斷響應(yīng)級別通訊網(wǎng)絡(luò)開通應(yīng)急資源調(diào)配現(xiàn)場指揮到位應(yīng)急啟動救援行動人員救助工程搶險警戒與現(xiàn)場封閉醫(yī)療救護人群疏散應(yīng)急增援應(yīng)急恢復(fù)事態(tài)控制響應(yīng)升級解除警戒現(xiàn)場清理善后處理事故調(diào)查應(yīng)急結(jié)束(關(guān)閉)專家支持現(xiàn)場監(jiān)測N審YYY總結(jié)評審YN事故發(fā)生應(yīng)急救援小組成員序號姓名職務(wù)聯(lián)系備注1張銳常務(wù)副經(jīng)理2張冬生副總工157147190663李繼東安質(zhì)部長186991119814李先乾工程部長5董曉亮測量隊長6肖騎物資部長7彭新澤財務(wù)部長8劉建平隧道工程師131099901609張志川施工隊長目錄第一節(jié)、編制依據(jù)····················································2第二節(jié)、工程概況····················································3第三節(jié)、臺風預(yù)警與預(yù)防··············································4一、有關(guān)臺風的相關(guān)介紹············································4二、臺風預(yù)警與預(yù)防················································4三、暴雨警報······················································6第四節(jié)、風險識別····················································7第五節(jié)、重點檢查及監(jiān)控內(nèi)容··········································7一、臨建設(shè)施······················································7二、圍擋墻························································8三、起重運輸機械··················································8四、腳手架工程···················································8五、臨時用電·····················································9第六節(jié)、預(yù)防措施····················································9一、組織措施······················································9二、技術(shù)措施······················································11三、人員物資準備·················································11四、臺風防御措施·················································12五、暴雨防御措施·················································14六、雷暴防御措施·················································15第七節(jié)、應(yīng)急處理···················································16一、通訊聯(lián)系·····················································16二、應(yīng)急準備·····················································16三、重大事故報告及報警原則·······································17四、救援器材及設(shè)備···············································17五、各類事故預(yù)防及應(yīng)急預(yù)案·······································18六、救援設(shè)備·····················································20七、應(yīng)急救援路線·················································21第一節(jié)、編制依據(jù)1、《建筑工程質(zhì)量檢查與驗收手冊》2、《施工組織設(shè)計》3、《本項目施工圖紙》4、《建筑施工現(xiàn)場環(huán)境與衛(wèi)生標準》JGJ146—20215、《建筑高處作業(yè)安全技術(shù)規(guī)范》JGJ80-20216、《建設(shè)施工安全檢查標準》JGJ59-20217、《建筑施工扣件鋼管腳手架安全技術(shù)規(guī)程》JGJ130-2021第二節(jié)、工程概況工程概況序號項目內(nèi)容1工程名稱蘇州綠地中央廣場三號地塊項目2工程地址蘇州市科技城龍山路與科發(fā)路交叉口3建設(shè)單位綠地集團蘇州高新置業(yè)4設(shè)計單位上海正軼建筑設(shè)計5勘察單位江蘇省地質(zhì)工程6建筑功能地下室為庫房、停車場,商鋪,地面樓層為商業(yè)用房7建筑面積及規(guī)模總建筑面積:約66406.47㎡,層數(shù)及單體建筑面積:3#樓為地下二層,地面36層.8檐高建筑檐高度:150m。9墻體類型框架柱、核心筒,內(nèi)墻砂加氣砼砌塊10屋面防水卷材、XPS擠塑聚苯板、鋼筋混凝土平屋面11幕墻玻璃幕墻12防水SBS改性瀝青防水卷材、防水涂膜13樓地面水泥樓地面14內(nèi)墻混合砂漿抹面15外墻玻璃幕墻。16保溫XPS擠塑聚苯板、50厚巖棉帶17標高:3#樓為4。2m(絕對標高),室內(nèi)外高差0.2m結(jié)構(gòu)概況序號項目內(nèi)容1結(jié)構(gòu)類型框架—核心筒2基礎(chǔ)類型樁筏基礎(chǔ)3抗震設(shè)防烈度6度4建筑結(jié)構(gòu)安全等級二級5耐火等級一級6鋼筋級別HPB300、HRB335、HRB400E第三節(jié)臺風預(yù)警與預(yù)防有關(guān)臺風的相關(guān)介紹1、臺風是發(fā)生于熱帶洋面上的一種熱帶氣旋。熱帶氣旋是:生成于熱帶或副熱帶洋面上,具有有組織的對流和確定的氣旋性環(huán)流的非鋒面性渦旋的統(tǒng)稱,包括熱帶低壓、熱帶風暴、強熱帶風暴、臺風、強臺風和超強臺風。當近地面最大風速到達或超過每秒17.2米時,即為臺風。2、熱帶氣旋分的等級劃分熱帶氣旋等級底層中心附近最大平均風速(m/s)底層中心附近最大風力(級)熱帶低壓(TD)10。8—17。16—7熱帶風暴(TS)17.2—24。48-9強熱帶風暴(STS)24。5—32。610—11臺風(TY)12-13強臺風(STY)41.5—50。914-15超強臺風(SuperTY)≥51.016或以上二、臺風預(yù)警與預(yù)防:1、預(yù)警等級、信號根據(jù)臺風影響范圍和程度,臺風預(yù)警等級分為四級:Ⅰ級(特別嚴重),Ⅱ級(嚴重),Ⅲ級(較重),Ⅳ級(一般)。臺風預(yù)警信號分五種,分別以白色、藍色、黃色、橙色和紅色表示。2、臺風預(yù)警信號及防御指引1)臺風白色預(yù)警信號(1)圖標:(2)含義:48小時內(nèi)可能受熱帶氣旋影響。(3)防御指引:a、警惕熱帶氣旋對當?shù)氐挠绊?;b、注意收聽、收看有關(guān)媒體的報道或通過氣象咨詢等氣象信息傳播渠道了解熱帶氣旋的最新情況,以決定或修改有關(guān)計劃。2)臺風藍色預(yù)警信號(1)圖標:
(2)含義:24小時內(nèi)可能受熱帶氣旋影響,平均風力可達6級以上,或陣風7級以上;或者已經(jīng)受熱帶氣旋影響,平均風力為6~7級,或陣風7~8級并可能持續(xù)。(3)防御指引:a、做好防風準備;b、注意有關(guān)媒體報道的熱帶氣旋最新消息和有關(guān)防風通知;c、固緊門窗、圍板、棚架、臨時搭建物,妥善安置易受熱帶氣旋影響的室外物品;d、其它同臺風白色預(yù)警信號。3)臺風黃色預(yù)警信號(1)圖標:
(2)含義:24小時內(nèi)可能受熱帶氣旋影響,平均風力可達8級以上,或陣風9級以上;或者已經(jīng)受熱帶氣旋影響,平均風力為8~9級,或陣風9~10級并可能持續(xù).(3)防御指引:a、進入防風狀態(tài),建議施工現(xiàn)場停止施工;b、關(guān)緊門窗,處于危險地帶和危房中的居民以及船舶,應(yīng)到避風場所避風,高空、水上等戶外作業(yè)人員應(yīng)停止作業(yè),危險地帶工作人員需撤離;c、相關(guān)應(yīng)急處置部門和搶險單位加強值班,密切監(jiān)視災(zāi)情,落實應(yīng)對措施;d、切斷危險的室外電源;e、停止露天施工活動,立即疏散人員;f、其它同臺風藍色預(yù)警信號.4)臺風橙色預(yù)警信號(1)圖標:
(2)含義:12小時內(nèi)可能受熱帶氣旋影響,平均風力可達10級以上,或陣風11級以上;或者已經(jīng)受熱帶氣旋影響,平均風力為10~11級,或陣風11~12級并可能持續(xù)。(3)防御指引:a、進入緊急防風狀態(tài),停止現(xiàn)場所有施工作業(yè);b、切勿隨意外出,確保呆在最安全的地方;c、其它同臺風黃色預(yù)警信號。5)臺風紅色預(yù)警信號(1)圖標:
(2)含義:12小時內(nèi)可能或者已經(jīng)受臺風影響,平均風力可達12級以上,或者已達12級以上并可能持續(xù)。(3)防御指引:a、進入特別緊急防風狀態(tài),停止現(xiàn)場所有施工作業(yè);b、人員應(yīng)盡可能呆在防風安全的地方,相關(guān)應(yīng)急處置部門和搶險單位隨時準備啟動搶險應(yīng)急方案;c、當臺風中心經(jīng)過時風力會減小或靜止一段時間,切記強風將會突然吹襲,應(yīng)繼續(xù)留在安全處避風;d、其它同臺風橙色預(yù)警信號。三、暴雨警報暴雨警報信號分為黃、紅、黑3個級別,如下所示:(一)黃色暴雨信號。其含義為:六小時內(nèi),本地將可能有暴雨發(fā)生。(二)紅色暴雨信號。其含義為:在剛過去的3小時內(nèi),本地部分地區(qū)降雨量已達50毫米以上,且雨勢可能持續(xù)。(三)黑色暴雨信號。其含義為:在剛過去的3小時內(nèi),本地部分地區(qū)降雨量已達100毫米以上,且雨勢可能持續(xù).第四節(jié)風險識別1、水淹(排水不暢)2、坍塌(坍塌或山體滑坡:包括構(gòu)造物、堆置物、土石方、深基坑(槽)倒塌、活動板房倒塌等等)3、道路濕滑或沖毀4、室外進水等造成的損失5、戶外高大設(shè)備倒塌(塔吊、標語牌、線桿、外架等)6、松散物飛揚造成的設(shè)備損害或人員傷害7、輸配電系統(tǒng)損壞8、觸電:電纜漏電、雷擊傷害。第五節(jié)重點檢查及監(jiān)控內(nèi)容
施工現(xiàn)場要實行嚴格的臺風來臨前檢查、臺風天氣持續(xù)期監(jiān)控、臺風天氣過后復(fù)查的檢查監(jiān)控制度,安排專人分工負責,對現(xiàn)場的臨建設(shè)施、圍擋檣、塔吊基坑設(shè)施、起重運輸機械、腳手架、施工用電等項目進行重點檢查和監(jiān)控。一、臨建設(shè)施
臨建設(shè)施包括:宿舍、食堂、辦公用房、廁所等。
監(jiān)控人的責任:全面檢查臨建設(shè)施的安全狀況,如有裂縫、傾斜、變形現(xiàn)象,及時采取加固、翻修,達不到要求的必須拆除重建;臺風暴雨天氣必須安排專人進行不間斷巡查;隨時觀察風雨對臨建設(shè)施的影響、受損情況及基坑、腳手架、塔吊等可能對臨建造成的破壞,如有危險立即將臨建內(nèi)人員轉(zhuǎn)移到安全地方。二、圍擋墻
圍擋墻包括:磚砌圍擋墻或其他。
監(jiān)控人的責任:全面檢查圍擋墻的安全狀況,如有破損、傾斜、變形等現(xiàn)象,及時采取加固、更換等措施;特別要加強對臨街圍擋墻的重點監(jiān)護,如有險情,立即對圍擋墻周邊設(shè)警示隔離設(shè)施,并設(shè)專人看護,嚴防圍墻倒塌傷人.三、起重運輸機械
起重運輸機械包括:塔吊、施工電梯。監(jiān)控人的責任:六級以上大風天氣應(yīng)立即停止作業(yè);重點監(jiān)控塔吊、人貨梯穩(wěn)定情況、附墻桿、排水情況、基坑對塔吊的影響等情況.四、腳手架工程監(jiān)控人的責任:六級以上大風天氣,禁止腳手架施工作業(yè);重點監(jiān)控腳手架基礎(chǔ)沉降情況、排水情況,確?;A(chǔ)穩(wěn)固;懸挑工字鋼是否彎曲變形;架體拉結(jié)有效;對臨近、房屋、高壓線處重點監(jiān)控,危險時應(yīng)對腳手架危及范圍內(nèi)設(shè)置警示隔離帶,并設(shè)專人監(jiān)護.臺風過后,對腳手架進行全面檢查驗收合格后,方可施工。五、臨時用電臨時用電包括:施工用電、生活用電等。
監(jiān)控人的責任:全面檢查施工現(xiàn)場的各類臨時用電設(shè)施、配電線路,嚴格實行三相五線制,確保做到三級配電、兩級保護,各類配電設(shè)施的防雨設(shè)施防護完好;臺風暴雨天氣應(yīng)立即切斷總電源,并準備好應(yīng)急照明器材。汛情過后,對配電系統(tǒng)進行全面的檢查驗收,符合安全要求后,方可送電施工。第六節(jié)預(yù)防措施一、組織措施1、以項目經(jīng)理為現(xiàn)場防臺風責任人,建立現(xiàn)場安全防臺風領(lǐng)導(dǎo)小組。防臺風小組職責為制定防臺風預(yù)案及防臺風檢查制度,教育現(xiàn)場每個施工人員要認真執(zhí)行各項防臺風安全管理制度.在氣象部門每次臺風預(yù)警信息發(fā)布后,項目經(jīng)理要立即組織防臺風小組成員開會,進行防臺風工作布置及組織各項防臺風措施落實。組織措施是其他各類措施的前提和保障,而且一般不需要增加什么費用,運用得當可以收到良好的效果,因此應(yīng)予以足夠的重視。防臺風領(lǐng)導(dǎo)小組組成責任和分工如下:姓名職務(wù)職責和分工組長李銀鋒項目經(jīng)理負責組織和指揮整個應(yīng)急救援工作副組長陳信友生產(chǎn)經(jīng)理協(xié)助組長開展工作組員陳利鋒質(zhì)量員1、協(xié)助組長做好事故報警,情況通報和事故處置工作。2、負責應(yīng)急救援的生活和救援物資供應(yīng)。3、負責消防、警戒、治安、保安、疏散和道路管制工作.4、現(xiàn)場救援工作。呂東芳施工員應(yīng)東祥機管員李慶明施工員陳信堯棟號長陳森祥棟號長李士勇材料員周光富安全員俞鄧安全員邵偉資料員3、防臺風管理制度:1)在工地宣傳欄發(fā)布臺風預(yù)警信息及停工通知,要求室外作業(yè)全部停工。2)所有彩鋼板瓦臨建房屋要求對屋面進行加固,防止臺風掀翻屋蓋。3)電氣設(shè)備要求覆蓋或安裝防雨設(shè)施,室外配電箱(柜)選用防雨設(shè)備.4)辦公室門窗、及精裝修外門窗要關(guān)嚴,防止室內(nèi)泡水,損失公司財產(chǎn).5)水泥倉庫要求四周疏通排水溝。室外臨時堆放的水泥要求蓋好雨布,位置較低的要求轉(zhuǎn)移.6)起重運輸機械井架未附墻的,要求及時附墻.7)外腳手架在頂部高度不能超過兩步架,并要求安裝好連墻件。8)臺風預(yù)警信息收到后,不能申請大型混凝土澆注。如樓面、地下室砼澆搗。二、技術(shù)措施1、由防臺風小組提出多個不同的防臺風方案及預(yù)案,然后對技術(shù)方案(預(yù)案)進行技術(shù)經(jīng)濟分析。優(yōu)選適合的技術(shù)方案。組織防臺風小組全體成員學(xué)習該方案。2、在臺風多發(fā)季節(jié)及時緊密的跟蹤氣象臺發(fā)布的氣象信息、臺風預(yù)報,臺風警報或緊急警報,以便在第一時間采取有效的措施,減輕或避免臺風帶來的損失.3、落實塔吊、人貨梯、電器等防臺風措施。塔吊、人貨梯、腳手架、工地圍墻等易兜風的設(shè)施要按相關(guān)技術(shù)要求進行防大風處理,多加側(cè)面支撐,防止倒塌和脫落;人貨梯要落地;用電設(shè)施和線路要逐一檢查,防止漏電和短路,對松散線路進行綁扎加固.三、人員物質(zhì)準備1、暴雨、臺風來臨前,現(xiàn)場要儲備足夠的物資以便暴雨、臺風后,迅速投入施工,保證施工繼續(xù)進行.2、暴雨或臺風來臨時,現(xiàn)場必須設(shè)人員值班,發(fā)現(xiàn)險情,立即按應(yīng)急方案采取應(yīng)急措施,暴雨或臺風后應(yīng)對現(xiàn)場所有設(shè)備、設(shè)施進行全面細致的檢查、整修,合格后方能投入使用。3、備足必需的搶險物資,搶險物資由施工組申報,材料組負責采購,倉庫負責保管,盡量做到防臺風專用,由防臺風小組安全員專人調(diào)配.1)編制袋400條;2)8號鐵線200kg;
3)柴油200kg;
4)水泵6臺;
5)應(yīng)急燈20盞;6)彩條布2000m2;7)面包車一輛.8)雨衣、雨褲、水鞋:50套四、臺風防御措施當天氣預(yù)警有臺風、暴雨災(zāi)害天氣時,采取以下安全措施:1、加強腳手架安全管理。排查所有內(nèi)外腳手架、模板支架、卸料平臺,特別是加強對腳手架基礎(chǔ)、架體結(jié)構(gòu)、拉結(jié)點、剪力撐的檢查,嚴把腳手架施工方案、技術(shù)交底和驗收關(guān),確保腳手架安全.2、加強大型機械設(shè)備安全管理。排查所有塔吊、人貸梯等大型機械設(shè)備,重點檢查大型機械設(shè)備的基礎(chǔ)、附墻、拉結(jié)點等涉及結(jié)構(gòu)穩(wěn)定的關(guān)鍵設(shè)施。對存在問題的,及時采取加固措施;四級風時,一律停止大型設(shè)備拆裝作業(yè);六級風或暴雨時,一律停止大型垂直運輸設(shè)備作業(yè),保證大型機械設(shè)備安全。3、加強高處作業(yè)安全管理。排查高處作業(yè)情況,重點檢查建筑工地“三寶”使用情況和臨邊洞口的防護情況。對存在問題的,立即予以整改.遇暴雨、六級以上強風,一律禁止進行攀登、懸空露天作業(yè),確保人員安全.4、加強工地臨時設(shè)施安全管理.排查建筑工地臨時工棚、材料倉庫、圍墻等臨時設(shè)施,對存在安全隱患的做好修繕加固工作,防止坍塌事故發(fā)生;對建筑工地出現(xiàn)堵水或內(nèi)澇的,及時采取措施處理;5、加強工地應(yīng)急處置準備管理。做好建筑工地應(yīng)急處置的準備用工作,儲備應(yīng)急物資、檢查應(yīng)急設(shè)備,組織應(yīng)急隊伍,要確保排水設(shè)施、機電設(shè)備的安全正常運行,確保垂直運輸設(shè)施的穩(wěn)固和防風安全,確保臨時用電設(shè)施防水防觸電的安全措施落實到位。6、注意及時收聽收看氣象災(zāi)害預(yù)警信息。本市氣象臺、電視臺、廣播電臺、12121氣象專線等媒體發(fā)布的臺風、暴雨等氣象災(zāi)害預(yù)警信息,根據(jù)天氣變化及時做好工地防汛防臺風工作。根據(jù)氣象信息的預(yù)警信號,工地各相關(guān)部門立即采取以下相應(yīng)行動:7、白色臺風信號時的行動:進入抗臺戒備狀態(tài),待召的應(yīng)急指揮即為全面負責落實防臺行動指揮,其他應(yīng)急組即為防臺、抗臺行動的協(xié)調(diào)人;檢查待招人員的通迅是否暢通;檢查塔吊基礎(chǔ)是否牢固、排柵等設(shè)施是否穩(wěn)固,包括臨時工柵是否安全,要采取措施加固、消除安全隱患.檢查各類門、窗等完整可靠;檢查所管戶外的松散物;蓋好所有戶外的蓋板;將臺風期間仍存放在戶外的設(shè)備、物件、起重機械等固定牢;檢查戶外電氣設(shè)備/臨時電氣設(shè)備的抗風/抗雨措施;檢查所管區(qū)域地面、地下的排水系統(tǒng)暢通;檢查應(yīng)急設(shè)備、如泵、水帶等隨時可用;注意收聽、收看有關(guān)媒體的報道或通過氣象咨詢等氣象信息傳播渠道了解的最新情況,以決定或修改有關(guān)計劃。8、綠色臺風信號時的行動:中止戶外一切高空作業(yè);檢查、保證消防設(shè)備及系統(tǒng)的可用性;關(guān)閉大門、窗戶,并檢查關(guān)閉是否牢固;將樓層外邊緣可能被風吹走的物品移入室內(nèi);檢查、保證戶外設(shè)備通道的安全性、即無阻塞、無松散物;檢查、保證工作人員的交接安排;檢查并保證食堂有維持24小時的食物;做好保安設(shè)備和保安亭的防護,必要時安排臨時出入口控制措施;安排12小時內(nèi)人員的交通;安排重型車輛和駕駛?cè)藛T,保證搶險活動的交通和機械正常;進一步清理松散物的,加固戶外堆放物件;檢查蓋好孔洞蓋板,確保蓋實穩(wěn)固;檢查、優(yōu)化臺風期間的工作計劃,根據(jù)氣象條件取舍工作項目;檢查、保證應(yīng)急抽水泵到預(yù)設(shè)現(xiàn)場;檢查電梯房/人貨梯防雨措施良好;檢查停車場和停放車輛;注意收聽廣播和電視隨播、增播、報道熱帶氣旋的最新消息和有關(guān)抗風通知。9、黃色臺風信號時的行動:大風到達前中斷一切戶外施工活動;關(guān)緊門窗;不要在迎風的窗戶旁站立;危險地帶和危房人員應(yīng)到避險場所避風;切斷危險的室外電源;嚴密監(jiān)視臺風對設(shè)施的影響,出現(xiàn)險情時及時撤離;再次檢查應(yīng)急組織人員的到崗情況。10、紅色或者黑色臺風信號時的行動:工地進入“應(yīng)急待命”狀態(tài),除值班人員堅守崗位外,其他所有人員在指定避難點原地待命,不得外出,遠離迎風門窗;當門窗被風損毀時,應(yīng)待風力沒有威脅時再行安裝;當臺風中心經(jīng)過當?shù)貢r,風力會減到很小或靜止一段時間,切記強風將會轉(zhuǎn)向突然吹襲,應(yīng)繼續(xù)留在安全處避風。11、臺風到來前嚴格按規(guī)定停止作業(yè)。臺風橙色預(yù)警信號發(fā)布后,要停止施工和高空作業(yè)。作業(yè)人員要減少戶外停留時間,特別注意不可在工地圍墻下躲風避雨。12、特殊情況下在高空作業(yè)突然來大風或臺風來臨時,施工人員不能及時下來躲避,要充分利用好安全帶,把安全帶牢牢系掛在牢固的結(jié)構(gòu)上面,確保安全帽的緊固性,必要時雙手緊抱鋼構(gòu)件或躲在設(shè)備擋風側(cè)系掛好安全帶,一定要就近尋找避風點,很多沒有經(jīng)歷過臺風的施工人員千萬不要過于慌亂,要保持鎮(zhèn)定。13、清理現(xiàn)場臨時用電箱,或?qū)﹄y以搬離的采取鋼絲繩斜拉筋固定,臺風來臨時一定要切斷現(xiàn)場施工總電源。14、加強工地排水,確保管網(wǎng)暢通。對周圍的排水管道進行清理,確保排水暢通,減少臺風期間工地積水;15、施工現(xiàn)場班房、辦公室及時采用鋼絲斜拉筋固定。臺風來臨前確保所有人員撤離施工現(xiàn)場.16、臺風來時,嚴禁進行設(shè)備吊裝,結(jié)構(gòu)安裝,砼澆筑,管道焊接、安裝等工作.17、必須進行砼澆筑時,應(yīng)用兩倍的草袋進行防護,并確保壓牢。18、施工現(xiàn)場的機具設(shè)備棚庫應(yīng)重新固定,棚庫上面和周圍的瓦楞板要綁扎牢固.19、現(xiàn)場的鐵皮、木板、彩鋼瓦等易被大風吹起的東西應(yīng)打掃干凈,材料設(shè)備擺好放牢,預(yù)制場地照明、動力電纜應(yīng)敷設(shè)好,固定牢固預(yù)防被臺風吹斷,發(fā)生漏電觸電事故。20、材料庫房和露天庫應(yīng)提前進行檢查,若有缺陷要馬上進行修整,露天庫的材料要擺放整齊,易損物件應(yīng)放入庫房保管,較輕的物品用重物壓好,或用鐵絲捆牢。五、暴雨防御措施1、檢查排水設(shè)施或通道的可用性,檢查應(yīng)排水設(shè)備的可用性,檢查門/窗/天臺等易進雨的設(shè)施,收蓋露天存放的物品疏散低洼易浸地區(qū)物資,要注意廣播、電視有關(guān)暴雨信息的最新廣播。發(fā)現(xiàn)險情,在采取了安全措施的情況下,組織搶險。雨后組織檢查,排除險情和隱串。2、暫停在空礦地方的戶外作業(yè);外出應(yīng)考慮天氣和道路情況是否許可;駕駛?cè)藛T應(yīng)注意道路可能出現(xiàn)嚴重水淹及交通擠塞;檢查戶外電氣設(shè)備/臨時電氣設(shè)備的抗風/抗雨措施;切斷低洼地帶有危險的室外電源;發(fā)現(xiàn)險情,在采取了安全措施的情況下,組織搶險。雨后組織檢查,排除險情和隱患。其它同黃色暴雨信號。3、員工留在室內(nèi),如住所可能出現(xiàn)嚴重水淹,則報警,組織救援,到安全地方暫避;停止戶外作業(yè);停止非事故搶險的交通運輸活動;如“黑"色信號在上班前發(fā)出,工地一律停工,除非有關(guān)暴雨時的情況下,組織搶險.雨后組織檢查,排除險情和隱患。其他同紅色暴雨信號.六、雷暴防御措施在6月之前完成所有防雷接地的檢查。雷暴期間,停止一切戶外活動,防雷暴措施方要如下:1、避雷針的設(shè)置安裝避雷針是防止直擊雷的主要措施.所有正在施工建造的建筑物,當高度在20m以上應(yīng)裝設(shè)避雷針。施工現(xiàn)場內(nèi)的塔式起重機,人貨梯及腳手架機械設(shè)備,若在相鄰建筑物、構(gòu)筑物的防雷設(shè)置的保護范圍以外,則應(yīng)安裝避雷針.若最高機械設(shè)備上有避雷針,且有保證最高機械設(shè)備最后退出現(xiàn)場,則其他設(shè)備可不設(shè)避雷針。機械設(shè)備上的避雷針的防雷引下線可利用該設(shè)備的金屬結(jié)構(gòu)體,但應(yīng)保證電氣聯(lián)接。機械設(shè)備所有的動力、控制、照明、信號及通信等線路,應(yīng)采用鋼管敷設(shè).鋼管與機械設(shè)備的金屬結(jié)構(gòu)體作焊接以保證其接地通道的電氣連接.2、避雷器裝設(shè)裝設(shè)避雷器是防止雷電侵入波的主要措施。高壓架空線路及電力變壓器高壓側(cè)應(yīng)裝設(shè)避雷器,避雷器的安裝位置應(yīng)盡可能靠近變電所.避雷器宜安裝在高壓熔斷器與變壓之間,以保護電力變壓器線路免于遭受雷擊。3、防止感應(yīng)雷擊的措施防止咸應(yīng)雷擊的措施是將被保護物接地。遵照國家標準《電氣裝置安裝工程接地裝置施工及驗收規(guī)范》(GB50169—92)的要求,建筑物在施工過程中,其避雷針(網(wǎng)、帶)及其接地裝置,應(yīng)采取自下而上的施工程序,即首先安裝集中接地裝置,后安裝引下線,最后安裝接閃器。建筑物內(nèi)的金屬設(shè)備、金屬管道、結(jié)構(gòu)鋼筋均應(yīng)做到有良好的接地。這樣做可保證建筑物在施工過程中防止感受應(yīng)雷。在施工中,高度在20m以上施工用的大鋼模板,就位后應(yīng)及時與建筑物的接地裝置連接。第七節(jié)應(yīng)急處理一、通訊聯(lián)系項目負責人:李銀鋒:安全員:周光富:醫(yī)院救護中心:120匪警:110火警:119通信聯(lián)系方式在施工現(xiàn)場和生活區(qū)的顯要位置張貼,便緊急情況下使用.二、應(yīng)急準備1、物資準備(1)食品準備:綜合部設(shè)置相對固定的食品供應(yīng)點,并與食品和飲用水生產(chǎn)廠家簽訂災(zāi)后食品、飲用水供應(yīng)協(xié)議。臺風發(fā)生后,綜合部聯(lián)系各食品供應(yīng)點安排一定數(shù)量食品供應(yīng)受災(zāi)干部群眾;(2)衣被和救生物品準備:由市救災(zāi)物資倉儲中心儲備,項目部根據(jù)災(zāi)情向市救災(zāi)物資倉儲中心申請供應(yīng)棉衣棉被、日用品、帳篷等日常急需物品和救生物品;(3)物資材料準備:生產(chǎn)部材料倉庫要保持儲備一定數(shù)量的防臺風物資存量,備品倉庫要保持儲備一定數(shù)量的發(fā)供電設(shè)備備品備件。2、應(yīng)急準備(1)管理人員在臺風季節(jié)及時跟蹤氣象臺天氣預(yù)報,及時向防臺風應(yīng)急負責人報告;(2)接到臺風預(yù)告后,根據(jù)臺風走向和趨勢的發(fā)展情況,及時啟動防臺風應(yīng)急預(yù)案,發(fā)布應(yīng)急準備指令,全體施工人員立即進入應(yīng)急準備狀態(tài);(3)項目部應(yīng)加強運行值班管理,及時調(diào)整、充實運行值班人員,安排,保證現(xiàn)場值班人員具備處理大型事故的能力;(4)項目部應(yīng)組織生產(chǎn)設(shè)備、設(shè)施搶險隊伍,隨時準備完成各種搶修任務(wù);(5)防臺風應(yīng)急領(lǐng)導(dǎo)小組適時向員工發(fā)出避災(zāi)疏散的指令和公告;(6)防臺風應(yīng)急領(lǐng)導(dǎo)小組應(yīng)協(xié)調(diào)組織防臺風搶險救援隊伍;(7)防臺風應(yīng)急小組研究部署防災(zāi)救災(zāi)工作,監(jiān)督、檢查應(yīng)急預(yù)案的實施,協(xié)調(diào)處理有關(guān)事項。三、重大事故報告及報警原則1、工地現(xiàn)場任何人發(fā)現(xiàn)發(fā)生重大事故的,必須立即報告工地負責人,工地負責人接到報告后,應(yīng)立即通知公司總部,并組織現(xiàn)場應(yīng)急救援小組開展現(xiàn)場搶救工作,如發(fā)生滑坡造成人員傷亡,應(yīng)第一時間直接打報120急救中心或蘇州市東渚醫(yī)院急救。2、公司領(lǐng)導(dǎo)接到事故報告后,應(yīng)立即組織公司應(yīng)急救援組趕赴施工現(xiàn)場,組織指揮現(xiàn)場搶救工作,同時將事故的概況(包括傷亡人員、發(fā)生事故時間、地點、原因等)分別用和快報的辦法報告上級主管部門以及政府有關(guān)部門。四、救援器材及設(shè)備1、通訊設(shè)備:包括固定、移動、對講機2、交通工具:供指揮、聯(lián)系、救援的用車3、急救藥品及器材:止血帶、頸托、擔架等救援器材等。4、救援設(shè)備:挖掘機、裝載機、自卸車等.五、各類事故的預(yù)防及其應(yīng)急預(yù)案:1、坍塌(山體滑坡)事故的預(yù)防及其應(yīng)急預(yù)案坍塌是指施工基坑(槽)坍塌、邊坡坍塌、模板支撐系統(tǒng)失穩(wěn)坍塌及施工現(xiàn)場臨時建筑(包括施工圍墻)倒塌等。(1)防止坍塌事故的基本安全要求:1)必須認真貫徹建設(shè)部“重申防止坍塌事故的若干規(guī)定”和“關(guān)于防止坍塌事故的緊急通知"精神,在項目施工中必須針對工程特點編制施工組織設(shè)計,編制質(zhì)量、安全技術(shù)措施,經(jīng)監(jiān)理單位審批后實施。2)土方工程、洞門開挖施工,須單獨編制專項的施工方案,編制安全技術(shù)措施,防止土方坍塌,尤其是制定防止洞頂土方坍塌的安全技術(shù)措施。①按土質(zhì)放坡或護坡:施工中,要按土質(zhì)的類別,較淺的基坑,要采取放坡的措施,對較深的基坑,要考慮采取護壁樁、錨桿等技術(shù)措施,必須有專業(yè)公司進行防護施工。(2)發(fā)生坍塌事故的應(yīng)急措施:1)當施工現(xiàn)場的監(jiān)控人員發(fā)現(xiàn)土方或建筑物有裂紋或發(fā)出異常聲音時,應(yīng)立即報告給應(yīng)急救援領(lǐng)導(dǎo)小組組長,并立即下令停止作業(yè),并組織施工人員快速撤離到安全地點。
2)當土方或建筑物發(fā)生坍塌后,造成人員被埋、被壓的情況下,應(yīng)急救援領(lǐng)導(dǎo)小組全員上崗,除應(yīng)立即逐級報告給主管部門之外,應(yīng)保護好現(xiàn)場,在確認不會再次發(fā)生同類事故的前提下,立即組織人員進行搶救受傷人員.3)當少部分土方坍塌時,現(xiàn)場搶救組專業(yè)救護人員要用鐵鍬進行撮土挖掘,并注意不要傷及被埋人員;當建筑物整體倒塌時,造成特大事故時,由市應(yīng)急救援領(lǐng)導(dǎo)小組統(tǒng)一領(lǐng)導(dǎo)和指揮,各有關(guān)部門協(xié)調(diào)作戰(zhàn),保證搶險工作有條不紊的進行。要采用吊車、挖掘機進行搶救,現(xiàn)場要有指揮并監(jiān)護,防止機械傷及被埋或被壓人員。4)被搶救出來的傷員,要由現(xiàn)場醫(yī)療室醫(yī)生或急救組急救中心救護人員進行搶救,用擔架把傷員抬到救護車上,對傷勢嚴重的人員要立即進行吸氧和輸液,到醫(yī)院后組織醫(yī)務(wù)人員全力救治傷員。5)當核實所有人員獲救后,將受傷人員的位置進行拍照或錄像,禁止無關(guān)人員進入事故現(xiàn)場,等待事故調(diào)查組進行調(diào)查處理.2、活動板房的安全措施活動板房結(jié)構(gòu)輕巧,不能抵抗級別較高的臺風,因此必須做到以下幾點防風措施:1)活動板房地基必須牢固,四周排水必須順暢;2)對屋面瓦進行加固,采用?48×3的腳手架鋼管在屋面上按橫豎向間距<3m設(shè)置成網(wǎng)格狀,鋼管之間用扣件連接。在板房的正面和背面距建筑物1m處,按間距3m將長100cm的?48×3鋼管打入地下,用?48×3鋼管扣件將屋面上的腳手架鋼管拉結(jié)在打入地下?48×3鋼管上.3)板房室內(nèi)外用電設(shè)備必須采用TN—S接地接零保護系統(tǒng),防止臺風將電線吹斷后造成火災(zāi)或人員觸電事故.板房加固示意圖:六、救援設(shè)備救援設(shè)備清單設(shè)備分類名稱及數(shù)量通訊器材對講機20部交通工具指揮車1部救援車120救員車救援設(shè)備裝載機挖掘機自卸車2臺1臺4臺急救藥品及器材止血帶頸托擔架滅火器20卷2個1個10個急救箱沙鏟編織袋雨衣雨鞋2個15400個50套七、應(yīng)急救援路線目錄一、工程概況1二、編制依據(jù)1三、預(yù)防教育措施1四、三寶管理措施2五、技術(shù)預(yù)防措施31、基坑(槽)坍塌預(yù)防措施32、邊坡坍塌預(yù)防措施63、腳手架坍塌事故預(yù)防措施64、模板支撐系統(tǒng)失穩(wěn)坍塌預(yù)防措施75、塔式起重機坍塌事故預(yù)防措施76、臨時設(shè)施坍塌預(yù)防措施8六、事故的控制、處理及資料8七、控制標準8防坍塌專項施工方案一、工程概況桂林市桂林市七星區(qū)福隆園片區(qū)(上關(guān)、三聯(lián))棚戶區(qū)改造項目03地塊1—9號樓、地下室工程位于桂林市七星區(qū)環(huán)城北二路南面、小東江東面,桂林醫(yī)學(xué)院西面。由桂林市環(huán)城水系建設(shè)開發(fā)、桂林市興進實業(yè)有限責任公司投資興建,廣西桂工監(jiān)理咨詢有限責任公司負責監(jiān)理,桂林市建筑設(shè)計研究院負責設(shè)計,桂林市勘察設(shè)計研究院負責地質(zhì)勘察,浙江宏宇建筑有限責任公司承建.本工程由地下1層,地上4~11層(1#~5#樓、9#樓為11層,6#~8#樓為4層).主要屋面(結(jié)構(gòu))標高為33.3m,框架剪力墻結(jié)構(gòu)?!?。000相對于黃海高程(絕對標高)為152。4m,總建筑面積約85350。81m2,其中地下面積22430。16m2,抗震設(shè)防烈度6度,建筑安全等級二級,建筑耐火等級一級,地基礎(chǔ)設(shè)計等級乙級。二、編制依據(jù)1《安全生產(chǎn)法》2《建筑工程預(yù)防高處墜落事故若干規(guī)定》(建質(zhì)[2003]82號)3《建筑施工安全檢查標準》(JGJ59—2021)4《建筑施工高處作業(yè)安全技術(shù)規(guī)范》(JGJ80-2021)5《鋼管扣件式腳手架安全技術(shù)規(guī)范》(JGJ130-2021)6《龍門架及井架物料提升機安全技術(shù)規(guī)范》JGJ88-20217其它有關(guān)安全管理的國家有關(guān)規(guī)范標準8桂林市桂林市七星區(qū)福隆園片區(qū)(上關(guān)、三聯(lián))棚戶區(qū)改造項目03地塊1-9號樓、地下室工程施工組織設(shè)計9桂林市桂林市七星區(qū)福隆園片區(qū)(上關(guān)、三聯(lián))棚戶區(qū)改造項目03地塊1—9號樓、地下室工程施工設(shè)計圖紙三、預(yù)防教育措施1、施工現(xiàn)場易發(fā)生施工坍塌事故起因主要有以下幾個方面:基坑坍塌;模板支撐體系;腳手架坍塌;臨時設(shè)施坍塌;為預(yù)防施工坍塌事故,保證施工安全,依據(jù)《安全生產(chǎn)法》《建筑施工安全檢查標準》對施工企業(yè)提出的要求,特編制本方案.2、根據(jù)建質(zhì)[2003]82號文《建筑工程預(yù)防坍塌事故若干規(guī)定》,建筑工程坍塌是指施工基坑(槽)坍塌、邊坡坍塌、基礎(chǔ)樁壁坍塌、模板系統(tǒng)失穩(wěn)坍塌及施工現(xiàn)場臨時建筑(包括施工圍墻)倒塌等,結(jié)合工地實際情況,本工程防坍塌措施主要防止施工基坑(槽)坍塌、邊坡坍塌、模板支撐系統(tǒng)失穩(wěn)、腳手架坍塌及臨時建筑倒塌。3、加大對安全生產(chǎn)的投入,設(shè)置安全管理機構(gòu)及配備專職安全管理人員,使安全生產(chǎn)的各項措施落實到人。4、加強對一線作業(yè)人員,尤其是民工的培訓(xùn)教育.公司安全培訓(xùn)教育的主要內(nèi)容是:國家和地方有關(guān)安全生產(chǎn)的方針、政策、法規(guī)、標準、規(guī)范、規(guī)程和企業(yè)的安全規(guī)章制度等。項目安全培訓(xùn)教育的主要內(nèi)容是:工地安全制度、施工現(xiàn)場環(huán)境、工程施工特點及可能存在的不安全因素等。班組安全培訓(xùn)教育的主要是:本工種的安全操作規(guī)程,事故案例剖析、安全紀律和崗位講評等.從而增強工人的安全意識,掌握安全知識,提高職工搞好安全生產(chǎn)的自覺性、積極性和創(chuàng)造性,使各項安全生產(chǎn)規(guī)章制度得以貫徹執(zhí)行。5、堅持班前安全活動,針對班組專業(yè)特點和作業(yè)條件,進行安全技術(shù)交底。安全技術(shù)交底主要包括兩方面的內(nèi)容:一是按照施工方案的要求,對施工方案進行細化和補充;二是要將操作者的安全注意事項講明,保證操作者的人身安全.6、落實安全生產(chǎn)責任制,強化安全檢查。工程項目經(jīng)理部的管理人員和專職、兼職安全員,要根據(jù)自身的工作特點和職責分工,嚴格執(zhí)行定期安全檢查制度,并經(jīng)常進行不定期的、隨機檢查.對于發(fā)現(xiàn)的問題和事故隱患,要按照“定人、定時間、定措施”的原則進行及時整改,并按時復(fù)查,消除事故隱患,防止安全事故的發(fā)生。7、采用新工藝、新技術(shù)、新設(shè)備施工和調(diào)換工作崗位時,項目部應(yīng)對操作人員進行新技術(shù)、新崗位的安全教育四、三寶管理措施安全帽、安全帶、安全網(wǎng)是建筑行業(yè)廣大職工公認的安全“三寶”,必須正確使用。必須從進貨的關(guān)口把住產(chǎn)品質(zhì)量關(guān),保證進入施工現(xiàn)場的產(chǎn)品是合格品,并加強對安全防護用品的管理,按規(guī)定配備個人安全防護用品。認真教育、嚴格檢查、督促職工正確佩戴使用。1、安全帽應(yīng)符合《安全帽》(GB2811-2007)國家標準。安全帽需經(jīng)常進行檢查,有異常損傷、裂痕等應(yīng)立即收回停止使用。2、每頂安全帽上應(yīng)有:制造廠名稱、商標、型號、制造年月、許可證編號等。并有出廠合格證。3、進入施工現(xiàn)場的人員必須正確佩戴安全帽,要系好帽帶,防止脫落,使其在高處墜落或物體打擊時起到保護作用。4、安全帶應(yīng)符合《安全帶》(GB6095-2021)要求,安全帶的帶體上應(yīng)縫有永久字樣的商標、合格證和檢驗證。合格證上應(yīng)注明:產(chǎn)品、生產(chǎn)年月、拉力試驗、沖擊實驗、制造廠名、檢驗員姓名等。5、高處作業(yè)人員必須系好安全帶.凡在2m以上高處作業(yè),必須系好合格的安全帶。有的高處作業(yè)點沒有掛安全帶的條件時,施工負責人應(yīng)為工人設(shè)置掛安全帶的安全拉繩、安
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025年度智能穿戴設(shè)備研發(fā)人員個人勞動合同書
- 2025年度股權(quán)抵押消費金融合同
- 二零二五年度同居關(guān)系終止合同書
- 二零二五年度瑜伽教練就業(yè)保障聘用合同
- 2025年度村委會林地承包與林業(yè)科研合作合同
- 浙江國企招聘2024臺州市椒江區(qū)社會事業(yè)發(fā)展集團有限公司招聘3人筆試參考題庫附帶答案詳解
- 2025青海省投招聘59人查筆試參考題庫附帶答案詳解
- 《臨床試驗的監(jiān)查》課件
- 電梯構(gòu)造知識培訓(xùn)課件
- 教育測量與評價知到智慧樹章節(jié)測試課后答案2024年秋石河子大學(xué)
- 山東建筑電氣與智能化疑難問題分析與解答
- 2022年鄭州衛(wèi)生健康職業(yè)學(xué)院單招英語模擬試題(附答案解析)
- Q∕GDW 10354-2020 智能電能表功能規(guī)范
- 土壤學(xué)習題與答案
- 國家自然科學(xué)基金(NSFC)申請書樣本
- 觀摩臺標準化建設(shè)方案
- 數(shù)字化影像與PACS教學(xué)大綱
- 凈身出戶離婚協(xié)議書(完善版)
- 壓瘡醫(yī)學(xué)護理課件
- 最小作業(yè)單元管理規(guī)定1
- excl表格形式綜合曲線坐標計算程序bata
評論
0/150
提交評論