項目專項施工方案
房建2標(biāo)段項目
4#STT253塔吊安拆方案
方案編制:
方案審核:
方案審批:
中建八局第一建設(shè)有限公司
2023年07月15日
1
項目專項施工方案
目錄
第一章編制依據(jù)...............................................................................................................................................4
第二章工程概況...............................................................................................................................................5
2.1工程概況..........................................................................................................................................................5
2.2塔吊設(shè)計概況..................................................................................................................................................6
2.3施工條件..........................................................................................................................................................7
第三章施工安排.............................................................................................................................................11
3.1管理人員配置及職責(zé)....................................................................................................................................11
3.2項目管理目標(biāo)................................................................................................................................................11
3.3勞務(wù)資源安排................................................................................................................................................11
3.4工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施........................................................................................................11
第五章施工準(zhǔn)備與資源配置計劃..................................................................................................................13
5.1施工準(zhǔn)備計劃................................................................................................................................................13
5.1.1技術(shù)準(zhǔn)備...............................................................................................................................................13
5.1.2現(xiàn)場準(zhǔn)備...............................................................................................................................................13
5.2資源配置計劃................................................................................................................................................13
5.2.1勞動力配置計劃....................................................................................................................................13
5.2.2主要機(jī)械配備計劃................................................................................................................................14
5.2.3測量計量設(shè)備配置計劃........................................................................................................................14
第六章施工方法及工藝要求..........................................................................................................................14
6.1方案及技術(shù)參數(shù)............................................................................................................................................14
6.2工藝流程........................................................................................................................................................18
6.3施工要點(diǎn)........................................................................................................................................................18
6.4驗(yàn)收標(biāo)準(zhǔn)及內(nèi)容............................................................................................................................................20
6.5驗(yàn)收人員及驗(yàn)收程序....................................................................................................................................22
第七章進(jìn)度管理計劃.....................................................................................................................................22
7.1確定施工進(jìn)度控制點(diǎn)....................................................................................................................................22
2
項目專項施工方案
7.2施工進(jìn)度管理組織結(jié)構(gòu)和職責(zé)分工............................................................................................................22
7.3進(jìn)度管理措施................................................................................................................................................22
第八章質(zhì)量管理計劃.....................................................................................................................................23
8.1質(zhì)量控制目標(biāo)分解........................................................................................................................................23
8.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工................................................................................................................23
8.3確定質(zhì)量控制點(diǎn)............................................................................................................................................23
8.4質(zhì)量保證措施................................................................................................................................................23
第九章安全管理計劃.....................................................................................................................................24
9.1職業(yè)健康安全管理分解目標(biāo)........................................................................................................................24
9.2安全管理組織機(jī)構(gòu)和職責(zé)分工....................................................................................................................24
9.3職業(yè)健康安全重大危險源............................................................................................................................24
9.4職業(yè)健康安全資源配置計劃........................................................................................................................25
9.5安全生產(chǎn)管理制度........................................................................................................................................25
9.6安全生產(chǎn)保證措施........................................................................................................................................26
9.6.1塔吊安拆施工安全保證措施................................................................................................................26
9.6.2使用過程中安全保證措施....................................................................................................................28
第十章環(huán)境管理計劃.....................................................................................................................................30
10.1環(huán)境管理目標(biāo)..............................................................................................................................................30
10.2環(huán)境管理組織機(jī)構(gòu)和職責(zé)分工..................................................................................................................30
10.3重大環(huán)境因素清單......................................................................................................................................30
10.4環(huán)境保護(hù)資源配置計劃..............................................................................................................................30
10.5環(huán)境保護(hù)措施..............................................................................................................................................30
第十一章綠色施工計劃.................................................................................................................................31
11.1綠色施工組織機(jī)構(gòu)和職責(zé)分工..................................................................................................................31
11.2綠色施工實(shí)施措施......................................................................................................................................31
11.3綠色施工評價..............................................................................................................................................31
第十二章成品保護(hù)管理計劃..........................................................................................................................31
3
項目專項施工方案
12.1成品保護(hù)組織機(jī)構(gòu)和職責(zé)分工..................................................................................................................32
12.2成品保護(hù)計劃及保證措施..........................................................................................................................32
第十三章應(yīng)急預(yù)案.........................................................................................................................................32
13.1事故類型和危害程度分析..........................................................................................................................32
13.2組織機(jī)構(gòu)及職責(zé)分工..................................................................................................................................33
13.3預(yù)防與預(yù)警..................................................................................................................................................33
13.3.1危險源監(jiān)控.........................................................................................................................................33
13.3.2預(yù)警行動.............................................................................................................................................33
13.4信息報告程序..............................................................................................................................................33
13.5應(yīng)急處置......................................................................................................................................................34
13.5.1響應(yīng)分級.............................................................................................................................................34
13.5.2響應(yīng)程序.............................................................................................................................................34
13.5.3處置措施.............................................................................................................................................34
13.5.4后期處理.............................................................................................................................................36
13.6塔吊安裝安全操作規(guī)程..............................................................................................................................36
13.7塔吊頂升安全操作規(guī)程..............................................................................................................................37
第十四章附件及附圖.....................................................................................................................................38
14.170噸汽車吊起重性能表.............................................................................................................................38
14.2立面圖附圖..................................................................................................................................................39
14.3塔機(jī)平面圖附圖..........................................................................................................................................40
4
項目專項施工方案
第一章編制依據(jù)
序號類別文件名稱編號
1《中華人民共和國安全生產(chǎn)法》國家主席令第70號
2《建設(shè)工程安全生產(chǎn)管理條例》國務(wù)院令第393號
國家行政文件住房和城鄉(xiāng)建設(shè)部《危險性較大的分部分項工程安全管
建設(shè)部令第37號
3理辦法》
4《建筑起重機(jī)械安全監(jiān)督管理規(guī)定》建設(shè)部令第166號
5《工程測量規(guī)范(附條文說明)》GB50026-2007
6《建設(shè)工程施工現(xiàn)場供用電安全規(guī)范》GB50194-2014
7《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
8《塔式起重機(jī)安全規(guī)程》GB5144-2006
9《塔式起重機(jī)》GB/T5031-2023
國家行業(yè)規(guī)范
10《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
11《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
12《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》JGJ46-2005
《建筑施工塔式起重機(jī)安裝、使用、拆卸安
13JGJ196-2010
全技術(shù)規(guī)程》
14《施工現(xiàn)場機(jī)械設(shè)備檢查技術(shù)規(guī)范》JGJ160-2016
15《技術(shù)質(zhì)量管理手冊》CSCEC81-JS-2023
企業(yè)管理文件
16《安全施工管理手冊》CSCEC81-AS-2023
17房建2標(biāo)段項目工程勘察報告(詳勘)/
其他
18STT253塔式起重機(jī)使用說明書/
第二章工程概況
2.1工程概況
工程名稱工程性質(zhì)科研廠房
建設(shè)規(guī)模(造
89846065.6元工程地址
價)
總占地面積3024.48㎡總建筑面積16,490.62平方米
建設(shè)項目的相關(guān)設(shè)計、采購、施工、
調(diào)試及試運(yùn)行、驗(yàn)收、保修、史邢路兩
項目承包范
建設(shè)單位側(cè)圍擋的維護(hù)及相關(guān)手續(xù)辦理、配合移
圍
交等工程總承包,不含精裝修工程、布
展工程、景觀工程、室外工程。
5
項目專項施工方案
設(shè)計單位
質(zhì)合格;符合現(xiàn)行的國家、省、市、法律、
勘察單位
量法規(guī)及規(guī)范要求。
全過程咨詢工
總工期365天
單位合期
同要安
總承包單位爭創(chuàng)“安全文明示范工地”
求全
綠
質(zhì)量監(jiān)督單
色施符合四節(jié)一環(huán)保要求
位
工
工程主要功科研、辦公、試驗(yàn)廠房
能或用途
2.2塔吊設(shè)計概況
表2.2-1塔吊設(shè)計概況
塔吊編號塔吊型號基礎(chǔ)頂標(biāo)高(m)初設(shè)安裝高度(m)最終安裝高度(m)
1#STT253(相對)18(1+3節(jié))51(1+14節(jié))
表2.2-2STT253塔吊70m起重性能表
6
項目專項施工方案
圖2.2-14#塔吊定位圖
2.3施工條件
1、道路及出入口:施工現(xiàn)場臨時道路具備通行條件,塔機(jī)東側(cè)和南側(cè)道路為預(yù)留道
路,具備通行條件;
2、供電設(shè)備:塔吊二級、三級箱已配備到位,具備供電條件;
3、塔吊基礎(chǔ):根據(jù)地勘報告中地基承載力數(shù)據(jù),天然基礎(chǔ)無法滿足要求,因此需設(shè)
計單位依據(jù)塔機(jī)性能參數(shù)計算復(fù)核樁基基礎(chǔ)參數(shù),詳情見塔吊基礎(chǔ)樁基圖紙。
圖2.3-1塔吊樁基礎(chǔ)結(jié)構(gòu)圖
7
項目專項施工方案
根據(jù)框架決定
基礎(chǔ)上平面
接地
在固定角鋼右邊澆注時使用的鋼筋數(shù)量既不能切短也不能
減少
山東中誠機(jī)械租賃有限公司
(材料標(biāo)記)
標(biāo)記處數(shù)更該文件號簽字日期
設(shè)計標(biāo)準(zhǔn)化
校對審定圖樣標(biāo)記重量比例
審核jc-002
工藝日期
圖2.3-2塔機(jī)塔機(jī)腳柱與基礎(chǔ)相對位置關(guān)系圖
8
項目專項施工方案
圖2.3-3基礎(chǔ)配筋圖
4、場地:塔吊基礎(chǔ)周邊已清理平整完畢,具備安裝工作面。
9
項目專項施工方案
第三章施工安排
3.1管理人員配置及職責(zé)
序號姓名崗位名稱職責(zé)
1項目經(jīng)理負(fù)責(zé)塔吊安拆過程對外關(guān)系,負(fù)責(zé)塔吊安裝過程安全監(jiān)督
1、負(fù)責(zé)塔吊安拆方案的審核
2、負(fù)責(zé)塔吊安拆過程方案的落實(shí)和檢查,確?,F(xiàn)場按照方案執(zhí)行
2項目總工
3、負(fù)責(zé)聯(lián)系塔吊進(jìn)場事宜
4、負(fù)責(zé)塔吊安拆過程各家單位配合協(xié)調(diào)
3商務(wù)經(jīng)理塔吊安拆過程資金總協(xié)調(diào)
1、全面負(fù)責(zé)塔吊安拆過程的安全監(jiān)督
4安全部2、對接當(dāng)?shù)匕脖O(jiān)站關(guān)于塔吊安拆過程的要求
3、負(fù)責(zé)塔吊進(jìn)場安全管理、塔吊司機(jī)管理、安裝工執(zhí)證上崗情況
1、負(fù)責(zé)現(xiàn)場的統(tǒng)一安排和現(xiàn)場指揮
5專業(yè)工程師
2、負(fù)責(zé)現(xiàn)場施工監(jiān)督協(xié)調(diào)
1、塔吊安裝前地腳螺栓地位復(fù)核
2、塔吊安拆過程垂直度校核
6測量工程師
3、塔吊安裝完后垂直度檢查
4、塔吊使用過程定期檢查塔身垂直度
7質(zhì)量部對塔吊構(gòu)件進(jìn)場質(zhì)量進(jìn)行驗(yàn)收檢查
租賃單位技術(shù)負(fù)
8全面負(fù)責(zé)塔吊安拆施工過程中相關(guān)事宜
責(zé)人
3.2項目管理目標(biāo)
項目管理目標(biāo)名稱目標(biāo)值
工期3天
質(zhì)量符合規(guī)范及說明書要求
特種作業(yè)人員持證上崗率100%;安全防護(hù)用品正確配備率100%;無高空
安全
墜落事故、觸電事故、起重設(shè)備坍塌事故及重傷事故的發(fā)生
綠色施工噪音污染可控
3.3勞務(wù)資源安排
施工開始施工分包商選
專業(yè)隊伍資質(zhì)要求工期分包方式責(zé)任人
項目時間定方式
塔吊山東中誠機(jī)械租賃
二級3天租賃公司選定
安拆有限公司
3.4工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對措施
序號重難點(diǎn)具體分析應(yīng)對措施責(zé)任人
10
項目專項施工方案
塔吊安拆前與作業(yè)面范圍內(nèi)其他
塔吊安裝與土方開挖、基礎(chǔ)開挖工
分包提前溝通協(xié)調(diào),避免同時作
1交叉作業(yè)作面同時進(jìn)行,場內(nèi)大型機(jī)械較多,
業(yè),安拆期間在作業(yè)面周圍設(shè)置
易造成人員傷害
警戒區(qū),避免造成人員傷害
第四章施工進(jìn)度計劃
4#塔吊計劃于2023年08月10日進(jìn)場,8月14日進(jìn)行安裝,安裝工期3天,計劃拆
除時間2023年03月01日,拆除工期3天。
11
項目專項施工方案
第五章施工準(zhǔn)備與資源配置計劃
5.1施工準(zhǔn)備計劃
5.1.1技術(shù)準(zhǔn)備
表5.1-1技術(shù)文件準(zhǔn)備計劃
序號文件名稱配備數(shù)量持有人
技術(shù)部
14#塔吊安拆施工方案各3安全部
工程部
2STT253塔吊說明書1
表5.1-2技術(shù)復(fù)核計劃
序號技術(shù)復(fù)核部位復(fù)核內(nèi)容責(zé)任人
1塔吊各部件各部件使用功能
2塔身垂直度、銷釘連接情況
5.1.2現(xiàn)場準(zhǔn)備
1塔吊周圍20米范圍內(nèi)場地平整完畢;
2塔吊基礎(chǔ)強(qiáng)度、平整度、接地等滿足規(guī)范及說明書要求(詳見塔吊基礎(chǔ)施工方
案);
3塔吊二級箱配備到位,布設(shè)于塔吊3米范圍內(nèi);
4汽車吊支設(shè)位置場地平整、堅實(shí)。
5.2資源配置計劃
5.2.1勞動力配置計劃
表5.2-1勞動力配備及職責(zé)分工
人員數(shù)量崗位職責(zé)
總指揮1名負(fù)責(zé)現(xiàn)場指揮和協(xié)調(diào)
安裝班長1名帶領(lǐng)本班組人員進(jìn)行設(shè)備安裝施工
安全員1名負(fù)責(zé)塔吊安裝施工的安全工作
安裝電工1名負(fù)責(zé)塔吊電氣連接和調(diào)試
拆裝工人4名負(fù)責(zé)塔吊各部件的安裝
信號工2名負(fù)責(zé)指揮吊車、塔吊進(jìn)行各部件的吊裝
設(shè)備員1名負(fù)責(zé)塔吊安裝及頂升所需的工具
汽車吊司機(jī)1名負(fù)責(zé)安塔過程中汽車吊的操作
12
項目專項施工方案
塔吊司機(jī)1名負(fù)責(zé)安裝過程中塔吊的操作
5.2.2主要機(jī)械配備計劃表5.2-2主要機(jī)械配備計劃
序號名稱規(guī)格型號數(shù)量備注
1手拉鏈條葫蘆2t4個
2手拉鏈條葫蘆1t2個
3大錘18SbI、12SbI各2把
4鐵錘4SbI、3SbI各2把
5沖子Φ364個
6起重用鋼絲繩6×37-1550-184×4m
7起重用鋼絲繩6×37-1550-184×8m
8卡環(huán)12t4個
9卡環(huán)8t6個
10卡環(huán)5t6個
11枕木180×200×200020條
12油壓千斤頂16t1個
13鉗工工具常用1批
14電工工具常用1批
15大型輔助吊機(jī)詳見安塔吊車站位圖1臺
16輔助吊機(jī)50t汽車吊1臺
17麻繩30m/150m2條/1條
安裝臨時
18電纜3×120mm2+1×35mm2120m
電纜
19常用起重鋼絲繩及卡環(huán)/1批
5.2.3測量計量設(shè)備配置計劃
表5.2-3測量計量設(shè)備配置計劃
序號儀器名稱分類數(shù)量使用特征檢定周期保管人
水平定位及
1全站儀B112個月
垂直度測量
2水準(zhǔn)儀B1標(biāo)高測量12個月
第六章施工方法及工藝要求
6.1方案及技術(shù)參數(shù)
1、主要安裝部件的重量和吊點(diǎn)位置見表6-1。
13
項目專項施工方案
表6-1主要安裝部件的重量和吊點(diǎn)位置
STT253零部件重量表
部件名稱重量(kg)備注
基礎(chǔ)節(jié)5104
標(biāo)準(zhǔn)節(jié)2095
爬升架5170
回轉(zhuǎn)總成7216
塔頭總成4000
70米起重臂平衡
8×400032t
重
70米起重臂組合
部件名稱重量(Kg)部件名稱重量(Kg)
SAMJ20013905J2008A1435
SAMJ20022865LJ2009A1040
J2006B2240PJ2506450
PJ20032017PJ2507356
70米平衡臂組合
部件名稱重量(Kg)部件名稱重量(Kg)
平衡臂總成9144配重臂6415
平衡臂1950
2、7.5m過渡節(jié),重5.1t;標(biāo)準(zhǔn)節(jié)每節(jié)重2.095t(吊點(diǎn)為四個吊裝孔,如圖所示)。
14
項目專項施工方案
圖6-1過渡節(jié)圖6-2頂升套架
3、頂升套架重量為5.17t(四個角銷軸孔為吊裝孔,如圖所示)。
圖6-3回轉(zhuǎn)總成
4、回轉(zhuǎn)總成重量為7.216t(四角銷軸孔為吊裝孔)。
5、起重臂70米,重16.5t,逐節(jié)安裝,見圖6-4。
圖6-4起重臂
6、塔吊平衡臂Ⅰ長4m,重量為1.95t,平衡臂Ⅱ長11.413m,重量為6.415t(含部
分拉桿及起升機(jī)構(gòu))。
15
項目專項施工方案
圖6-5平衡臂Ⅱ圖6-6平衡臂Ⅰ
8、平衡重總計32噸,共8塊8×4.0t=32t(有專用吊裝孔)。
圖6-7平衡重
16
項目專項施工方案
2汽車吊選用及布置
塔機(jī)安裝采用一臺70t汽車吊,其性能見附表。汽車吊可通過硬化道路進(jìn)入現(xiàn)場,到
達(dá)基礎(chǔ)中心附近10m的位置,支開汽車吊用于安裝。
6.2工藝流程
安裝基礎(chǔ)節(jié)——安裝三節(jié)標(biāo)準(zhǔn)節(jié)——安裝頂升套架——安裝回轉(zhuǎn)總成——安裝駕駛
室——安裝平衡臂——安裝一塊(最靠近塔身的)配重——安裝起重臂——安裝剩余配重。
6.3施工要點(diǎn)
1基礎(chǔ)節(jié)及標(biāo)準(zhǔn)節(jié)安裝
1)在基礎(chǔ)節(jié)上將吊具按吊點(diǎn)綁扎好,輔助設(shè)備起鉤拉緊鋼絲繩,吊運(yùn)并緩而穩(wěn)地就
位至預(yù)埋腳柱連接處,立放基礎(chǔ)節(jié),將塔身基礎(chǔ)節(jié)總成插入固定支腳(但絕不要插入固定
支腳固定框內(nèi)),用銷軸將基礎(chǔ)節(jié)和固定支腳連接,再用鎖銷將銷軸固定。
2)標(biāo)準(zhǔn)節(jié)的安裝如同1)步驟。
注意事項:安裝方向要正確,基礎(chǔ)節(jié)和標(biāo)準(zhǔn)節(jié)爬升塊在頂升時起重臂所在的對側(cè);銷
軸打入時要注意立銷孔方向,以免立銷無法打入。
此階段70t汽車吊在10m作業(yè)半徑內(nèi),伸桿37.9m,工況下吊重13t,滿足吊裝要求。
2套架安裝
1)在地面將油缸,活塞桿朝下安裝在并用銷軸固定在套架上,裝上頂升橫擔(dān),并用
銷軸與油缸連接。
2)安裝附屬操作平臺、欄桿組裝好,需要綁扎的,用8#鐵絲綁扎。操作平臺和欄桿
的安裝如下:
用軸銷將走道支撐銷固在套架上;
吊起通道用軸銷銷固在套架上;
立起通道撐桿用軸銷銷固在通道處;
裝上護(hù)欄且銷固;
用固定箍將護(hù)欄組裝在一起;
3)在頂升套架上將吊具按吊點(diǎn)綁扎好,輔助設(shè)備起鉤拉緊鋼絲繩,吊運(yùn)并緩而穩(wěn)地
就位至基礎(chǔ)節(jié)正上方,起重人員輔助頂升導(dǎo)輪就位,將套件套在標(biāo)準(zhǔn)節(jié)外側(cè),并將頂升橫
擔(dān)固定在基礎(chǔ)節(jié)上的爬升塊上,且將頂升套架鎖在基礎(chǔ)節(jié)橫腹桿上。吊放頂升泵站到下層
的操作平臺上。
注意事項:安裝方向要正確,基礎(chǔ)節(jié)和標(biāo)準(zhǔn)節(jié)爬升塊在頂升套架缺口側(cè)的對側(cè)。
17
項目專項施工方案
3回轉(zhuǎn)總成的安裝
1)將吊具掛在上支座四個支柱耳套下,將回轉(zhuǎn)支承總成吊起;
2)將回轉(zhuǎn)支承總成放緩慢在塔身頂部。切記下支座的引進(jìn)梁應(yīng)與塔身節(jié)踏步的位置
關(guān)系;下支座與套架連接時,應(yīng)對好四角的標(biāo)記;
3)用銷軸將下支座與標(biāo)準(zhǔn)節(jié)連接牢固,用鎖銷固定;
4)操作頂升系統(tǒng),將液壓油缸伸長至基節(jié)的下踏步上,將頂升套架頂升至與下支座
連接耳板接觸,用銷軸將頂升套架與下支座連接牢固。
5平衡臂與起重臂的安裝
1)平衡臂的安裝
在地面上組裝好平衡臂總成,電控系統(tǒng)(一個電控柜、兩個電阻箱)、行走平臺護(hù)欄和
拉桿均裝在后臂節(jié)上。
a.吊起平衡臂總成,用銷軸將平衡臂前后節(jié)臂固定聯(lián)接好。
b.將平衡臂逐漸抬高至適當(dāng)?shù)奈恢?,便于其拉桿與過渡節(jié)后向銷軸孔順利相連,將拉
桿用銷軸聯(lián)接,安裝開口銷并張開。
c.緩慢地將平衡臂下放使其上拉桿受力,再吊裝起升機(jī)構(gòu)至相應(yīng)位置,用銷軸與平衡
臂結(jié)構(gòu)聯(lián)接好。
2)司機(jī)室的安裝
司機(jī)室內(nèi)的電氣設(shè)備安裝齊全后吊起司機(jī)室。把司機(jī)室放在上支座靠右平臺的前端,
對準(zhǔn)耳板上孔的位置,然后用三根銷軸聯(lián)接并穿好開口銷。
3)起重臂的安裝
(1)在地面上,將①(引入變幅小車并固定在臂根部)和②起重臂節(jié)組裝好;
(2)將組裝好的起重臂節(jié)吊起,移動起重臂節(jié)根部至平衡臂根部,將下弦耳板插入聯(lián)
板中,并掛在銷軸上;
(3)抬起起重臂,將上弦耳板插入聯(lián)板中,用銷軸固定;
(4)緩慢放下起重臂讓上弦銷軸受力;
(5)吊裝完第一、第二節(jié)起重臂后汽車吊移動至基礎(chǔ)南側(cè)30米的位置進(jìn)行剩余吊裝
工作;
6配重塊的安裝
首先將鋼絲繩穿入吊耳中,吊起配重塊,將平衡臂上的銷軸插入配重塊孔內(nèi)。其余配
7穿繞鋼絲繩
1)變幅機(jī)構(gòu)的穿繞方法
18
項目專項施工方案
2)起升機(jī)構(gòu)的穿繞方法
6.4驗(yàn)收標(biāo)準(zhǔn)及內(nèi)容
檢查項目檢查內(nèi)容
檢查可拆卸地腳與過渡節(jié)是否安裝到位并鎖緊
基礎(chǔ)檢查輸電線距塔機(jī)最大旋轉(zhuǎn)部分的安全距離
檢查電纜通過情況,以防損壞
19
項目專項施工方案
檢查項目檢查內(nèi)容
塔身檢查標(biāo)準(zhǔn)節(jié)連接銷軸是否安裝到位并鎖緊
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 運(yùn)動副 課程設(shè)計
- 足球課程設(shè)計的思路
- 通信原理matlab實(shí)驗(yàn)課程設(shè)計
- 插齒機(jī)機(jī)械原理課程設(shè)計
- 送貨上門課程設(shè)計
- 郵件收發(fā)程序Java課程設(shè)計
- 裝配式建筑施工課程設(shè)計
- 物流會計做賬課程設(shè)計
- 2025年度工業(yè)機(jī)器人OEM定制與技術(shù)服務(wù)合同3篇
- 2024版大型廠房出租及配套設(shè)施租賃與管理服務(wù)合同3篇
- 鷓鴣山隧道瓦斯地段專項施工方案
- HG∕T 2058.1-2016 搪玻璃溫度計套
- 九宮數(shù)獨(dú)200題(附答案全)
- 泌尿科一科一品匯報課件
- 白銅錫電鍍工藝
- 拜耳法氧化鋁生產(chǎn)工藝
- 2024年南京信息職業(yè)技術(shù)學(xué)院高職單招(英語/數(shù)學(xué)/語文)筆試歷年參考題庫含答案解析
- 部編版二年級下冊道德與法治第二單元《我們好好玩》全部教案
- 幼兒園利劍護(hù)蕾專項行動工作方案總結(jié)與展望
- 合同信息管理方案模板范文
- 2024年大唐云南發(fā)電有限公司招聘筆試參考題庫含答案解析
評論
0/150
提交評論