新建臨沂臨港疏港鐵路工程
路基石方爆破專項(xiàng)施工方案
編制:
審核:
審批:
日期:
目錄
第一章編制依據(jù)....................................................................................................................1
第二章工程概況....................................................................................................................1
2.1工程概述....................................................................................................................1
2.2地形地貌、地質(zhì)條件................................................................................................2
2.3周圍環(huán)境條件............................................................................................................3
2.4施工任務(wù)及要求........................................................................................................3
2.5主要工程數(shù)量............................................................................................................4
第三章施工安排....................................................................................................................4
3.1現(xiàn)場(chǎng)管理組織............................................................................................................4
3.2現(xiàn)場(chǎng)管理目標(biāo)............................................................................................................6
第四章施工進(jìn)度計(jì)劃............................................................................................................6
第五章施工準(zhǔn)備與資源配置計(jì)劃........................................................................................7
5.1技術(shù)準(zhǔn)備....................................................................................................................7
5.2施工現(xiàn)場(chǎng)準(zhǔn)備............................................................................................................8
5.3資源配置計(jì)劃............................................................................................................9
5.3.1設(shè)備配備.........................................................................................................9
5.3.2人員配備.........................................................................................................9
5.3.3測(cè)量設(shè)備配置計(jì)劃.......................................................................................10
第六章爆破施工工藝..........................................................................................................10
6.1鑿巖機(jī)具及爆破器材的選取..................................................................................10
6.1.1鑿巖機(jī)具的選取...........................................................................................10
6.1.2爆破器材的選取...........................................................................................11
6.2爆破參數(shù)設(shè)計(jì)..........................................................................................................11
6.2.1中深孔爆破參數(shù)設(shè)計(jì)...................................................................................11
6.2.2光面爆破參數(shù)...............................................................................................15
6.2.3起爆網(wǎng)絡(luò)設(shè)計(jì)...............................................................................................19
6.3爆破施工工藝流程..................................................................................................20
6.4爆破施工方法選擇..................................................................................................21
I
6.5爆破安全校核..........................................................................................................24
6.5.1爆破振動(dòng)安全控制.......................................................................................24
6.5.2爆破飛石的控制...........................................................................................25
6.5.3空氣沖擊波安全距離...................................................................................25
第七章工期保證措施..........................................................................................................26
7.1工期保證體系..........................................................................................................26
7.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工......................................................................27
7.3工期保證措施..........................................................................................................27
第x章質(zhì)量保證措施..........................................................................................................28
8.1質(zhì)量目標(biāo)..................................................................................................................28
8.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工..........................................................................28
8.3質(zhì)量保證體系..........................................................................................................30
8.4施工質(zhì)量管理措施..................................................................................................30
第九章安全施工措施..........................................................................................................31
9.1職業(yè)健康安全管理目標(biāo)..........................................................................................31
9.2建立安全組織機(jī)構(gòu),明確安全職責(zé)和權(quán)限..........................................................32
9.3職業(yè)健康安全重大危險(xiǎn)源分析..............................................................................33
9.4安全生產(chǎn)管理制度..................................................................................................36
9.4.1班前活動(dòng)記錄...............................................................................................36
9.4.2機(jī)械設(shè)備管理制度.......................................................................................37
9.4.3特種作業(yè)持證上崗制度...............................................................................38
9.4.4爆破器材保管制度.......................................................................................38
9.4.5爆炸物品的現(xiàn)場(chǎng)臨時(shí)保管制度...................................................................39
9.4.6爆破作業(yè)安全管理制度...............................................................................39
9.5安全技術(shù)與防護(hù)措施..............................................................................................41
9.5.1安全技術(shù)措施...............................................................................................41
9.5.2爆破器材運(yùn)輸安全措施...............................................................................41
9.5.3爆破器材臨時(shí)存放安全防護(hù)措施...............................................................42
9.5.4爆破器材領(lǐng)用、發(fā)放、清退安全措施.......................................................42
II
9.5.5爆破器材保管安全措施...............................................................................42
9.5.6盲炮的處理措施...........................................................................................43
9.5.7爆破作業(yè)防護(hù)措施.......................................................................................43
9.5.8爆破試驗(yàn)安全措施.......................................................................................44
9.5.9施工安全措施...............................................................................................45
9.5.10光面爆破施工作業(yè).....................................................................................45
9.5.11控制爆破飛石、振動(dòng)的安全措施.............................................................47
第十章安全警戒..................................................................................................................48
10.1爆破安全警戒措施................................................................................................48
10.2裝藥時(shí)的警戒........................................................................................................48
10.3爆破時(shí)警戒點(diǎn)........................................................................................................48
10.4爆破時(shí)的警戒........................................................................................................49
10.5爆破時(shí)警戒信號(hào)....................................................................................................49
10.6警戒清場(chǎng)................................................................................................................50
10.7起爆........................................................................................................................50
10.8爆后檢查................................................................................................................50
第十一章環(huán)境保護(hù)與文明施工..........................................................................................51
11.1環(huán)境保護(hù)及文明施工管理措施............................................................................51
11.2資源利用管理........................................................................................................51
11.2.1資源利用管理目標(biāo).....................................................................................51
11.2.2資源利用職責(zé)分工.....................................................................................51
11.3“五節(jié)”實(shí)施措施....................................................................................................53
11.3.1節(jié)能措施.....................................................................................................53
11.3.2節(jié)材措施.....................................................................................................53
11.3.3節(jié)水措施.....................................................................................................53
11.3.4節(jié)地措施.....................................................................................................53
11.3.5人力節(jié)約措施.............................................................................................54
11.4環(huán)境保護(hù)措施........................................................................................................54
11.5文明施工措施........................................................................................................54
III
第十二章爆破作業(yè)審批流程..............................................................................................55
12.1爆破方案的審批....................................................................................................55
12.2爆炸物品的審批及使用........................................................................................55
12.3爆破記錄................................................................................................................56
第十三章事故的預(yù)防和應(yīng)急預(yù)案......................................................................................57
13.1危險(xiǎn)源的辨識(shí)及分析............................................................................................57
13.2應(yīng)急組織機(jī)構(gòu)及職責(zé)............................................................................................57
13.3預(yù)防與預(yù)警措施....................................................................................................61
13.3.1爆破事故的預(yù)防.........................................................................................61
13.3.2對(duì)周邊環(huán)境造成影響的防范.....................................................................62
13.3.3對(duì)周邊環(huán)境造成影響的防范.....................................................................62
13.4應(yīng)急響應(yīng)................................................................................................................62
13.5信息發(fā)布................................................................................................................63
13.6后期處置................................................................................................................64
13.7保障措施................................................................................................................64
13.8應(yīng)急培訓(xùn)與演練....................................................................................................66
13.9應(yīng)急救援路線........................................................................................................67
第十四章新型冠狀病毒肺炎疫情防控預(yù)案......................................................................67
14.1風(fēng)險(xiǎn)分析................................................................................................................67
14.2疫情響應(yīng)對(duì)策........................................................................................................68
14.3防護(hù)及應(yīng)急救援組織機(jī)構(gòu)及職責(zé)........................................................................68
14.4預(yù)防疫情防控措施................................................................................................71
14.5監(jiān)測(cè)與預(yù)警............................................................................................................73
14.6應(yīng)急響應(yīng)................................................................................................................75
14.7后期處置................................................................................................................76
14.8應(yīng)急保障................................................................................................................76
附件..........................................................................................................................................77
附件一爆破施工的平面位置.......................................................................................77
IV
第一章編制依據(jù)
表1規(guī)范及文件
序
類別文件名稱編號(hào)
號(hào)
1中華人民共和國(guó)安全生產(chǎn)法/
2中華人民共和國(guó)環(huán)境保護(hù)法/
3建設(shè)工程質(zhì)量管理?xiàng)l例/
4中華人民共和國(guó)環(huán)境噪聲污染防治法/
國(guó)家行
5政文件民用爆炸物品安全管理?xiàng)l例/
6建設(shè)工程安全生產(chǎn)管理?xiàng)l例/
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施《危險(xiǎn)性較大的
7建辦質(zhì)〔2018〕31號(hào)
分部分項(xiàng)工程安全管理規(guī)定》有關(guān)問題的通知
8危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定住建部令第37號(hào)
9爆破安全規(guī)程GB6722-2014
10鐵路路基工程施工安全技術(shù)規(guī)程TB10302-2023
11鐵路路基工程施工機(jī)械配置技術(shù)規(guī)程Q/CR9224-2015
國(guó)家行
12鐵路工程基本作業(yè)施工安全技術(shù)規(guī)程TB10301-2023
業(yè)規(guī)范
13鐵路路基工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)TB10414-2018
14爆破作業(yè)單位資質(zhì)條件和管理要求GA990—2012
15爆破作業(yè)項(xiàng)目管理要求GA991—2012
16設(shè)計(jì)DK8+300-DK11+400區(qū)間路基設(shè)計(jì)圖/
17圖紙不銹鋼園區(qū)站設(shè)計(jì)圖/
企業(yè)管
18線性基礎(chǔ)設(shè)施項(xiàng)目機(jī)構(gòu)設(shè)置及人員配置指引局基字[2018]438號(hào)
理文件
19類似項(xiàng)目的施工經(jīng)驗(yàn)
其他
20工程爆破實(shí)用手冊(cè)
第二章工程概況
2.1工程概述
本項(xiàng)目為新建臨沂臨港疏港鐵路工程主線自坪嵐鐵路碑廓站南側(cè)鐵牛廟端咽喉引
出,并行坪嵐鐵路向西走行,下穿疏港大道后于西辛興村西北側(cè)折向南,上跨G518國(guó)
道、繡針河后沿廬山路東側(cè)向南走行,先后上跨疏港東路、規(guī)劃改移疏港大道,于唐家
1
村西側(cè)折向西上跨廬山路及黃海四路,隨后線路沿黃海四路南側(cè)向西前行,于DK7+280
處設(shè)特鋼園區(qū)站。出站后線路繼續(xù)向西,于李家村西北側(cè)折向西南,終至不銹鋼園區(qū)站。
新建線路長(zhǎng)度12.95km。
該項(xiàng)目新建鐵路等級(jí)為I級(jí),單線運(yùn)行,設(shè)計(jì)行車速度60km/h。爆破施工位于特鋼
園區(qū)站至不銹鋼園區(qū)站段,此段路基為路塹,在進(jìn)行土石方開挖時(shí),需配合爆破施工,
樁號(hào)為DK8+400~DK12+886.99,最深處開挖37.46米。爆破施工的平面位置見附圖一。
圖2.1爆破施工縱斷面
2.2地形地貌、地質(zhì)條件
25.1~101.6m,相對(duì)高差76.5m,該區(qū)特點(diǎn)為丘低坡緩,溝寬谷闊,起伏如波。河、
塘零星分布。道路通達(dá),交通便利。爆破區(qū)沿線路縱向分布。
(1)地質(zhì)巖性:
二長(zhǎng)花崗巖(ηο53(1)a):黃褐色、灰綠色、青灰色,全段廣泛分布、全風(fēng)化帶
(W4),σ0=250kpa,γ=19.5KN/m3,φ=25°,f=0.4,厚約0~8m,屬Ⅲ級(jí)硬土,C組
填料;強(qiáng)風(fēng)化帶(W3),σ0=350kpa,γ=23KN/m3,φ=40°,f=0.45,厚15~17m,屬Ⅳ
級(jí)軟石,B組填料;弱風(fēng)化帶(W2)σ0=1000kpa,γ=24.5KN/m3,φ=50°,f=0.55,
屬Ⅴ級(jí)次堅(jiān)石,A組填料。
(2)氣象水文
本區(qū)屬暖溫帶季風(fēng)區(qū)半濕潤(rùn)大陸性氣候。氣候總特征是:春季溫暖,干燥多風(fēng);夏
季濕熱,雨量充沛;秋季涼爽,晝夜溫差大;冬季寒冷,雨雪稀少。四季分明,光照充
足,無霜期長(zhǎng)。常年最熱月為7月和8月,平均氣溫為25.5℃,年際變動(dòng)在28.2~23.3℃
2
之間,極端最高氣溫為38.9℃(1988年7月8日);常年最冷月為1月,平均氣溫為-
1.9℃,年際變動(dòng)在-4.6~0.3℃之間。極端最低氣溫為-19.2℃(1969年2月5日)。歷年
降水量的地區(qū)分布中間少,東西多,由東西部向中間遞減。多年平均降水量最多的地區(qū)
為東部朱蘆一帶(898.0mm),最少為北部陡山一帶(773.9mm)。各月平均日照時(shí)數(shù)以
5、6月份最多,分別為244.1小時(shí)和222.0小時(shí)。最少是2月和7月,分別為173.7小
時(shí)和181.4小時(shí)。土壤最大凍結(jié)深度為0.50m。
(3)地震動(dòng)參數(shù)
依據(jù)《中國(guó)地震動(dòng)參數(shù)區(qū)劃圖》(GB18306-2015),擬建工程場(chǎng)地地震動(dòng)峰值加速度
為0.10~0.15g,地震動(dòng)反應(yīng)譜特征周期為0.45s。
2.3周圍環(huán)境條件
該爆破工程施工線路全段基本平行于黃海四路,東部爆破作業(yè)區(qū)域路段距離個(gè)別村
莊民房較近,西部爆破作業(yè)區(qū)域路段穿過大山路終至不銹鋼園區(qū)內(nèi),沿線南側(cè)有民房,
北側(cè)距離黃海四路約200米,其余路段沿線的民房、廠房、養(yǎng)殖大棚和圍墻等在爆破施
工前由政府部門協(xié)調(diào)全部拆除。爆破區(qū)域周圍1000米內(nèi)無國(guó)家級(jí)文物和極重要保護(hù)設(shè)
施,500米內(nèi)無省級(jí)文物和重要保護(hù)設(shè)施等。縱觀整個(gè)線路段,爆破區(qū)域地形簡(jiǎn)單,視
野開闊,爆區(qū)環(huán)境優(yōu)良。管線穿過線路調(diào)查情況:地理通訊6條,高壓線3條,奧德燃
氣管道2條。
表2.3爆破區(qū)四鄰距離表
方位地面、地下或空中距離(m)保護(hù)對(duì)象
北地面200黃海四路
東地面施工現(xiàn)場(chǎng)
南地面100民房
西地面施工場(chǎng)地
2.4施工任務(wù)及要求
施工任務(wù):對(duì)工程設(shè)計(jì)爆破區(qū)域內(nèi)的巖石實(shí)施爆破。
(1)質(zhì)量要求:爆破后巖石塊度應(yīng)滿足機(jī)械破碎清運(yùn)要求,爆破、清運(yùn)后路基標(biāo)高、
寬度、邊坡坡度等應(yīng)滿足工程技術(shù)設(shè)計(jì)要求。
(2)工期要求:爆破工程應(yīng)在規(guī)定的工期內(nèi)完成。
3
(3)安全要求:爆破產(chǎn)生的爆破振動(dòng)、飛石等危害不得對(duì)周邊建筑物及地下設(shè)施造
成影響,爆破施工確保周邊作業(yè)人員及機(jī)械設(shè)備安全。
2.5主要工程數(shù)量
表2.5主要工程數(shù)量表
工程量
序號(hào)項(xiàng)目名稱單位
單項(xiàng)合計(jì)
1挖土方m3824241
3441575
2路基主體挖石方m32617334
3基床加固m353905.853905.8
第三章施工安排
3.1現(xiàn)場(chǎng)管理組織
為完成爆破施工任務(wù),加強(qiáng)項(xiàng)目施工標(biāo)準(zhǔn)化管理,確保工程建設(shè)工期、質(zhì)量、安全
目標(biāo),項(xiàng)目部組建管理路基土石方爆破施工的三工區(qū),路基土石方爆破施工由生產(chǎn)經(jīng)理
劉長(zhǎng)喜負(fù)責(zé),技術(shù)由總工孫彥龍負(fù)責(zé),由計(jì)劃合同部、工程技術(shù)部、安全監(jiān)督管理部、
質(zhì)量管理部、財(cái)務(wù)資金部、物資設(shè)備部、征地拆遷部、綜合辦公室、測(cè)量部、試驗(yàn)室共
10個(gè)職能部室配合,現(xiàn)場(chǎng)管理由孫向東負(fù)責(zé);現(xiàn)場(chǎng)組織機(jī)構(gòu)框圖見下圖:
4
項(xiàng)目經(jīng)理
項(xiàng)目副經(jīng)理項(xiàng)目副經(jīng)理
總工程師商務(wù)經(jīng)理
(分管生產(chǎn))(分管安全質(zhì)量)
安
工計(jì)全質(zhì)工物綜征財(cái)
程劃監(jiān)量地資合拆務(wù)測(cè)
技合督管試設(shè)辦協(xié)資量
術(shù)同管理驗(yàn)備公調(diào)金部
部部理部室部室部部
部
三工區(qū)
爆破架子隊(duì)
圖3.1現(xiàn)場(chǎng)管理組織機(jī)構(gòu)
表3.1主要崗位職責(zé)分工
序號(hào)主要崗位職責(zé)和權(quán)限
1)負(fù)責(zé)項(xiàng)目施工、竣工驗(yàn)收、試運(yùn)行和保修等階段的組織實(shí)施、指
揮和管理工作。
1項(xiàng)目經(jīng)理
2)建立完善的項(xiàng)目運(yùn)行管理體系,制定項(xiàng)目管理各項(xiàng)辦法和規(guī)章制
度,負(fù)責(zé)總承包項(xiàng)目經(jīng)理部的各項(xiàng)管理工作。
1)指揮爆破施工按計(jì)劃進(jìn)行。
2)領(lǐng)導(dǎo)、協(xié)調(diào)施工中各項(xiàng)工作和各職能組的工作。
2生產(chǎn)經(jīng)理
3)在爆破過程中,發(fā)出起爆和解除命令。
4)處理影響全局的工作。
1)組織項(xiàng)目技術(shù)人員進(jìn)行工程圖紙會(huì)審、技術(shù)核定工作。牽頭編制
施工技術(shù)方案,監(jiān)督施工技術(shù)方案執(zhí)行情況并根據(jù)工程實(shí)際情況進(jìn)
3總工程師行相應(yīng)調(diào)整和補(bǔ)充。
2)編制項(xiàng)目總進(jìn)度計(jì)劃,并進(jìn)行分析、跟蹤、控制,負(fù)責(zé)總承包合
同、分包合同實(shí)施全過程的進(jìn)度、費(fèi)用、質(zhì)量管理與控制。
4商務(wù)經(jīng)理1)參與圖紙會(huì)審,做到對(duì)設(shè)計(jì)文件、圖紙、資料、規(guī)范、標(biāo)準(zhǔn)透徹
5
序號(hào)主要崗位職責(zé)和權(quán)限
了解,提出會(huì)審建議。
2)參與項(xiàng)目施工組織設(shè)計(jì)和施工方案的編制,及時(shí)組織分包月報(bào)量
的審核審批,督導(dǎo)進(jìn)行分包經(jīng)濟(jì)簽證月清月結(jié)。
3)協(xié)助領(lǐng)導(dǎo)簽訂內(nèi)外分包施工合同,協(xié)助項(xiàng)目經(jīng)理進(jìn)行勞動(dòng)力管
理。
1)負(fù)責(zé)對(duì)附近村民、工廠發(fā)布爆破公告,公告內(nèi)容包括:爆破地
點(diǎn)、爆破時(shí)間、爆破次數(shù)、警戒范圍、警戒標(biāo)志、各種信號(hào)及其意
義,以及發(fā)出信號(hào)的方式、時(shí)間、安全措施等有關(guān)注意事故。
2)在爆破作業(yè)地段,負(fù)責(zé)設(shè)置明確的工作范圍標(biāo)志,并安排警戒人
員。在鄰近交通要道和人行通道的方位或地段設(shè)置防護(hù)屏障。
5安全總監(jiān)3)做好爆前周邊人員的疏散、車輛及設(shè)備的擅離工作,爆破前15分
鐘,確保爆破危險(xiǎn)區(qū)域內(nèi)無人及車輛,警戒人員至少在起爆前半小
時(shí)到指定地點(diǎn)上崗,按設(shè)計(jì)斷絕各通往或經(jīng)過爆破點(diǎn)的通道,直至
發(fā)出解除警戒信號(hào)后,方準(zhǔn)離開警戒崗位。
4)爆破時(shí),必須同時(shí)發(fā)出聲響信號(hào)和視覺信號(hào),使危險(xiǎn)區(qū)內(nèi)的人員
都能清楚地聽到和看到。
1)全面負(fù)責(zé)項(xiàng)目質(zhì)量管理工作。
2)負(fù)責(zé)日常巡查、質(zhì)量會(huì)議(質(zhì)量周檢)。
6質(zhì)量總監(jiān)
3)負(fù)責(zé)將質(zhì)量目標(biāo)、質(zhì)量保證措施向?qū)I(yè)工程師交底和培訓(xùn)。
4)負(fù)責(zé)創(chuàng)優(yōu)工程策劃書的編制及落實(shí)。
1)按安全規(guī)程要求負(fù)責(zé)施工安全,制止違章作業(yè)。
爆破架子隊(duì)2)組織對(duì)爆破器材的加工、試驗(yàn)、檢驗(yàn)。
7
隊(duì)長(zhǎng)3)負(fù)責(zé)裝藥、連線、堵塞、起爆及爆破質(zhì)量驗(yàn)收。
4)負(fù)責(zé)對(duì)拒炮、盲爆的處理。
3.2現(xiàn)場(chǎng)管理目標(biāo)
表3.2現(xiàn)場(chǎng)管理目標(biāo)
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
工期2023年9月20日至2023年1月31日全竣工,總工期134天。
檢驗(yàn)批、分項(xiàng)、分部工程質(zhì)量檢驗(yàn)合格率100%,單位工程一次驗(yàn)
質(zhì)量目標(biāo)
收合格率100%。
安全目標(biāo)項(xiàng)目實(shí)施中無安全責(zé)任事故發(fā)生。
環(huán)保施工、CI目標(biāo)無較大及以上環(huán)境事件發(fā)生。
第四章施工進(jìn)度計(jì)劃
根據(jù)項(xiàng)目施工計(jì)劃安排,計(jì)劃2023年9月20日至2023年1月31日全竣工,總工
期134天。
6
表4工期安排
序
施工項(xiàng)目開始時(shí)間完成時(shí)間
號(hào)
1DK8+400~DK11+400爆破施工2023.9.202023.1.31
2DK11+400~DK12+886.99爆破施工2023.9.202023.11.18
第五章施工準(zhǔn)備與資源配置計(jì)劃
5.1技術(shù)準(zhǔn)備
在開工前及時(shí)收集各種技術(shù)資料,包括工程地質(zhì)資料、施工圖、工程量清單、材料
工本分析或成本分析等前期準(zhǔn)備工作。
(1)施工前應(yīng)組織施工人員對(duì)設(shè)計(jì)文件、圖紙、資料認(rèn)真進(jìn)行熟悉,查對(duì)是否齊全、
有無遺漏、差錯(cuò)或相互之間有無矛盾之處,發(fā)現(xiàn)差錯(cuò)應(yīng)及時(shí)向設(shè)計(jì)單位提出補(bǔ)齊或更正,
并作出記錄。
(2)在研究設(shè)計(jì)圖紙、資料過程中,需與現(xiàn)場(chǎng)實(shí)際情況核對(duì),并在必要時(shí)進(jìn)行補(bǔ)充
調(diào)查,以利作好準(zhǔn)備。
(3)摸清原有地下管線及地上構(gòu)造物情況,便于施工時(shí)采取保護(hù)措施,避免發(fā)生意
外事故。
(4)施工前應(yīng)對(duì)測(cè)量?jī)x器如水準(zhǔn)儀、全站儀、鋼尺進(jìn)行校核。
(5)專項(xiàng)方案經(jīng)公司審核、監(jiān)理單位、建設(shè)單位審查通過后組織專家論證,論證通
過后的方案及時(shí)報(bào)公司二次審批,監(jiān)理單位、建設(shè)單位審批通過后,由本方案編制人員
對(duì)相關(guān)專業(yè)工程師進(jìn)行方案交底。專業(yè)工程師根據(jù)方案交底內(nèi)容在施工前組織現(xiàn)場(chǎng)作業(yè)
人員進(jìn)行技術(shù)交底,明確質(zhì)量、安全保證措施。
5.1技術(shù)文件準(zhǔn)備計(jì)劃
序號(hào)文件名稱文件編號(hào)配備數(shù)量備注
1爆破安全規(guī)程GB6722-20142
2爆破作業(yè)單位資質(zhì)條件和管理要求GA990—20122
3爆破作業(yè)項(xiàng)目管理要求GA991—20122
4工程爆破實(shí)用手冊(cè)/1
7
5.2施工現(xiàn)場(chǎng)準(zhǔn)備
(1)進(jìn)入施工現(xiàn)場(chǎng)的人員必須佩戴安全帽和上崗證,現(xiàn)場(chǎng)管理人員和作業(yè)人員的安
全帽應(yīng)區(qū)分,勞動(dòng)保護(hù)用品穿戴齊全,安全監(jiān)察人員佩戴袖標(biāo)(牌)。
(2)所用大型機(jī)械施工現(xiàn)場(chǎng)必須嚴(yán)格執(zhí)行一機(jī)一人專職防護(hù),做到“五個(gè)一”,即:
一機(jī)、一人(專職防護(hù))、一本(機(jī)械施工日志)、一牌(設(shè)備標(biāo)識(shí)牌)、一證(機(jī)械操作證)。
每臺(tái)機(jī)械都必須懸掛機(jī)械設(shè)備標(biāo)識(shí)牌。
(3)施工現(xiàn)場(chǎng)布置“五牌一圖”及各類標(biāo)示牌、警示牌。
(4)清理施工現(xiàn)場(chǎng),拆除有礙爆破施工的廢舊建筑物,修筑進(jìn)出爆破區(qū)的簡(jiǎn)易道路
和便道,便于人員、機(jī)械的進(jìn)出。
(5)規(guī)劃施工機(jī)械、車輛和爆破器材臨時(shí)存放、安全警戒哨、起爆站位置,施工現(xiàn)
場(chǎng)防洪與排水措施。
(6)建立通訊聯(lián)絡(luò),爆破施工現(xiàn)場(chǎng)、起爆站、警戒哨應(yīng)建立并保持通訊聯(lián)絡(luò),通訊
聯(lián)絡(luò)可使用移動(dòng)電話或?qū)?duì)講機(jī)。
(7)爆破施工前對(duì)周邊道路及民房進(jìn)行調(diào)查取證及采集影像資料等工作,避免后期
引發(fā)索賠事件。
(8)爆破施工與爆破公告
①公告發(fā)布時(shí)間:爆破施工公告在施工前3前發(fā)布,爆破公告在爆破前1天發(fā)布;
②爆破施工公告內(nèi)容
爆破項(xiàng)目名稱:臨沂臨港疏港鐵路工程爆破施工
委托單位:中國(guó)建筑第x工程局有限公司新建臨沂臨港疏港鐵路工程項(xiàng)目經(jīng)理部
設(shè)計(jì)施工單位:中國(guó)建筑第x工程局第一建設(shè)有限公司
安全評(píng)估單位:中鐵十四局集團(tuán)
安全監(jiān)理單位:長(zhǎng)城爆破公司
爆破作業(yè)時(shí)限:2023年8月20日至2023年12月31日
③爆破公告內(nèi)容
爆破地點(diǎn):按現(xiàn)場(chǎng)實(shí)際位置填寫
每次爆破時(shí)間:路基:8:00—18:00
安全警戒范圍:爆區(qū)周圍200米范圍內(nèi)
8
安全警戒標(biāo)志:警戒標(biāo)志牌、繩
起爆信號(hào):用手搖式警報(bào)器發(fā)送信號(hào)
警戒聯(lián)絡(luò)信號(hào):使用對(duì)講機(jī)聯(lián)絡(luò)
5.3資源配置計(jì)劃
設(shè)備配備
為保證工程施工連續(xù)、順利,上下工序互不干擾,在前期準(zhǔn)備時(shí),必須按擬定的生
產(chǎn)規(guī)模投入相應(yīng)的設(shè)備。設(shè)備生產(chǎn)能力的高低,直接關(guān)系到工程的進(jìn)度,照爆破施工施
工進(jìn)度推算,需配備如表所示機(jī)械設(shè)備。
表5.3.1機(jī)械設(shè)備配置
序號(hào)設(shè)備名稱規(guī)格數(shù)量備注
1潛孔鉆KS9016臺(tái)狀況完好
DY90-148臺(tái)
2紅五環(huán)空壓機(jī)狀況完好
HV-0.22/88臺(tái)
3發(fā)電機(jī)150KW8臺(tái)狀況完好
4挖掘機(jī)(破碎錘)卡特3203臺(tái)狀況完好
5霧炮WPJ0110臺(tái)狀況完好
6灑水車CSC60702輛狀況完好
人員配備
工程要?jiǎng)?chuàng)效,必須以安全生產(chǎn)作保障。因此,在日常生產(chǎn)工作中,必須成立以負(fù)責(zé)
人為第一責(zé)任人的安全生產(chǎn)管理小組,肩負(fù)起日常的一切安全生產(chǎn)及現(xiàn)場(chǎng)管理工作任務(wù),
立足現(xiàn)場(chǎng),消除隱患,避免發(fā)生人身及設(shè)備事故,確保工程零事故,爆破施工人員持證
情況見表-1所示,人員配備情況見表5.3.2-2所示。
表-1爆破施工人員持證情況
姓名擬任崗位年齡性別專業(yè)學(xué)歷職稱上崗證書備注
爆破中級(jí)技
劉長(zhǎng)喜爆破負(fù)責(zé)人52男本科高級(jí)工程師
術(shù)人員
爆破中級(jí)技
金昌利爆破負(fù)責(zé)人47男本科工程師
術(shù)人員
爆破作業(yè)人
王殿江爆破員29男本科
員許可證
9
姓名擬任崗位年齡性別專業(yè)學(xué)歷職稱上崗證書備注
爆破作業(yè)人
曹甲佳爆破員29男本科
員許可證
爆破作業(yè)人
劉凱爆破員30男本科
員許可證
爆破作業(yè)人
楊恒安全員27男本科
員許可證
爆破作業(yè)人
王帥安全員27男???/p>
員許可證
爆破作業(yè)人
宋海民保管員25男???/p>
員許可證
爆破作業(yè)人
李凱保管員26男專科
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 保安班長(zhǎng)述職報(bào)告7篇
- 酒店經(jīng)理辭職報(bào)告15篇
- 常壓儲(chǔ)罐應(yīng)會(huì)復(fù)習(xí)試題及答案(一)
- 《平凡的世界》簡(jiǎn)短閱讀體會(huì)與心得五篇
- xx區(qū)云計(jì)算項(xiàng)目可行性研究報(bào)告
- 物業(yè)經(jīng)理個(gè)人工作總結(jié)范本
- 2024年度跨境電商質(zhì)押借款合同范本3篇
- 2024年度醫(yī)院臨床實(shí)驗(yàn)項(xiàng)目合作協(xié)議范本3篇
- 智能云家居課課程設(shè)計(jì)
- 長(zhǎng)距離供熱管道項(xiàng)目可行性研究報(bào)告
- 2024年時(shí)事政治試題【有答案】
- 2024年認(rèn)證行業(yè)法律法規(guī)及認(rèn)證基礎(chǔ)知識(shí)
- 促銷活動(dòng)方案(共29頁(yè)).ppt
- 自動(dòng)打印機(jī)機(jī)械原理課程設(shè)計(jì)
- 培訓(xùn)準(zhǔn)備工作清單
- 沉井工程檢驗(yàn)批全套【精選文檔】
- 貝類增養(yǎng)殖考試資料
- 旅游專業(yè)旅游概論試題有答案
- 混凝土熱工計(jì)算步驟及公式
- 病理生理學(xué)試題及復(fù)習(xí)資料
- 國(guó)電南自遠(yuǎn)動(dòng)服務(wù)器作業(yè)指導(dǎo)書1介紹
評(píng)論
0/150
提交評(píng)論